Citation Numbers: 105 N.E. 99, 211 N.Y. 107, 1914 N.Y. LEXIS 1027
Judges: Collin, Miller
Filed Date: 4/14/1914
Status: Precedential
Modified Date: 10/19/2024
[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 109
[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 110
[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 111
[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 112
The statute requiring and prescribing the substance and conditions of the bond is as perfectly binding on the principal and surety as if it had been set forth in the bond in its very words. (McCracken v. Hayward, 2 How. [U.S.] 608.) The bond, conforming to the statute, *Page 114
imposed only such obligations as the statute permits. The statute is in a sense a recognition by Congress of the inability of persons supplying contractors for public works with labor and materials to take liens upon the public property of the United States and a substitute for a mechanic's lien law. (UnitedStates v. Ansonia Brass, etc., Co.,
It should be noticed, in order that there may be a true understanding of the relevant decisions, that the statute takes up the entire subject covered by a prior statute (Act of August 13, 1894, ch. 280; 28 U.S. Stat. L. 278), and, therefore, is to be treated as a substitute act.
Obviously the entire liability of the surety company to the claimant for the materials furnished by it under the contract between it and the Church Construction Company arises through the execution of the bond by the surety company as a surety for the construction company. The claimant could reach the surety company through the bond alone, which, with the statute as a part of it, defines and limits the rights of the claimant as against it, and the method and tribunals through which those rights might be enforced. His right of action against it through any form of legal proceeding was created by the bond and the statute, and must be enforced pursuant to the terms and conditions of the statute and not otherwise. (Stitzer v. United States,
182 Fed. Rep. 513; United States v. Boomer, 183 Fed. Rep. 726;Baker Contract Co. v. United States, 204 Fed. Rep. 390.) It was, however, a qualified and conditional, and not an absolute right or cause of action. An act of Congress, which at the same time and in itself authorizes or creates a new cause of action and prescribes the limitations thereof and of its enforcement, makes those limitations conditions of the liability itself. Such an act is not a statute of limitations, and a compliance with the conditions which it prescribes is indispensable to the enforcement of the right *Page 115
it creates, because they are parts of or elements in the right itself and not limitations of the remedy only. The limitation of the remedy is a limitation to the right. (The Harrisburg,
The surety company became the surety for the Church Construction Company as expressed in the bond. The contract between the United States and the Construction Company was completed and finally settled September 28, 1908. Within the six months from that date, terminating March 27, 1909, the United States had not instituted any action upon the bond. The statute contemplated that the rights and claims of all claimants under the bond should be adjudicated in a single action brought upon the bond. (United States v. Congress Construction Co.,
The liability of the surety company to the claimant did not become absolute and direct when, after it had supplied the materials to the original contractor, their price became due, or when the contract between the original contractor and the United States was completed and finally settled. It remained qualified and conditional. Its certainty or absoluteness depended upon the possibility that, by means of the only method provided or permitted by the statute and not then instituted, the validity and enforceability of the claim be adjudicated. A judgment for it in an action prescribed by and conducted in accordance with the requirements of the statute could alone render it complete and absolute. The means of enforcement define both the right of the claimant and the liability of the surety which it was the intention of Congress to create.
It is unnecessary to consider whether or not the presentation of the claim to the receiver and the subsequent proceeding is a suit or action brought by the claimant. We are not required to pass beyond the fact that the claimant has no right of action and the surety company no liability cognizable in this action or proceeding. Whatever right of action was in the claimant or liability on the part of the surety was conditioned upon the use of the statutory remedy. Divorced from that remedy the right and the liability are non-existent. The claimant should have conformed with the provisions of the statute and obtained in the statutory action and presented to the receiver a judgment establishing the validity and amount of his claim. His claim as presented was conditional and not absolute, and its allowance was error. (People v. Metropolitan Surety Co.,
For the reason stated the order of the Appellate Division should be affirmed, with costs. The first question should be answered in the negative and the second question remain unanswered.
United States Fidelity & Guaranty Co. v. United States for ... , 27 S. Ct. 381 ( 1907 )
United States v. Congress Construction Co. , 32 S. Ct. 44 ( 1911 )
Fourth Nat. Bank of NY v. Francklyn , 7 S. Ct. 757 ( 1887 )
Title Guaranty & Trust Co. of Scranton v. Crane Co. , 31 S. Ct. 140 ( 1910 )
The Harrisburg , 7 S. Ct. 140 ( 1886 )
United States v. Ansonia Brass & Copper Co. , 31 S. Ct. 49 ( 1910 )
Philip Carey Co. v. Maryland Casualty Co. , 201 Iowa 1063 ( 1926 )
Paul Schoonover, Inc. v. Ram Construction Inc. , 129 Ariz. 204 ( 1981 )
Mapes v. Foster , 38 Wyo. 244 ( 1928 )
Mineral Resources, Inc. v. Mahnomen Construction Co. , 289 Minn. 412 ( 1971 )
Minneapolis-Honeywell Regulator Co. v. Terminal ... , 41 N.J. 500 ( 1964 )