Citation Numbers: 214 N.J. 76, 67 A.3d 601, 2013 WL 3064600, 2013 N.J. LEXIS 589
Judges: Patterson
Filed Date: 6/20/2013
Status: Precedential
Modified Date: 11/11/2024
delivered the opinion of the Court.
This construction dispute requires the Court to consider two issues: 1) when a building can be considered substantially complete for purposes of calculating the ten-year period of the statute of repose, N.J.S.A. 2A: 14-1.1(a), and 2) whether the Comparative Negligence Act, N.J.S.A. 2A:15-5.2, and the Joint Tortfeasors Contribution Law, N.J.S.A. 2A:53A-2, authorize allocation of fault at trial to defendants who have obtained dismissals pursuant to the statute of repose, N.J.S.A. 2A:14-l.l(a).
Following structural failures in its public safety facility, plaintiff Town of Kearny (Town) sued the project’s architectural firm, Brandt-Kuybida Architects (Brandt-Kuybida), and three of its individual architects, alleging that Brandh-Kuybida was liable for defects in the facility that rendered it unusable. The Town and Brandt-Kuybida filed claims against the project’s soil engineering firm, Soils Engineering Services, Inc. (SESI), and one of its individual engineers, and structural engineering firm, HarrisonHamnett, P.C. (Harrison-Hamnett), and its principal. The trial court granted summary judgment motions filed by SESI and Harrison-Hamnett on the ground that the Town’s complaint was filed more than ten years after the engineers completed their work on the construction project, ruling that the claims against these defendants were barred by the statute of repose and the statute of limitations. The trial court, however, denied a similar motion filed by the defendant architect, holding that the ten-year
The Town appealed. The Appellate Division affirmed the trial court’s application of the statutes of repose and limitations to Brandt-Kuybida but reversed the trial court’s denial of the architect’s application for an apportionment of fault to the dismissed codefendants.
We affirm. We hold that the trial court properly denied Brandt-Kuybida’s motion for summary judgment on the statute of repose issue. We concur with the trial court’s finding that the ten-year period prescribed in N.J.S.A. 2A:14-l.l(a) commenced when the first Temporary Certificate of Occupancy was issued for the Town’s public safety facility. We further hold that, when the claims against a defendant are dismissed on statute of repose grounds, fault may be apportioned to the dismissed defendant under the Comparative Negligence Act and the Joint Tortfeasors Contribution Law.
I.
The South Kearny Improvement Projects Corporation (SKIP) was charged by the Town with the responsibility to oversee the design and construction of a new public safety facility, including police and fire stations. In October 1989, BrandWKuybida submitted a proposal to SKIP to design and plan the new facility. SKIP selected BrandWKuybida to perform the work. A principal of the firm, Louis Brandt, was initially designated as the lead architect. The Town and Brandt-Kuybida executed a contract on April 9, 1990. After Brandt-Kuybida dissolved in 1994, Michael Kuybida became the primary architect for the project.
SKIP chose Beleor Construction (Belcor) to build the facility in accordance with Brandt-Kuybida’s design, and, on July 11, 1994, SKIP and Belcor entered into a construction contract. Among other provisions, the construction contract required Belcor to achieve substantial completion of the project within 360 days of the issuance of a Notice to Proceed. That notice was issued on September 12, 1994. The contract between SKIP and Belcor defined substantial completion to be the date upon which the project architect, Brandt-Kuybida, certified that the facility is “sufficiently complete in accordance with the Contract Documents so that the Owner can occupy or utilize the Work for its intended use.”
Construction of the facility began in the fall of 1994. On November 15,1995, Beleor signed a document entitled “Certificate of Substantial Completion” (Certificate). On November 24, 1995, Brandt-Kuybida and SKIP signed that same document. In language similar to that of the July 11, 1994 contract, the Certificate defined the date of substantial completion as “the Date certified by the Architect when construction is sufficiently complete, in accordance with the Contract Documents, so the Owner can occupy or utilize the Work or designated portion thereof for the use for which it is intended, as expressed in the Contract Documents.” The signatories to the Certificate, however, failed to complete it. For reasons that the record does not disclose, the “date of issuance” and the “date of completion” of the project were left blank on the form.
