DocketNumber: No. 17,989
Judges: Barnes, Hamer, Letton
Filed Date: 1/2/1915
Status: Precedential
Modified Date: 11/12/2024
Action for personal injuries. Plaintiff recovered, and defendant appeals. The plaintiff was a teamster in the employment of defendant, which is. a draying company. At the time of the accident he was about 24 years old. He had worked for defendant for about four months and was earning |47.50 a month. On the day of the accident the defendant ivas engaged in unloading and delivering two large steam boilers, each six feet in diameter, eight feet long, and weighing about eight tons. Each boiler was upon a separate flat-car. These boilers were unloaded by placing skids so as to form an inclined plane upon one side. An unloading apparatus was then made by making a chain loop around the rail of a side-track, on the other side of the flat-car and parallel thereto, fastening a rope to the chain, thence passing the rope twice around each end of the boiler, bringing the rope back to the chain, where a rope loop was made through which the rope was passed and then wrapped a number of times around the ropes leading to the boiler, at right angles; the free end was then held by a man at right angles to the line, so that when the boiler started to roll down the skids the friction of the wrapped ropes upon the ropes leading to the boiler acted as a brake, and the man holding the end could gradually pay out the rope, and thus control the movement of the boiler down the skids. The first boiler had been unloaded safely in this manner. The testimony shows that' this is the usual and customary method of unloading-articles of this nature among those engaged in the busi
The particular acts of negligence charged in the petition are that, instead of following the plan used in lowering the first boiler, the defendant changed the manner of placing the ropes about the boiler, and, instead of using two ropes, carelessly and negligently used only one rope for that purpose; that, instead of taking the loose end of the rope in a half hitch around a stable and solid object and wrapping or entwining it about the other portion of the rope in order to give the one holding it greater purchase and holding power defendant carelessly and negligently failed so to do, and carelessly directed the plaintiff to take hold of the rope and permit it to loosen gradually so as to lower the boiler, and that, because of the careless and. dangerous way in which the rope had been placed by defendant, when the weight of the boiler came upon it, it failed to hold, and the plaintiff’s arm became entangled. The defendant, pleads assumption of risk and contributory negligence.
The evidence is clear that, in order to secure sufficient friction to lower such a boiler safely, it is essential that.
The first assignment is that the court erred in overruling defendant’s challenge to the juror Armstrong. Section 8158, Rev. St. 1913, provides that it shall be sufficient cause for the challenge of a juror, “that he is a party to a suit pending for trial in that court, at that term.” The evidence shows that Mr. Armstrong was a member of the board of trustees of the village of Bethany, and that a summons was served upon him as such officer in an action in equity brought by certain individuals to disconnect territory from the village. The case was tried to the court and determined in October, 1912. The present action was tried in December, 1912, at the same term. Under the statute, Mr. Armstrong had not been selected as a juror .and did not sit in October. Mr. Armstrong’s name did not appear as a party to the suit and he had no personal interest in it. There are two reasons why this assignment
It is urged that the juror had consulted with Mr. Strode, •counsel for the village, who is one of the attorneys for the plaintiff. "This, however, while it might justify defendant in using a peremptory challenge in order to remove the juror, is not a ground to excuse a juror for cause under the statute.
It is next contended that the evidence is insufficient to ■sustain the verdict. We have already stated the substance •of the proof. It is said, however, that all the witnesses .said the rope was wrapped around twice and that this must be true, otherwise the boiler could not have been stopped when it started to roll. The evidence shows that the plaintiff’s arm held the rope from going through the loop. This stopped that end of the boiler. Two men were holding the rope at the other end and apparently stopped
It is next assigned that the court erred in allowing the-attorney for plaintiff to appeal to the prejudice of the jury by refenfing to plaintiff’s family and his property. The-remark of counsel to which the first objection was taken is only in the record by inference from the objection,'but' the- court sustained the objection. The jury should also-have been told to ignore the statement.
The record also shows that counsel said: “Which will you do, let the Sullivan-Schaberg company go without paying anything, or make a pauper out of him, with these debts on his hands, without giving him anything?” This was objected to and the objection overruled. The question at issue was not whether the plaintiff was or would become a pauper, but it was whether the defendant had been guilty of actionable negligence. But we cannot say that the remark itself excited the passions or prejudices of the jury. The record showed that the plaintiff was a laboring man receiving $47.50 a month; that the accident had prevented'
It is next assigned that the court erred in allowing a temporary model to be used in the district court. The same model was used in the argument .before this court and no serious complaint was made. It assisted us to obtain an idea of the manner in which the ropes were used, and we find no error in allowing its use.
It is next insisted that the verdict was excessive. The evidence shows that both bones of the plaintiff’s arm were broken near the wrist; that the flesh and tissues were so torn and cut that only a strip of flesh and skin was left by which the hand remained attached to the arm; that he was six weeks at the hospital the first time, but after going home the wound was dressed every other day for a month. He then returned to the hospital for a second operation. He remained there for three or four weeks. After this the wound was again dressed at his home for about a month. He was compelled to go to the hospital a third time for another operation, where he stayed three, or four weeks. After that still another operation had to be performed to withdraw some wires which had been used to hold the bones of his arm together. It is also shown that he suffered pain for more than a year; that he has no control over his first finger and that the left arm is about two inches shorter than the right. The evidence shows that the surgical and hospital charges are over $750. The jury rendered a verdict for $7,526. The'district court required a remittitur of $2,500, which was made, so that the ques
The plaintiff endured great pain and suffered permanent injury. Considering the loss of wages during the time that he was entirely incapacitated and the surgical and hospital expenses, there is left as compensation for his suffering, for the shortening of his arm, and for the loss of the use of the first finger about $3,500. We do not consider this excessive.
The judgment of the district court is
Affirmed.