By the Court,
The district court entered summary judgment against appellants Charlie Brown Construction Company, Inc. (Brown) and Delta Electric Company, Inc. (Delta), subcontractors on a subdivision project approved by respondent City of Boulder City (City) on six grounds. Two of the grounds consisted of a statutory construction favoring the City and a determination that the City was not unjustly enriched by the uncompensated labor and materials supplied by Brown and Delta for off-site improvements to the City’s property.
Summary judgment is proper when it appears that there is no genuine issue of material fact, and the moving party is entitled to a judgment as a matter of law. Wiltsie v. Baby Grand Corp., 105 Nev. 291, 774 P.2d 432, 433 (1989). The facts here are not disputed. Appellants assert three claims for relief: (1) that they were third-party beneficiaries of the agreement between the City and Boulder Development, Inc. (Boulder Development) and that the City wrongfully released Boulder Development’s cash deposit; (2) that the City was negligent in releasing funds deposited by the subdivider and in not requiring the subdivider to post a payment bond as mandated by City ordinance; and (3) that the City was unjustly enriched by the retention of and non-payment for their work.
Appellants’ second contention is meritorious. Because we discern merit in the negligence claim, we reverse the summary judgment granted in favor of the City.
Facts
The City approved a subdivision project submitted by the subdivider, Boulder Development. Brown and Delta entered into subcontracts with the general contractor for construction of the off-site improvements on the project. Brown and Delta completed
In approving the subdivision, the City required the subdivider to post a cash deposit in lieu of a bond to insure performance of the off-site construction, but it did not require the filing of a payment bond to insure payment to the subcontractors. The City subsequently accepted title to the off-site improvements and released the cash deposit. Brown and Delta, after exhausting all other possible avenues for payment, filed this suit against the City.
Third-Party Beneficiary Claims
The trial court correctly rejected the claim that appellants were third-party beneficiaries of the off-site improvement agreement between the City and Boulder Development. However, even if there were a third-party beneficiary theory upon which recovery could be based, it would afford no relief to appellants. Claims under a third-party beneficiary theory are necessarily contract claims. The presentment of claims requirement set out in NRS 268.020, as applied to contractual claims against municipalities, has been upheld by this court. L-M Architects, Inc. v. City of Sparks, 100 Nev. 334, 683 P.2d 11 (1984). There was no presentment to the Boulder City Council within the requisite six month time period and any contractually-based theories of recovery are therefore barred by the clear language of the statute. The district court correctly concluded that NRS 268.020 barred Brown and Delta’s claims on this theory.
We have previously invalidated Nevada’s statutory presentment restrictions upon a tort claimant’s ability to sue. Turner v. Staggs, 89 Nev. 230, 235-236, 510 P.2d 879, 883, cert. denied, 414 U.S. 1079 (1973). Therefore, any tort claims appellants have must be considered on their merits. Because appellants’ contract claims lack merit, we need not address them further.
Unjust Enrichment Claims
Having determined that Brown’s and Delta’s negligence claims are meritorious, we deem it unnecessary to address their claims based upon theories of unjust enrichment.
Brown and Delta contend that the City was negligent in either prematurely releasing the cash deposit or failing to obtain a payment bond on their behalf as required by Boulder City Municipal Code § ll-36-12(A) and ll-36-5(K)(l) and (L)(l). A negligence claim framed in this manner appears to be an issue of first impression in this jurisdiction. The issue is, what cause of action, if any, was created by the City’s failure to follow and enforce its own mandatory ordinance, the only apparent purpose of which was to protect subcontractors and enable them to obtain payment.
Boulder City Municipal Code § ll-36-12(A) provided:
(A) Performance Bond or Deposit: If any required improvements have not been completed to the satisfaction of the City Engineer prior to the City Council approval of the final map, the subdivider shall file with the City Clerk a faithful performance bond in the amount deemed sufficient by the City Engineer to cover the cost of said improvements, engineering and inspection fees. The subdivider shall also file a bond in an amount required by law on bonds for public construction, and by its terms insure labor and materials payment for labor performed and materials rendered under the terms of the improvement agreement. Such bond shall be executed by a surety company authorized to transact a surety business in the State of Nevada, and must be satisfactory to and be approved by the City Attorney as to form [emphasis added]. In lieu of said faithful performance bond, the subdivider may deposit cash with the City in the amount fixed, as aforementioned, by the City Engineer.
