Citation Numbers: 217 N.J. Super. 526, 526 A.2d 282, 1987 N.J. Super. LEXIS 1177
Filed Date: 5/21/1987
Status: Precedential
Modified Date: 11/11/2024
Klimar Realty, Inc. (Klimar) appeals from a September 30, 1985 final decision of the Department of Environmental Protection, Division of Water Resources (DEP) which denied Klimar’s application for a stream encroachment permit pursuant to N.J. S.A. 13:lD-29 et seq
Klimar’s permit application initially consisted of various documents and a filing fee submitted to DEP on May 15,1985. By
Klimar argues that its application was “complete” within the meaning of N.J.S.A. 13:1D-31 no later than June 26. It relies on N.J.S.A. 13:lD-30, which provides that where DEP requests additional information from the applicant,
the application will be construed to be complete when the additional information is received by [DEP].
DEP responds that the Klimar application was not “complete” until July 3 when it was “accepted for review” by DEP. DEP relies upon N.J.A.C. 7:13-2.8(a) and (b):
(a) A maximum of 20 working days from the receipt of the application will be allowed for preliminary review of the application for completeness. During this period the Department will either accept the application for review, which will begin the 90-day review period, or reject the application for incompleteness and inform the applicant in writing of the information necessary to complete his application.
(b) The 90-day review period begins on the day a project number is assigned and the application is accepted for review. At this time an acknowledgment letter is sent to the applicant.2
The September 30, 1985 final decision is reversed. The matter is remanded to DEP with directions to issue the stream encroachment permit to Klimar.
Klimar commenced the litigation by filing a complaint in lieu of prerogative writs in the Law Division. On cross-motions for summary judgment, the Law Division judge transferred the matter to this court. R. 1:13-4(a); R. 2:2-3(a)(2). Although Klimar argues that the Law Division had jurisdiction and should have granted summary judgment in its favor, it has not appealed from the transfer order. In any event, our disposition of the appeal moots those arguments.
DEP relied in its brief on N.J.A.C. 7:1C-I.7(a)2 and 7:10-1.8, applicable to a variety of construction permit applications, which also provide that DEP shall act "within 90 days after the application has been accepted for filing" and that where additional information is requested DEP shall act "within 90 days after such additional information has been accepted." N.J.A.C. 7:1C-1.8(a). At oral argument, the Attorney General acknowledged that the applicable regulation here is N.J.A.C. 7:13-2.8, which deals specifically with stream encroachment permits.
N.J.A.C. 7:13-2.8(b) describes a number of actions DEP may take during the 90-day period. We need not determine here whether, when or in what circumstances the running of the 90-day period may be tolled or interrupted by a DEP finding that the additional information submitted is not sufficient for it to act.