Structural defects in the facility surfaced shortly after the Kearny Police Department took occupancy. The building settled differentially, causing gaps between the ceiling and a wall, as well as leaks, buckled tiles and cracks in the walls. The Kearny Police Department reported leaks in various parts of the building and doors that could not close because they did not fit in their frames. Although the Town continued to use the facility, there were further complaints about structural flaws in the building. In 2003, the Town’s Construction Official received an emergency call that the ceiling in the police dispatch area of the building was about to collapse. By 2007, ceilings in the facility had fallen, pipes had separated and pulled, and glass had broken, all of which were attributed to uneven settlement. The Town never issued a final certificate of occupancy. The Town’s Construction Official ordered all occupants to evacuate the building on February 8, 2007. The building has been vacant and unused since that date.
Belcor initiated arbitration proceedings against the Town because the Town withheld final payment under the contract. Bel
II.
On April 7, 2006, the Town filed an action in the Law Division, asserting negligence and breach of contract claims against Brandt-Kuybida and two of its principals, Louis Brandt and Michael Kuybida, and another architect, Robert Strebi (the Brandt-Kuybida defendants); negligence claims against Harrison-Hamnett and its principal, John N. Harrison (the HarrisonHamnett defendants); and negligence and breach of contract claims against SESI and one of its engineers, William St. Pierre (the SESI defendants). The Brandt-Kuybida defendants pled an affirmative defense based upon their right to seek apportionment of fault to all other parties who contributed to the incident. They also asserted a cross-claim against their codefendants, premised upon common-law indemnification and contribution pursuant to the Comparative Negligence Act and the Joint Tortfeasors Contribution Law.
The Brandt-Kuybida defendants filed a motion for summary judgment. They asserted, among other theories, that the statute of repose, N.J.S.A. 2A:14-l.l(a), barred the Town’s claims.
The trial court, however, granted summary judgment motions filed by the Harrison-Hamnett defendants and the SESI defendants. It held that the ten-year period set forth in the statute of repose commenced for the SESI defendants on the date that their involvement in the project ended, July 31, 1990, and that the statutory period commenced for the Harrison-Hamnett defendants on the date that their role in the project concluded, October 30, 1995. Consequently, the trial court held that the actions against the SESI and Harrison-Hamnett defendants were barred by both the statute of repose, N.J.S.A. 2A:14-l.l(a), and the
The BrandL-Kuybida defendants filed a motion for leave to appeal the trial court’s order denying summary judgment. The Appellate Division granted the motion and summarily remanded the ease to the trial court for reconsideration in light of this Court’s decision in Daidone v. Buterick Bulkheading, 191 N.J. 557, 924 A.2d 1193 (2007). On remand, the trial court analyzed Daidone but again denied the Brandt-Kuybida defendants’ summary judgment motion. It then granted the Town’s motion to strike several of the Brandt-Kuybida defendants’ affirmative defenses, including the affirmative defense asserting their right to seek apportionment of fault to other parties. The trial court held that by virtue of the dismissal of the Town’s claims against the Harrison-Hamnett defendants and the SESI defendants, those defendants were no longer parties, and Brandt-Kuybida was not entitled to an apportionment of fault against them.
The case was tried before a jury for six days in October 2008. The trial court rejected the Brandt-Kuybida defendants’ argument that the date of substantial completion should be determined by the jury, and denied their motion to dismiss the Town’s claims on statute of repose grounds at the close of the Town’s case. In accordance with the trial court’s decision striking the Brandi Kuybida defendants’ apportionment defense, the jury considered only the fault of those defendants, not that of the codefendants previously dismissed on statute of repose grounds.