Boulder City Municipal Code § ll-36-5(K)(l) and (L)(l) provided:
(K) Documents Required Prior to Approval of Final Map: The following shall be filed with the Planning Director prior to the final map being presented for action to the City Council:
1. Improvement Agreement and Performance Bond: The subdivider shall execute and file with the Planning Director an agreement between himself and Boulder City, specifying the period within which he shall complete all improvements and work in accordance with City specifications and standards to the satisfaction of the City Engineer. The subdivider shall also file with the Planning Director at the same time, a performance*502 bond and a labor and material bond as required by Section 11-36-12 of this Chapter. Said improvement agreement and performance bond shall be approved as to form by the City Attorney.
(L) Action by City Council:
1. Within fifteen (15) days of the filing of the final map and other documents as required by this Chapter with the City Clerk, the City Council shall approve the map if it conforms with all applicable provisions of this Chapter and the Planning and Zoning Act of the State of Nevada. The time limit for approval of the map may be extended by mutual written consent of the City Council and the subdivider.
The successor provisions to these ordinances appear in a substantially similar form in BCMC § ll-39-12(A) and ll-39-5(L)(l) and (M). We see no merit in the negligent release of funds theory and decline to impose any liability on the City for its release of the performance deposit. However, the provisions of the ordinance which require a payment bond for labor and materials are clearly for the purpose of insuring payment to subcontractors who provide the labor and materials for the off-site improvements which ultimately inure to the ownership of the City.
Appellants correctly contend that BCMC § ll-36-12(A) required Boulder Development to file a payment bond covering labor and materials for the off-site improvements, and that the City was required to secure compliance with the provision before granting the necessary final map approval. Appellants contend that the City’s negligence in failing to require a payment bond directly and proximately resulted in Boulder Development never obtaining such a bond. Consequently, when Boulder Development became insolvent and appellants’ mechanics’ liens were eliminated by the trustee’s sale under the construction lender’s deed of trust, appellants were unable to collect the amounts due them. Appellants conclude that if the City had required a payment bond, appellants would have recovered the money owed them. We agree.
It is elementary that statutes, or in this case municipal enactments, must be construed as a whole and not be read in a way that would render words or phrases superfluous or make a provision nugatory. People of California v. Tahoe Regional Planning Agency, 766 F.2d 1308, 1314 (9th Cir. 1985); People v. Craft, 224 Cal.Rptr. 626, 629 (Cal. 1986). And, there is a presumption
Accordingly, this court has generally declined to use judicial construction to alter the meaning of clearly expressed enactments. In the case of In re Walter’s Estate, 60 Nev. 172, 183-84, 104 P.2d 968, 973 (1940), we held, quoting from State v. Jepsen, 46 Nev. 193, 196, 209 P. 501, 502 (1922):
Where the language of a statute is plain and unambiguous, and its meaning clear and unmistakable, there is no room for construction, and the courts are not permitted to search for its meaning beyond the statute itself [citations omitted].
The ordinance at issue here seems clear to us. It specifies that “[t]he subdivider shall also file a bond . . . and by its terms insure labor and materials payment for labor performed and materials rendered under the terms of the improvement agreement” (emphasis supplied). The same ordinance, after requiring the filing of a labor and materials bond, further emphasizes its importance by requiring the City Attorney to approve the bond as to form. Moreover, and more importantly, the ordinance does not permit necessary final map approval «without it having first been determined that the payment bond was filed as required. In pertinent part, the ordinance reads as follows:
1. Within fifteen (15) days of the filing of the final map and other documents as required by this Chapter with the City Clerk, the City Council shall approve the map if it conforms with all applicable provisions of this Chapter. . . .
A literal reading of BCMC ll-36-12(A) and ll-36-5(K)(l) and (L)(l) requires the City to obtain a payment bond (from a subdi-vider) for the protection of suppliers of labor and materials in an amount equal to bonds required by law for public construction.
