Citation Numbers: 196 N.E. 9, 267 N.Y. 161, 1935 N.Y. LEXIS 1201
Judges: Lehman
Filed Date: 4/16/1935
Status: Precedential
Modified Date: 10/19/2024
In June, 1930, the State of New York awarded to William Bailey Corporation a contract for the construction of a section of a public highway. The work was completed and accepted on September 16, 1931. The plaintiff filed a notice of lien on October 16, 1931. No other notices of lien and no assignments of the contract or of moneys due thereunder were filed within thirty days after the completion of the work. At that time a balance of $8,838.16 was still due from the State on the contract. The priority of the plaintiff's lien over all other claims upon this fund is undisputed. The dispute concerns only the manner in which the balance of this fund must be distributed. The contractor William Bailey Corporation has made a series of written assignments of moneys earned under its contract with the State. These assignments were executed and filed after the time in which liens may be filed had expired. They were given for indebtedness which had accrued before the assignments were made. The judgment granted at Special Term provides for a proportionate distribution upon all the assignments regardless of the time when the assignments were executed or filed. The Appellate Division modified the judgment and directed that the unpaid balance should be applied upon the assignments in the same order in which they were filed.
At common law a contractor could, by assignment of a contract or moneys earned thereunder, transfer to a third party a fund which was created through labor and materials *Page 164
furnished by subcontractors and from which such subcontractor expected to be paid. (Bates v. Salt Springs Nat. Bank,
By recent amendments to the Lien Law the Legislature has provided a more equable distribution of moneys earned upon a public contract. An assignee, by filing his assignment "prior to the filing of a notice of lien or assignment of every other party to the action" obtains *Page 165 priority over liens or assignments filed thereafter only "to the extent of advances made upon such assignment before the filing of the notice of lien or assignment next subsequent to his assignment, but as to advances made subsequent to a notice of lien or assignment filed and unsatisfied such assignee for the purpose of determining his proportionate share of moneys available for distribution as provided in subdivision four of this section shall be treated as a lienor having a lien to the extent of advances so made." (§ 25, subd. 1.) In the same way an assignee "whose assignment is duly filed subsequent to the filing of the notice of lien or assignment of any other party shall for the purpose of determining his proportionate share of moneys available for distribution, as provided in subdivision four of this section be treated as a lienor having a lien to the extent of advances actually made upon such assignment prior to the filing thereof." (§ 25, subd. 2.) "Moneys available for distribution among lienors of any class shall be distributed prorata in accordance with their respective valid liens." (§ 25, subd. 4.)
In terms, section
For definition of the rights of these assignees to any balance remaining after liens and assignments under section 25 are satisfied, we must look to the other provisions of the statute or to the common law.
Concededly the contractor has no right to such balance after he has assigned all moneys due under his contract to these assignees. They or some of them must stand in his place, and they stand in his place in the order in which their assignments became valid, in accordance with section 16; that is, in the order in which they were filed. Assignments of moneys made after the assignor had already effectively assigned all the money earned under the contract, can pass nothing to the assignees.
The Appellate Division so held, and the judgment entered upon its decision so provides. Under that judgment the first two assignees receive payment of their claims in full instead of prorata with the other assignees. Miller-Grey, Inc., the second assignee, failed, however, to appeal from the judgment of Special Term, and that judgment cannot be increased in its favor. It has not appeared upon this appeal to defend the increased judgment.
The judgment should be modified to the extent that the amount payable to Miller-Grey, Inc., is reduced to the amount in the original judgment, and as modified affirmed with costs to the respondent Pennsylvania-Dixie Cement Corporation.
CRANE, Ch. J., O'BRIEN, HUBBS, CROUCH, LOUGHRAN and FINCH, JJ., concur.
Judgment accordingly. *Page 167