The Brandt-Kuybida defendants appealed. Analyzing the Comparative Negligence Act, the Joint Tortfeasor Contribution Law
We granted the Town’s petition for certification and the BrandWKuybida defendants’ cross-petition for certification. 209 N.J. 98, 35 A.3d 681 (2012).
III.
The parties dispute whether the trial court should have granted the Brandt-Kuybida defendants’ motion for summary judgment on the statute of repose. The Brandt-Kuybida defendants primarily rely upon the Certificate of Substantial Completion signed on November 15 and 24, 1995, contending that the latter date constitutes the operative date by which the construction was substantially complete. They contend that, if the Court does not accept November 24,1995, as the date of substantial completion, it should instead find February 1, 1996, to be the critical date, given the Town’s acknowledgement of that date in its Stipulation of Settlement with Belcor and the corresponding Town of Kearny Resolution 1999(R)-338. The Brandt-Kuybida defendants argue that in
The Town argues that the trial court properly ruled that the date of substantial completion was April 9, 1996, when the first Temporary Certificate of Occupancy was issued. Although the Town concedes that parties to a construction dispute may stipulate to a date of substantial completion, it contends that there was no such stipulation in this ease. The Town asserts that because no agreed-upon date was included in the Certificate of Substantial Completion, that document lacked a material term and has no legal effect. The Town urges the Court to defer to the factual findings of the trial court regarding the actual date upon which work on the project had progressed to the point of substantial completion. It argues that the trial court correctly denied the BrandUKuybida defendants’ motion for summary judgment, because the action was timely filed.
With respect to the issue of apportionment, the Town argues that the Appellate Division erred when it reversed the trial court’s pretrial and trial orders and permitted the Brandb-Kuybida defendants to allocate fault to the SESI and Harrison-Hamnett defendants. The Town contends that, when the claims against an individual or entity are dismissed pursuant to the statute of repose, liability should not be apportioned to that individual or entity, because the Comparative Negligence Act, N.J.S.A 2A:15-5.2(a)(2), authorizes apportionment only to “the parties to a suit.” The Town argues that the SESI and Harrison-Hamnett defendants are distinguishable from various categories of parties to whom fault may be apportioned under our law. Instead, the Town likens the dismissed defendants in this case to an employer protected from civil liability by the workers’ compensation bar, to which fault may not be apportioned under the relevant statutes.
The Brandb-Kuybida defendants counter that allocation of fault to the SESI and Harrison-Hamnett defendants is consistent with the protective goals of the statute of repose because those defen
IV.
The first issue before the Court is whether the trial court properly denied the Brandt-Kuybida defendants’ motion for summary judgment and their motion to dismiss at the close of the Town’s case at trial based upon the statute of repose. We review de novo the grant or denial of a motion for summary judgment. Coyne v. State Dep’t of Transp., 182 N.J. 481, 491, 867 A.2d 1159 (2005). Summary judgment must be granted if “the pleadings, depositions, answers to interrogatories and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact challenged and that the moving party is entitled to a judgment or order as a matter of law.” R. 4:46-2(c). The judge must decide whether “the competent evidential materials presented, when viewed in the light most favorable to the non-moving party, are sufficient to permit a rational factfinder to resolve the alleged disputed issue in favor of the non-moving party.” Brill v. Guardian Life Ins. Co., 142 N.J. 520, 540, 666 A.2d 146 (1995).
In 1967, “the Legislature enacted the statute [of repose] in response to the expanding application of the ‘discovery rule’ to new types of tort litigation, the abandonment of the ‘completed and accepted rule’ ... and the expansion of strict liability in tort for personal injuries caused by defects in new homes to builder/sellers of those homes.” Newark Beth Israel Med. Ctr. v. Gruzen & Partners, 124 N.J. 357, 362, 590 A.2d 1171 (1991) (quoting O’Connor v. Altus, 67 N.J. 106, 117-19, 335 A.2d 545 (1975)). The statute was intended “ ‘to cut back on the potential of [design and construction professionals] to be subject to liability for life.’ ” Ibid, (quoting Ramirez v. Amsted Indus., Inc., 86 N.J. 332, 356, 431 A.2d 811 (1981)). To that end, the statute of repose imposes a ten-year limit upon actions against parties responsible for the design, planning, supervision or construction of improvements to real property.
