DocketNumber: No. 8530SC1141
Judges: Arnold, Eagles, Phillips
Filed Date: 12/30/1986
Status: Precedential
Modified Date: 11/11/2024
Plaintiffs only contention in regard to the order granting a new trial — that the motion which gave rise to it was not timely filed — has no foundation and we overrule it. Defendant’s motion for a new trial, made under Rule 59, N.C. Rules of Civil Procedure, was served on 28 December 1984 and section (b) of that rule provides that motions made thereunder “shall be served not later than 10 days after entry of the judgment.” The contention that the motion came too late is based upon the premise that judgment was entered on 12 December 1984, but the record does not show that judgment was entered on 12 December 1984 or at any other time for that matter. What was entered on 12 December 1984 was the jury verdict, which is not mentioned in the provision limiting the time within which motions for a new trial can be made.
The verdict directed against plaintiff at the conclusion of his evidence in the second trial was on the stated ground that his evidence was insufficient to establish either that defendant was negligent or that its negligence was a proximate cause of plaintiffs injury. The validity of this ruling depends upon whether plaintiffs evidence when viewed in its most favorable light tends to show that the two anchor bolts which held the steel column in place were defective and that their deficiency was a proximate cause of the column’s fall. For his evidence is plainly sufficient to establish that defendant was responsible for install
Pertinent to the question presented the record shows the following preliminary or background facts: It was a one-story steel supported building in the early stages of construction. Some days earlier, just when is immaterial, the defendant general contractor had erected the outer masonry walls, had poured the concrete footings for the five steel columns that were to support the roof beams and had installed anchor bolts for the columns in the footings. Two anchor bolts, parallel to each other, were installed for each column and each anchor bolt except for the top 2 or 3 inches was embedded in the concrete footing. On the day of the accident and immediately before it happened plaintiff and other experienced members of the steel erection crew had erected two of the five steel columns and had affixed steel I-beams to the top of each column. The I-beams were the horizontal support for the roof, and each beam was about 30 feet long and weighed about 1,500 pounds. Each column was a 5 inch steel pipe, approximately 18 feet high with a 6 inch by 8 inch steel base plate. In erecting each column the following procedure was followed: A leveling nut and washer was run down on each anchor bolt to the level of the concrete floor that would be poured later; with the aid of a crane the column with its protruding base plate was set on the nuts; and after another washer and nut was put on the bolt and tightened down the crane was removed and the column was left standing with no other support. After the first column was set an I-beam was affixed to it and the wall as follows: While the I-beam was held up by a crane plaintiff, sitting or standing on the beam when necessary, first bolted one end of the beam to the top of the column and then welded the other end onto a steel bearing plate fastened into the building’s outer wall, after which the crane was released without incident. Then the second column was erected and an I-beam was bolted to it and welded to the wall bearing plate as before; when the crane was removed from the second beam plaintiff, as he usually did, was sitting on the beam waiting for another beam to be delivered, but as the crane detached from the beam the second column began wavering and then fell over.
When repetition is eliminated plaintiffs other evidence relating to the anchor bolts and the fall of the column consists only of the following: Plaintiff testified that: The building plans
The foregoing is at least some evidence that the anchor bolts defendant installed for the fallen column were defective; for the
Affirmed.