In analyzing the intent of the City ordinance, it is clear that the City Council undertook to protect subcontractors doing off-site work from insolvent and irresponsible contractors. The record reveals that for many years, the City, despite its own ordinance, had only required performance bonds from subdividers in connection with the construction of off-site improvements. The City contends that its historical conduct thus negates any intent on its part in enacting the ordinance to protect subcontractors despite the plain language of the statute providing a protective mechanism for both the City and subcontractors. Heretofore, the City has apparently only enforced the provision which protected it and ignored the provision which protected subcontractors. We must
Given the City’s obvious intent and the clear language of the City’s ordinance, we decline to construe the payment bond provision of BCMC § ll-36-12(A) beyond the terms of its plain and ordinary meaning.
Beyond the plain language of the City ordinance, which is controlling, there are sound policy reasons for enforcing the literal sense of the ordinance in question. First, the City is in a position, essentially without cost, to insist on a payment bond that will protect subcontractors such as appellants from financial loss. The transaction costs incurred by the City in securing such protection would be minimal and, in any event, could be passed
We are aware of the general rule that municipalities or governmental agencies are not usually liable for failure to enforce ordinances or for dereliction of duties which benefit the public at large. Frye v. Clark County, 97 Nev. 632, 637 P.2d 1215 (1981); Bruttomesso v. Las Vegas Met. Police Dept., 95 Nev. 151, 591 P.2d 254 (1979); Commerce & Industry Ins. v. Toledo, 543 N.E.2d 1188 (Ohio 1989). However, the express language of the City’s ordinance makes this case qualitatively more than a simple failure to enforce an ordinance. The ordinance requires a payment bond and prohibits final map approval until there has been full compliance with the ordinance. If the ordinance had merely required the subdivider to secure a bond, without obligating the City to assure compliance as a condition precedent to final approval, then the City’s liability would be an unlikely prospect. But where, as here, the ordinance clearly requires the City to insure procurement of a payment bond, this is not failure to enforce but failure to perform a mandatory duty imposed on the City for the protection of specific entities whose work product will eventually become City property.
An exception to the general rule of non-liability for failure to enforce a statute is when there is some special relationship between the governmental agency and a particular individual or class of individuals. Frye, 97 Nev. at 634, 637 P.2d at 1216. Accord Platt v. District of Columbia, 467 A.2d 149 (D.C.App. 1983); O’Connor v. City of New York, 447 N.E.2d 33 (N.Y. 1983). The City has, perforce of its own ordinance, created a special relationship between the City, its agencies and subcontractors doing off-site work.
It cannot reasonably be contended that the City’s labor and materials bond requirement benefitted anyone other than subcontractors performing off-site work. The ordinance imposed upon
In Brennen v. City of Eugene, 591 P.2d 719 (Or. 1979), the Oregon supreme court was faced with a similar question. In Brennen, the city’s ordinance required it to refuse to issue a license to a taxi cab operator unless the operator could show that it had the required minimum amount of liability insurance. The city’s agent issued a license to an operator that did not meet the requirement. A passenger was subsequently injured in an accident caused by the underinsured taxi operator and was unable to collect the full amount of the judgment against the operator. The court held that the city was liable for the difference between the amount of the operator’s leviable assets and the amount of the judgment because its agent had violated a mandatory (as opposed to discretionary) requirement in the ordinance. Liability for this type of misfeasance is still the rule in Oregon. Cf. Salem School Dist. v. First State Ins. Co., 734 P.2d 369 (Or.App. 1987). (The Salem court assumed the school district’s liability on facts analogous and went immediately to the issue of insurance coverage for the liability). The result and the reasoning of Brennen is sound, just and equitable and is very similar to the case before us.
Brennen is consistent with the California jurisprudence in this area. In California, however, governmental liability is governed by statute. Cal. Gov. Code § 815; State of California v. Superior Court, 197 Cal.Rptr. 914 (1984). The approach and cases in California are nevertheless illustrative of the principles we adopt here. California Government Code section 815.6, one of the statutory bases for imposing liability, provides:
Where a public entity is under a mandatory duty imposed by an enactment that is designed to protect against a risk of a particular kind of injury, the public entity is liable for an injury of that kind proximately caused by its failure to discharge the duty unless the public entity establishes that it exercised reasonable diligence to discharge the duty.