No action whether in contract, in tort, or otherwise to recover damages for any deficiency in the design, planning, supervision or construction of an improvement to real property, or for any injury to property, real or personal, or for an injury to the person, or for bodily injury or wrongful death, arising out of the defective and unsafe condition of an improvement to real property, nor any action for contribu*93 lion or indemnity for damages sustained on account of such injury, shall be brought against any person performing or furnishing the design, planning, supervision of construction or construction of such improvement to real property, more than 10 years after the performance or furnishing of such services and construction.
[N.J.S.A. 2A:14-l.l(a).]6
The statute of repose is construed broadly to serve its legislative objective “of providing a reasonable measure of protection against expanding liability for design and construction professionals.” Newark Beth Israel, supra, 124 N.J. at 363, 590 A.2d 1171; accord Rosenberg, supra, 61 N.J. at 198, 293 A.2d 662. It is “ ‘unlike the typical statute of limitations [because t]he time within which suit may be brought under [the statute of repose] is entirely unrelated to the accrual of any cause of action.’ ” Daidone, supra, 191 N.J. at 564, 924 A.2d 1193 (alteration in original) (quoting Rosenberg, supra, 61 N.J. at 199, 293 A.2d 662). “[T]he discovery rule does not extend the ten-year statute of repose, because that statute was specifically passed to protect architects and other construction professionals from” indefinite liability that might otherwise be imposed by application of the discovery rule. Trinity Church, supra, 394 N.J.Super. at 176, 925 A.2d 720 (citing Russo Farms, supra, 144 N.J. at 116, 675 A.2d 1077). Thus, the date upon which the Town’s cause of action accrued for purposes of the discovery rule is irrelevant to the issue before us.
Our case law distinguishes between defendant contractors who are hired to perform limited services and defendants with supervisory responsibilities that span the entire project, in determining the date upon which the ten-year period begins for purposes of N.J.S.A. 2A:14-l.l(a). For the former, the ten-year period begins to run at the conclusion of the contractor’s specific task. As this Court held in Daidone, supra, 191 N.J. at 568, 924 A.2d 1193, “if a plaintiff wishes to impose liability on an individual design professional or a sub-contractor, he or she will have to track when those design or construction services were completed
For professionals such as the BrandL-Kuybida defendants, whose responsibilities for the Kearny public safety facility continued throughout its design and construction, the ten-year period set forth in N.J.S.A 2A:14-1.1(a) commences on the date of the project’s substantial completion. In Russo Farms, supra, 144 N.J. at 116-17, 675 A.2d 1077, this Court reversed a panel that ruled that the “ ‘performance or furnishing’ of services and construction” was not complete, and therefore did not trigger the commencement of N.J.S.A. 2A:14-1.1(a)’s ten-year period until “the final items on the punch list were completed.” Citing the Legislature’s interest in fairness and certainty, the Court rejected defining substantial completion as the date on which all outstanding construction issues are addressed:
[I]f liability were to be measured from the date the last retainage is released and all disputed and punch list items are completed, a contractor’s exposure to suit might be prolonged unreasonably. Disputes over workmanship and compensation for services can continue for years____[A] contractor would remain liable and the commencement of the statute of repose could be delayed indefinitely. Such a result is inconsistent with the statutory purpose to provide repose and allow contractors and architects to walk away from liability at a certain point in time; indeed, it would, all too often, provide “liability for life.”
[Id. at 117-18, 675 A.2d 1077.]
