Judges: Cabdozo, McLaughlin
Filed Date: 1/25/1921
Status: Precedential
Modified Date: 10/19/2024
I dissent. The plaintiff did not perform its contract. Its failure to do so was either intentional or due to gross neglect which, under the uncontradicted facts, amounted to the same thing, nor did it make any proof of the cost of compliance, where compliance was possible.
Under its contract it obligated itself to use in the plumbing only pipe (between 2,000 and 2,500 feet) made by the Reading Manufacturing Company. The first pipe delivered was about 1,000 feet and the plaintiff's superintendent then called the attention of the foreman of the subcontractor, who was doing the plumbing, to the fact that the specifications annexed to the contract required all pipe used in the plumbing to be of the Reading Manufacturing Company. They then examined it for the purpose of ascertaining whether this delivery was of that manufacture and found it was. Thereafter, as pipe was required in the progress of the work, the foreman of the subcontractor would leave word at its *Page 246 shop that he wanted a specified number of feet of pipe, without in any way indicating of what manufacture. Pipe would thereafter be delivered and installed in the building, without any examination whatever. Indeed, no examination, so far as appears, was made by the plaintiff, the subcontractor, defendant's architect, or any one else, of any of the pipe except the first delivery, until after the building had been completed. Plaintiff's architect then refused to give the certificate of completion, upon which the final payment depended, because all of the pipe used in the plumbing was not of the kind called for by the contract. After such refusal, the subcontractor removed the covering or insulation from about 900 feet of pipe which was exposed in the basement, cellar and attic, and all but 70 feet was found to have been manufactured, not by the Reading Company, but by other manufacturers, some by the Cohoes Rolling Mill Company, some by the National Steel Works, some by the South Chester Tubing Company, and some which bore no manufacturer's mark at all. The balance of the pipe had been so installed in the building that an inspection of it could not be had without demolishing, in part at least, the building itself.
I am of the opinion the trial court was right in directing a verdict for the defendant. The plaintiff agreed that all the pipe used should be of the Reading Manufacturing Company. Only about two-fifths of it, so far as appears, was of that kind. If more were used, then the burden of proving that fact was upon the plaintiff, which it could easily have done, since it knew where the pipe was obtained. The question of substantial performance of a contract of the character of the one under consideration depends in no small degree upon the good faith of the contractor. If the plaintiff had intended to, and had complied with the terms of the contract except as to minor omissions, due to inadvertence, then he might be allowed to recover the contract price, less the amount *Page 247
necessary to fully compensate the defendant for damages caused by such omissions. (Woodward v. Fuller,
What was said by this court in Smith v. Brady (supra) is quite applicable here: "I suppose it will be conceded that everyone has a right to build his house, his cottage or his store after such a model and in such style as shall best accord with his notions of utility or be most agreeable to his fancy. The specifications of the contract become the law between the parties until voluntarily changed. If the owner prefers a plain and simple Doric column, and has so provided in the agreement, the contractor has no right to put in its place the more costly and elegant Corinthian. If the owner, having regard to strength and durability, has contracted for walls of specified materials to be laid in a particular manner, or for a given number of joists and beams, the builder has no right to substitute his own judgment or that of others. Having departed from the agreement, if performance has not been waived by the other party, the law will not allow him to allege that he has made as good a building as the one he engaged to erect. He can demand payment only upon and according to the terms of his contract, and if the conditions on which payment is due have not been performed, then the right to demand it does not exist. To hold a different doctrine would be simply to make another contract, and would be giving to parties an encouragement to violate their engagements, which the just policy of the law does not permit." (p. 186.)
I am of the opinion the trial court did not err in ruling on the admission of evidence or in directing a verdict for the defendant.
For the foregoing reasons I think the judgment of the Appellate Division should be reversed and the judgment of the Trial Term affirmed.
HISCOCK, Ch. J., HOGAN and CRANE, JJ., concur with CARDOZO, J.; POUND and ANDREWS, JJ., concur with McLAUGHLIN, J.
Order affirmed, etc. *Page 249
Andrulis v. Levin Construction Corp. ( 1993 )
First Mortg. Co. of Pa. v. Carter ( 1982 )
In Re Moses N. Aslan, Debtor. Moses N. Aslan Irving ... ( 1990 )
Rhode Island Turnpike & Bridge Authority v. Bethlehem Steel ... ( 1977 )
H.L.C. & Associates Construction Company, Inc. v. The ... ( 1966 )
Coca-Cola Bottling Co. of Elizabethtown, Inc. v. Coca-Cola ... ( 1988 )
Superior Motels, Inc. v. Rinn Motor Hotels, Inc. ( 1987 )
John's Insulation, Inc. v. Hartford Accident & Indemnity Co.... ( 1998 )
Okaw Drainage District of Champaign and Douglas County, ... ( 1989 )
Latz v. Latz A/K/A Schafer ( 1971 )
Taco Bell Corp. v. Continental Casualty Co. ( 2004 )
Moulton Cavity & Mold, Inc. v. Lyn-Flex Industries, Inc. ( 1979 )
Deems v. Western Maryland Railway Co. ( 1967 )
Groves v. John Wunder Co. ( 1939 )
Mount Sinai Hospital v. Borg-Warner Corp. ( 1981 )
Bear, Stearns Funding, Inc. v. Interface Group-Nevada, Inc. ( 2005 )
Warden v. McGraw-Hill Companies, Inc. ( 2000 )
International Fidelity Insurance v. County of Rockland ( 2000 )