Filed Date: 7/1/1981
Status: Precedential
Modified Date: 11/11/2024
Triangle PWC, Inc. (Triangle) appeals from a determination by the Director of the Division of Building and Construction (DBC) in the Department of the Treasury on April 17,1980 that:
1. THE STATE WILL NOT APPROVE THE USE OF HIGH POWER TRIANGLE CABLE ON ANY DBC PROJECTS UNTIL AFTER JANUARY 1, 1981, UNLESS
2. TRIANGLE PWC PROVIDES THE STATE WITH A LIST OF ALL PURCHASORS [sic] OF HIGH POWER CABLE FROM MAY 1972 (THE INCEPTION OF THE GREYSTONE CONTRACT) TO DATE. THE STATE WILL CONDUCT A RANDOM AUDIT OF THE BUYERS TO VERIFY THE PERFORMANCE OF THESE CABLES. IF THERE HAS BEEN NO PATTERN OF FAILURES, THE DISQUALIFICATION OF SAID CABLES WILL BE LIFTED. IF THERE IS A PATTERN OF FAILURES, DISQUALIFICATION WILL REMAIN IN EFFECT UNTIL JANUARY 1, 1981.
We stayed the determination pending the appeal, “subject to the proviso that any part of the term of the disqualification will be served should the court affirm the decision under appeal.” We now reverse and remand the matter to the Director for reconsideration and the issuance of a new final decision.
On March 24, 1977 the Director notified Triangle in writing that DBC was considering debarring it, i.e., excluding it from contracting, for a period of five years because of alleged violations of N.J.A.C. 17:13-8.2(9), (10) and (12). The violations were stated to be:
.. [Y]our failure to provide a manufactured product on a State public works project which was in conformance with the contract specifications and your continuing failure to assume responsibility for all damages incurred for the replacement of the failed materials manufactured and supplied by Triangle PWC, Inc. The materials in question are # 2 5KV and 500 MCM 5KV electrical cable supplied for the Greystone Psychiatric Hospital Electrical Site Utilities Project ....
A hearing was held before a hearing officer appointed by the Director. The hearing officer thereafter issued a lengthy report in which, on the basis of his findings of fact and conclusions of law, he recommended that DBC’s case against respondent “should be dismissed with prejudice because of a failure to make out a prima facie case of clear and convincing evidence of manufacturing defects attributable to Respondent.” On DBC’s claim of newly discovered “concrete” evidence supporting its allegation that Triangle cable was defective, further hearings took place before the same hearing officer. He submitted a supplemental report in which he again concluded that DBC failed to present clear and convincing evidence to substantiate its charges.
The Director declined to accept and adopt the findings and conclusions of the hearing officer. Instead, he issued a letter opinion containing the determination that is the subject matter of this appeal.
In our view, the Director did not approach the problem properly. It is evident that he was heavily influenced by his belief that Triangle should have assumed its “responsibilities” to pay both material and labor costs associated with replacing the cable. He spoke of the cable’s failure being “a disaster for the
The Director noted that the parties agreed at the hearing that the failure might be attributed to one of three factors: improper installation or mechanical damage, defective manufacture or impressed voltage (overloading), especially lightning strikes. He said that it was “quickly conceded” that the failure was not caused by improper installation. He acknowledged and apparently did not contest the hearing officer’s inability to find “clear and convincing” evidence in support of the State’s contention that the cable was defective. But he added that “[njeither can I find ‘clear and convincing’ evidence on the part of Triangle that failure was due to lightning or that some other external effect overloaded the system.” In this regard the Director fell into error, for under the applicable regulation the burden of proving a cause for debarment was on the State. In the absence of clear and convincing proof of such cause, Triangle was not obligated to show why it should not be debarred.
Citing 28 failures that had occurred in two sizes of cable over a span of a year and a half, the Director stated that “the high incidence of failure . . . may not be convincing in the true sense of the word but certainly is ‘clear’ evidence to me that something went wrong in these particular sizes of cables.” But it is
As a further indication that “there was something defective or inferior in the Triangle product,” the Director said, “I have since learned that Ace and Wire Cable Co., the supplier of Triangle cable to Broadway Maintenance Co., Inc., was sued by BMC for the cable failure,” and that the case was settled out of court in the amount of $250,000. This reference to the litigation and settlement was manifestly unfair. There was nothing about it in the record before the Director except for an occasional passing reference to the existence of a lawsuit. The Director’s decision could be based only upon the record developed by the hearing officer, N.J.S.A. 52:14B-10(d), not upon that which he may have ascertained outside the record.
We conclude, for the reasons expressed above, that the matter must be remanded to the Director for reconsideration and the issuance of a new final decision and order. In his review of the record submitted by the hearing officer, he shall be guided by the standard referred to above, namely, that the existence of the alleged causes for debarment must be established by evidence which he determines to be “clear and convincing in nature.” N.J.A.C. 17:13-8.3(a)(5). If he elects again upon such review to reject the recommended report and to decide the matter adversely to Triangle, his final decision shall include findings of
Reversed and remanded for further proceedings consistent with the foregoing. Jurisdiction is not retained.