Deferring to the construction industry’s standard practice of deeming a project complete, the Court held that “substantial completion” had occurred for statute of repose purposes “when the certificate of occupancy was issued and the architect certified to the owner that building was substantially completed.” Id. at 117, 675 A.2d 1077. The Court accepted the certificate of occupancy as
This Court’s holdings in Russo Farms and Daidone support the determinations of the trial court and the Appellate Division in this ease. The trial and appellate courts agreed that the ten-year period prescribed by the statute of repose commenced on April 9, 1996, when the first Temporary Certificate of Occupancy was issued for the facility. As the trial court noted, this certificate indicated that the building was sufficiently complete so that it could be occupied and used. We agree and hold that the issuance of that certificate triggered the running of the ten-year period for purposes of the statute of repose under N.J.S.A. 2A:14-l.l(a).
While this Court in Russo Farms acknowledged the importance of the date of substantial completion as certified by a project’s lead architect, see Russo Farms, supra, 144 N.J. at 92-93, 117, 675 A.2d 1077, a stipulated date of substantial completion may also be relevant to a court’s analysis of the statute of repose, see Trinity Church, supra, 394 N.J.Super. at 170, 925 A.2d 720 (concluding parties can stipulate via contract to substantial completion date). Here, however, we have no such benchmark. The critical term — the date of substantial completion — is missing from the Certificate of Substantial Completion signed on November 15 and 24, 1995, and the document bears no official date of execution. Moreover, as the trial court found, in November 1995, substantial work remained to be completed before the building could be used. Accordingly, the incomplete Certificate signed in November 1995 is irrelevant to the statute of repose in this case.
We affirm the trial court’s finding that the ten-year period of the statute of repose, N.J.S.A. 2A:14-l.l(a), commenced on April 9, 1996, when the first Temporary Certificate of Occupancy was issued. Accordingly, we hold that the Town’s action was timely filed against the BrandWEiuybida defendants. We affirm the Appellate Division’s determination that the trial court properly denied the Brandt-Kuybida defendants’ motion for summary judgment.
V.
We review de novo the Appellate Division’s decision reversing the trial court’s ruling on the issue of whether the jury should consider the SESI and Harrison-Hamnett defendants’ fault in its apportionment calculation. See Murray v. Plainfield Rescue Squad, 210 N.J. 581, 584, 46 A.3d 1262 (2012) (reviewing meaning of statute de novo); Manalapan Realty, supra, 140 N.J. at 378, 658 A.2d 1230 (reviewing legal decisions de novo).
The Comparative Negligence Act and the Joint Tortfeasors Contribution Law comprise the statutory framework for the allocation of fault when multiple parties are alleged to have contributed to the plaintiff’s harm. Under the Comparative Negligence Act, in negligence and strict liability actions in which “the
(1) The amount of damages which would be recoverable by the injured party regardless of any consideration of negligence or fault, that is, the full value of the injured party’s damages.
(2) The extent, in the form of a percentage, of each party’s negligence or fault. The percentage of negligence or fault of each party shall be based on 100% and the total of all percentages of negligence or fault of all the parties to a suit shall be 100%.
[N.J.S.A. 2A:15-5.2(a).]
In practice, the Comparative Negligence Act requires the fact-finder to assign to each party on the verdict sheet a percentage of fault, with the percentages assigned to each party adding up to 100%. N.J.S.A. 2A: 15-5.2(a)(2). With the factfinder’s task complete, ‘Ttjhe judge shall mold the judgment from the findings of fact made by the trier of fact.” N.J.S.A. 2A:15-5.2(d). In accordance with N.J.S.A. 2A:15-5.3(a), if a defendant’s fault is assessed at sixty percent or more, the plaintiff may recover the full amount of the awarded damages from that defendant alone. If the factfinder apportions less than sixty percent of fault to that defendant, the plaintiff may recover from that defendant only the percentage of the damages assessed. N.J.S.A. 2A:15-5.3(c).