The leading California case interpreting this statute is Morris v. Marin County, 136 Cal.Rptr. 251 (Cal. 1977). In Morris, the court reviewed a provision of the California Labor Code (§ 380) providing that every county or city which required permits to build or perform construction “shall require that each applicant
The parallels between the above cases and the instant case are evident. In fact, because the City imposed the obligation upon itself (rather than have it imposed by the State) the case for liability is arguably stronger. The City had an obligation to insure that a payment bond was posted before approval of the subdivision was granted. It did not do so and the subcontractors were unable to obtain payment. The City cannot now avoid liability by saying that it never requires such bonds or that it did not intend to enforce its own ordinance as written.
Effect of the Economic Loss Doctrine on the Ability to Recover in Negligence
The City claims that appellants only suffered economic damages and therefore the economic loss doctrine bars the negligence claim. We disagree.
This case is readily distinguishable from the economic loss
We previously noted that “[t]he primary purpose of the rule is to shield a defendant from unlimited liability for all economic consequences of a negligent act, particularly in the commercial setting, and thus keep the risk of liability reasonably calculable.” Stern, 98 Nev. at 411, 651 P.2d at 638. The rule is derived in part from the decision in Robins Dry Dock & Repair Co. v. Flint, 275 U.S. 303 (1927), where the court said: “[A]s a general rule, at least, a tort to a person or property of one man does not make the tortfeasor liable to another merely because the injured person was under a contract with the other, unknown to the doer of the wrong.” See Kingston Shipping Co., Inc. v. Roberts, 667 F.2d 34, 35 (1982). Id. at 309. The rule is aimed at third parties.
Both Stem and Central Bit are cases where individuals and entities who suffered damage to their economic expectancies because of allegedly defective products sought recovery from the parties participating in the supplying of the product.
Additionally, although appellants did not suffer property injury in the more traditional tort sense in which we generally view the
Also, given the context of the dispute, it would be disingenuous for the City to claim that appellants’ injuries were unforeseeable. Manifestly, the ordinance was structured for the express purpose of preventing the very injuries sustained by Brown and Delta. Therefore, the City could easily foresee that its failure to utilize the machinery which it created to prevent such injuries could, in fact, substantially contribute to their occurrence. The injuries and their extent are clearly foreseeable. As the purely economic recovery rule is bound up in foreseeability, the rule enunciated in Stern and Central Bit is simply inapplicable to this case.
Conclusion
For the reasons noted above, we reverse the summary judgment entered below and direct that summary judgment be entered in favor of Brown and Delta as to both liability and damages unless the amount of damage is factually disputed, in which case the district court shall require a trial limited to the issue of damages.
All municipalities and counties in Nevada require a performance bond or its equivalent when the subdivider has yet to complete the required improvements at the time of the approval of the final map. We have no information on how many also require payment bonds.
The dissent suggests that “an equally plausible” reading of BCMC § 11-36-12(A) is that the required payment bond applies only in the case of public construction. With due respect to the dissent, we note that the subject ordinance is applicable only to subdividers and subdivisions. It is common knowledge that subdivision construction entails work on private land owned by the subdivider. It does not involve or relate to “public construction.” We therefore fail to see how any rule of statutory construction or judicial interpretation could be rationally invoked to transmute an ordinance that expressly applies to subdividers and subdivisions into an ordinance applicable to public construction.
We find it equally implausible that the City would interject a public construction requirement for a payment bond in an ordinance that has no application whatsoever to public construction. It seems clear to us that the reference to public construction in the provision at issue serves only as a basis for setting the amount of the payment bond.
We are aware that Brown and Delta could have insisted on proof of a payment bond before applying their labor and materials. However, subcontractors are in an inferior bargaining position relative to general contractors and are dependent on the latter’s good will for employment. A reasonable subcontractor, rather than risking the prospect of antagonizing the general contractor, could assume that a payment bond had been provided inasmuch as it is a requirement for approval of the final map. Moreover, if the City is disinclined to provide the protection afforded by its own ordinance, it should repeal its obligations thereunder and thereby eliminate any basis for subcontractors relying on the City as a source of assistance in obtaining payment for their work.
In Stern, the plaintiffs were not even parties to the original transaction and were several steps removed from the design and construction of the hotel.