Judges: WalKeb
Filed Date: 11/5/1908
Status: Precedential
Modified Date: 10/19/2024
PLAINTIFF'S APPEAL.
The plaintiff alleged that, on 4 January, 1902, he had entered into a contract with the defendant to log certain timber lands owned by it, the defendant to furnish the necessary equipment, to provide for the means for performing the contract, which were to be charged to the plaintiff, who was credited each month with the logs delivered by him. Statements were furnished each month showing the balance due. The plaintiff further alleged that the land was well timbered and the contract, if performed, would have enabled him to realize a profit of $100,000. There were allegations as to the respective duties and obligations of the parties, and evidence to sustain the same. The essential facts are (11) stated in Hawk v. Lumber Co.,
The contract was, of course, unperformed at the time of the breach, and the evidence tended to show that it would have taken several years to complete the work under it. The breach occurred in November, 1903. The estimates as to the quantity of timber on the land varied considerably, the plaintiff's evidence tending to show that there were between 150,000,000 and 200,000,000 feet of timber and 20,000 acres of land, while the evidence of the defendant tended to show that there were only 5,000 acres and from 30,000,000 to 40,000,000 feet of timber.
The court permitted a witness, Benjamin Moore, over the objection of the plaintiff, made in apt time, to testify as follows: That "it would not have cost less than $4.50 or $5, at least, to log the land in 1904, 1905, 1906 and 1907, and that wages had increased since 1903 something like 50 per cent." Other witnesses were permitted to testify to the same facts. The plaintiff requested the court to charge the jury as follows: "If the jury shall find that the defendant wrongfully broke its contract with the plaintiff, he is entitled to have his damages assessed upon the conditions as they existed at the time of the breach, and they will not consider whether the expense of logging has increased since that time, or decreased, but will estimate his damages upon the conditions then existing, and the estimate should be based upon the present value of the contract at the time of the breach." This instruction was refused and the plaintiff excepted. The court charged the jury as follows: "1. The sixth issue is, what damage has the plaintiff sustained by reason of the wrongful breach of the contract? The burden of this issue is on the plaintiff. *Page 9 Should you answer the first, second and third issues ``Yes,' the plaintiff will be entitled to recover the difference between the contract price, which is agreed was three dollars per thousand feet, and the cost of cutting, hauling and loading the logs on the cars of the Norfolk Southern Railway Company at Croatan, of all the merchantable (12) timber that was left on the land at the date the plaintiff stopped work for the defendant company." Plaintiff excepted to this part of the charge.
"2. You must find the quantity of timber on the land that was embraced in the contract, the number of feet and the amount that it would cost the plaintiff to deliver said logs on board the cars of the Norfolk Southern Railway Company at Croatan, at the time or times said logs were to be delivered, under the terms of the contract. Should you find that it would cost three dollars per thousand feet or more, the plaintiff would not be entitled to recover any amount on account of said logs, for there would be no profit in it to him." The plaintiff excepted to each of these instructions.
The issues and the answers thereto were as follows:
1. Did plaintiff and defendant enter into the contract as alleged in the complaint? Answer: Yes.
2. Did the plaintiff perform the contract on his part as fully as he was permitted to do by defendant? Answer: Yes.
3. Did the defendant wrongfully break the contract and prevent the plaintiff from further performance thereof? Answer: Yes.
4. Did the defendant wrongfully convert the personal property of the plaintiff as alleged in the complaint? Answer: Yes.
5. What damage has plaintiff sustained by the wrongful conversion of his personal property? Answer: $1,359.
6. What damage has plaintiff sustained by the wrongful breach of the contract? Answer: $2,250 with interest on same.
7. Have the matters and things complained of been heretofore adjudicated as to the conversion of the personal property, as alleged in the answer? Answer: Yes.
8. Have the matters and things alleged in the complaint, other than the conversion of the personal property, been heretofore adjudicated, as alleged in the answer? Answer: No. (13)
The plaintiff moved for a new trial, which was refused, and judgment was entered upon the verdict. He then excepted and appealed.
We are of the opinion the judge erred in admitting the testimony of Benjamin Moore and other witnesses as to facts supervening the breach of the contract, that is, the cost of logging after the breach and the increase in the rate of wages, and also in refusing the plaintiff's prayer for instruction. This case, in respect to the damages recoverable for the breach of the contract is governed by Wilkinson v.Dunbar, post, 20. We held there that, while the entire damage must be assessed, present and prospective, the measure of damages is the value of the contract at the time of the breach. Justice Hoke, for the Court, says in that case: "There was evidence offered tending to show that this contract would have required some years in its performance beyond the time when a breach was established, and, as to this prospective damage, that to arise in the time required for performance after such breach, the correct rule would be the present value of the difference between the contract price and the cost of performance. We hold, as stated, that recovery for this prospective damage can be had, but defendant is only entitled to the present value of his contract, and, in so far as such damage is allowed by anticipation, proper allowance should be made for the fact that present recovery is had for damage that would only have accrued at a future time. This position as to the correct rule for determining values to arise and accrue in the future, when a present recovery is allowable, is very well illustrated in Pickett v. R. R.,
The language of Chief Justice Nelson (afterwards a justice of the Supreme Court of the United States) is especially applicable to our case. He says: "Where the contract, as in this case, is broken before the arrival of the time for full performance, and the opposite party elects to consider it in that light, the market price on that day of the breach is to govern in the assessment of damages. In other words, the damages are to be settled and ascertained according to the existing state of the market at the time the cause of action arose, and not at the time fixed for full performance. The basis upon which to estimate the damages, therefore, *Page 11 is just as fixed and easily ascertained in cases like the present, as in actions predicated upon a failure to perform at the day."
The concurring opinion of Bronson, J., is equally as strong and explicit in stating the same principle. The rule, as now formulated by this Court, and governing in such cases as this one, is well supported, not only byMasterton v. Mayor, supra, but by the other cases which will be found in the learned and forceful opinion of Justice Hoke. We need not refer to them seriatim and make special comment upon the reasons assigned therein for the conclusion reached by the Courts (15) of Alabama, Iowa, Wisconsin and Illinois, and by this Court in Oldham v. Kerchner,
We think that, under the peculiar circumstances of this case, the new trial, which we award, should extend to all the issues, for the reason, among others which are controlling, that the facts of the case may be more fully developed and the questions intended to be presented, *Page 12
more clearly presented. To do otherwise might result in injustice to one or both of the parties. We grant the new trial generally in the exercise of the discretion which belongs to this court, as has been so often decided.Burton v. R. R.,
Let there be a new trial as to all the issues.
New trial.
Cited: Wilkinson v. Dunbar, post, 26; Dixon v. Grand Lodge,