The Joint Tortfeasors Contribution Law plays a complementary role in the statutory scheme. Under that statute, a party that is liable for more than the percentage share of the damage award that is assessed by the factfinder may have contribution rights against other parties. N.J.S.A. 2A:53A-3. The statute “was enacted to promote the fair sharing of the burden of judgment by joint tortfeasors and to prevent a plaintiff from arbitrarily selecting his or her victim.” Holloway v. State, 125 N.J. 386, 400-01, 593 A.2d 716 (1991). As this Court noted in Erny v. Estate of Merola, 171 N.J. 86, 99, 792 A.2d 1208 (2002), “[wjhen applied together, the [Comparative Negligence Act and Joint Tortfeasors Contribution Law] implement New Jersey’s approach to fair apportionment of damages among plaintiffs and defendants, and among joint defendants.”
When interpreting multiple statutes governing the same subject, the Court should attempt to harmonize their provisions. Saint Peter’s Univ. Hosp. v. Lacy, 185 N.J. 1, 14-15, 878 A.2d 829 (2005) (‘“Statutes that deal with the same matter or subject should be read in pari materia and construed together as a “unitary and harmonious whole.” ’ ” (quoting In re Adoption of a Child by W.P. & M.P., 163 N.J. 158, 182-83, 748 A.2d 515 (2000) (Poritz, C.J., dissenting))). Here, our task is to harmonize the text and intent of the Comparative Negligence Act and the Joint Tortfeasors Contribution Law with the statute of repose. See Brodsky, supra, 181 N.J. at 110-11, 853 A.2d 940 (analyzing several provisions of Comparative Negligence Act to determine whether defendant dismissed because of bankruptcy is “party” to the suit); Burt v. W. Jersey Health Sys., 339 N.J.Super. 296, 303-05, 771 A.2d 683 (App.Div.2001) (harmonizing Comparative Negligence Act, Joint Tortfeasors Contribution Law, and Affidavit of Merit statute, N.J.S.A. 2A:53A-27 to -29).
We previously have not determined whether the Comparative Negligence Act and the Joint Tortfeasors Contribution Law authorize allocation of fault to a defendant who obtains a dismissal by virtue of the statute of repose. This Court and the Appellate
The Appellate Division in Ramos v. Browning Ferris Industries of South Jersey, Inc., 194 N.J.Super. 96, 106, 476 A.2d 304 (App.Div.1984), rev’d on other grounds, 103 N.J. 177, 510 A.2d 1152 (1986), and this Court in Ramos, supra, 103 N.J. at 181, 510 A.2d 1152, rejected an indemnification claim by the plaintiffs supplier of workplace equipment against its employer. Because the employer was immune from civil liability pursuant to the Workers’ Compensation Act, N.J.S.A. 34:15-1 to -127, the Appellate Division held that it was not a “party” within the meaning of N.J.S.A. 2A:15-5.2. Ramos, supra, 194 N.J.Super. at 102, 106-07, 476 A.2d 304. This Court agreed, focusing upon the complete immunity afforded by the Workers’ Compensation Act, which precludes any claim in Superior Court against the employer and “removes the employer from the operation of the Joint Tortfeasors Contribution Law.” Ramos, supra, 103 N.J. at 184, 510 A.2d 1152. In Ram,os, by virtue of the Workers’ Compensation bar, no cause of action in tort against the employer ever arose. See ibid. Accordingly, no fault could be allocated to the employer pursuant to the Comparative Negligence Act and the Joint Tortfeasors Contribution Law. Id. at 184, 193-94, 510 A.2d 1152.
This Court reached a different conclusion when the defendant at issue was not protected by statutory immunity but was dismissed from the case by virtue of a settlement. In Young v. Latta, 123 N.J. 584, 585, 589 A.2d 1020 (1991), a medical malpractice “plaintiff settled before trial with one defendant-physician” and proceeded to trial against another. Although the non-settling defendant had not asserted a cross-claim for contribution against the settling defendant, the Court permitted him to seek an allocation of fault to the settling defendant, holding that “a non-settling defendant may seek a credit in every case in which there are multiple defendants, whether or not a cross-claim for contribution has been
Thus, when a defendant ceases to participate in the case by virtue of a settlement, a non-settling defendant who meets the relevant requirements as to notice and proof may obtain an allocation of fault to the settling defendant. See Young, supra, 123 N.J. at 596-97, 589 A.2d 1020. The settling defendant does not pay any portion of the judgment; any percentage of fault allocated to the settling defendant operates as a credit to the benefit of the defendants who remain in the case. Id. at 595-96, 589 A.2d 1020; accord R. 4:7-5(c).
We hold that the trier of fact must determine the percentage of fault or negligence of a party dismissed from a negligence action following that party’s discharge in bankruptcy. .. That conclusion assures that defendants are not deprived of the benefits of the Comparative Negligence Act, namely their right to be held accountable only for their percentage of fault, provided that portion is less than sixty percent.
[Id. at 116, 853 A.2d 940 (citing N.J.S.A. 2A:15-5.3(c)).]
Under Brodsky, a defendant against whom plaintiff had a potential claim, but who was shielded by bankruptcy law from liability for that claim, was nonetheless held to be an essential component of the jury’s assessment of fault under the Comparative Negligence Act. Ibid.
The Appellate Division has also considered the issue of apportionment in several settings. In Bencivenga v. J.J.A.M.M., Inc., 258 N.J.Super. 399, 406-08, 609 A.2d 1299 (App.Div.), certif. denied, 130 N.J. 598, 617 A.2d 1220 (1992), the panel rejected a defendant’s request for an instruction directing the jury to assess the fault of the unidentified individual who assaulted him on the defendant’s premises and had been named as a fictitious defendant in the complaint pursuant to Rule 4:26-4. When an actual defendant is properly named in the case, however, statutory constraints
From the governing statutes and our case law, we can derive several guiding principles. First, the Comparative Negligence Act and the Joint Tortfeasors Contribution Law promote “the distribution of loss ‘in proportion to the respective faults of the parties causing that loss.’ ” Brodsky, supra, 181 N.J. at 114, 853 A.2d 940 (quoting Blazovic v. Andrich, 124 N.J. 90, 107, 590 A.2d 222 (1991)). Given the impact of a defendant’s percentage of fault on the scope of its liability, the statutes’ objectives are best served when the factfinder evaluates the fault of all potentially responsible parties. Ibid.; Young, supra, 123 N.J. at 594-95, 589 A.2d 1020; Bolz, supra, 400 N.J.Super. at 160-61, 946 A.2d 596; Burt, supra, 339 N.J.Super. at 306-07, 771 A.2d 683.
Second, our courts have barred apportionment where, as a matter of law, defendant could not under any circumstances be a joint tortfeasor under N.J.S.A 2A:53A-2. Brodsky, supra, 181 N.J. at 115, 853 A.2d 940. Thus, in Ramos, an employer subject only to an action under the Workers’ Compensation Act, and immunized from any action in tort, was not subject to apportion
Third, apportionment of fault under the Comparative Negligence Act and the Joint Tortfeasors Contribution Law does not turn on whether the plaintiff is in a position to recover damages from the defendant at issue. Our courts have authorized a factfinder’s assessment of the fault of a defendant from whom the plaintiff is barred from recovering damages by virtue of bankruptcy, Brodsky, supra, 181 N.J. at 116, 853 A.2d 940, from whom plaintiff cannot recover for failure to meet a statutory element for municipal liability, Bolz, supra, 400 N.J.Super. at 161—62, 946 A.2d 596, and from whom the plaintiff can collect only limited damages, Johnson, supra, 239 N.J.Super. at 319, 571 A.2d 318. Thus, statutory constraints on a plaintiff’s ability to recover from a given defendant do not automatically preclude apportionment of fault to that defendant, notwithstanding the defendant’s discharged liability.
Fourth, a claimant’s failure to conform to a statutory requirement for asserting claims against a given defendant does not necessarily bar apportionment of that defendant’s fault at trial. In Burt, supra, 339 N.J.Super. at 304, 771 A.2d 683, apportionment of fault to a physician defendant was permitted notwithstanding the plaintiffs failure to comply with the requirements of the Affidavit of Merit statute. Thus, in a case in which a plaintiff fails to meet a statutory requirement to file a claim against a particular defendant, our comparative fault statutes do not require that the remaining defendants be penalized when the factfinder allocates fault.
Applied here, these principles require that we affirm the Appellate Division’s decision on the issue of apportionment. Allocation of fault to the dismissed defendants — who will, in any event, pay no damages — does not subvert the statute of repose’s purpose to
Accordingly, the Appellate Division properly reversed the trial court’s pretrial and trial orders denying the Brandt-Kuybida defendants’ applications for an allocation of fault to the SESI and Harrison-Hamnett defendants.
VI.
We affirm the judgment of the Appellate Division. We remand the matter to the trial court for a new trial on the issue of liability,
For affirmance and remandment — Chief Justice RABNER and Justices LaVECCHIA, ALBIN, HOENS, PATTERSON, Judges RODRÍGUEZ (temporarily assigned) and CUFF (temporarily assigned) — 7.
Opposed — None.
The Brandt-Kuybida defendants also asserted a defense based upon the ten-year statute of limitations that governs construction claims asserted by public entities, N.J.S.A. 2A:14-1.2. In this case, the parties stipulated that the statute of repose and statute of limitations were coextensive, and that the ten-year period for each commenced on the date of substantial completion. The Town did not assert that the discovery rule tolled the commencement of the statute of limitations in this case. See Rosenberg v. Town of N. Bergen, 61 N.J. 190, 195-98, 293 A.2d 662 (1972) (applying discovery rule to toll limitations period). The trial court agreed that the date upon which the ten-year period of the statute of repose and the ten-year limitations period began for purposes of N.J.S.A. 2A: 14-1.2 were the same. The Appellate Division affirmed without further discussion.
Although the trial court transcript reflects that the jury received a verdict sheet, the verdict sheet is not part of the record.
The Appellate Division affirmed the trial court's determination that fault could not be apportioned to the Town under the Comparative Negligence Act and the Joint Tortfeasors Contribution Law, and that issue is not before this Court.
A motion for dismissal based on Rule 4:37-2(b) "requires essentially the same analysis” as a motion for summary judgment under Rule 4:46-2. Shelcusky v. Garjulio, 172 N.J. 185, 199, 797 A.2d 138 (2002).
The statute of repose does not protect parties who are "in actual possession and control [of the improvement] as owner, tenant, or otherwise” at the time that the defective and unsafe condition causes the injury or damage at issue. N.J.S.A. 2A: 14-1.1(a).
The statute was amended in May 2001, L. 2001, c. 76, § 1, but the changes as a result of that amendment are irrelevant here.
In Young, the Court emphasized the importance of timely notice to a plaintiff and any remaining defendants when a non-settling defendant seeks to prove the fault of a settling codefendant. Young, supra, 123 N.J. at 597, 589 A.2d 1020; see also Newman v. Isuzu Motors Am., Inc., 367 N.J.Super. 141, 153, 842 A.2d 255 (App.Div.2004) (concluding defendant waived right to seek apportionment of fault to settling plaintiff by failing to assert cross-claim or provide timely notice).
The Town's awareness of construction defects during the ten-year statute of repose period distinguishes this case from Rosenberg. There, the plaintiff’s personal injury took place approximately thirty-three years after the road, that she alleged to have been negligently constructed, had been repaved. Rosenberg, supra, 61 N.J. at 193, 293 A.2d 662. Affirming the dismissal of the plaintiff’s claim, this Court noted that by virtue of the statute of repose, no viable cause of action against the asphalt contractor defendant ever arose. Id. at 199, 293 A.2d 662.