Judges: Rippey
Filed Date: 2/28/1939
Status: Precedential
Modified Date: 10/19/2024
Plaintiff appeals, by permission of this court, from a judgment entered upon the order of the Appellate Division, first department, unanimously affirming the judgment entered upon an order of Special Term dismissing the first cause of action on motion of defendant under rule 106 of the Rules of Civil Practice on the ground that the complaint did not state facts sufficient to constitute a cause of action.
Plaintiff alleges that defendant and one Charles had entered into an agreement prior to July 16, 1936, whereby Charles agreed to do certain pipe installation and other work in connection with a heating plant that defendant was installing in the Lombardy Hotel and in adjacent buildings in New York city, that Charles had purchased certain materials from plaintiff and owed a balance thereon for which plaintiff was about to file a mechanic's lien against the real property in course of improvement and against defendant and Charles, and that Charles had stopped work because of disagreements with defendant. It appears that defendant had the general contract for the work and that Charles was its subcontractor.
The plaintiff further alleges that the plaintiff, Charles and defendant thereupon entered into a tripartite agreement in writing which is made a part of the complaint. It is this contract which furnishes the basis for the cause of action which has been dismissed. In the contract, it is recited that differences have arisen between the parties under the subcontract, that Charles has filed a lien against the property and that defendant has made certain payments to Charles for work already done under the contract. Charles agreed to waive any right which he might have on the lien filed and to any claim against defendant by lien or otherwise for past or future labor and services upon payment by defendant to Charles or to his assignee of $950. Charles agreed promptly to proceed with and complete the *Page 53 work remaining to be done. Plaintiff agreed to furnish the necessary materials for completion of the work and to waive any right to a lien on the premises or to any further claim for payment for the materials already furnished or to be furnished on payment by defendant to it of the sum of $2,800 at its request "five days after the completion of the installation by said Thomas J. Charles in accordance with the contract or purchase orders No. 943, etc., above referred to and the specifications accompanying the same and approval of the same by Edwin A. Kingsley, engineer for Petroleum Heat Power Company, Inc."
Charles failed to complete the installation and defendant finished the work. Plaintiff refrained from filing any lien and furnished all materials required for the completion of the contract and alleges that it fully performed all obligations specified in the contract to be performed by it. Defendant refused to pay the $2,800 which it agreed to pay on the sole ground that Charles personally did not complete the work. In the complaint, it is alleged that it was intended and agreed between the parties that the sum of $2,800 should be paid by defendant to plaintiff five days after the completion of the work or within a reasonable time thereafter and that "said completion bore upon plaintiff's right of payment solely as convenient means of fixation of the time thereof, and not as condition precedent to the right of such payment and the parties intended said right of payment should be absolute." To sustain the complaint, plaintiff is entitled to every favorable inference that reasonably may be drawn from the allegations that it contains.
Defendant claims, so far successfully, that completion of the installation by Charles was a condition precedent to its liability under the contract and much reliance is placed onAmies v. Wesnofske (
It is true that the time of payment to plaintiff was to be fixed by the consummation of a condition, but that condition was that the subcontract between Charles and defendant should be completed, that the work should be approved by defendant's representative and that five days should elapse thereafter before payment could be required. The finishing of the work by Charles individually was not a material part of the contract between plaintiff and defendant. It might have been material as between Charles and the defendant. The promise of defendant to pay was independent of the completion of the work by Charles individually, the time of payment being based alone on the happening of the condition stated (Childs v. Smith,
The fundamental rule in the construction of all agreements is to ascertain the substantial intent of the parties (Kennedy v.Porter,
Upon the facts appearing in the complaint in this case, hairline distinctions will not be drawn nor circuitous reasoning indulged nor technicalities relied on to bar recovery on a contract based on valid considerations which has for its purpose the securing of payment of what appears to be a just debt where the intent that it should be paid is clear. If the agreement is capable of a construction which will make it valid and enforceable, that construction will be placed on it (3 Williston on The Law of Contracts [Rev. ed.], § 769; Archibald v.Thomas, 3 Cow. 284, 290; Standard Oil Co. v. Scofield, 16 Abb. New Cases, 372; Hoffman v. AEtna Ins. Co.,
The judgments should be reversed and the motion denied, with costs in all courts, and ten dollars costs of motion. (See
CRANE, Ch. J., O'BRIEN, HUBBS, LOUGHRAN and FINCH, JJ., concur; LEHMAN, J., taking no part.
Judgments reversed, etc.
Acushnet Company v. Beam, Inc. ( 2018 )
Nederlandse Draadindustrie NDI B v. v. Grand Pre-Stressed ... ( 1979 )
Singer Products Co. v. First American Bank of New York (In ... ( 1989 )
Flli Moretti Cereali S.P.A. v. Continental Grain Company ( 1977 )
Alaska Pacific Salmon Co. v. Reynolds Metals Co. ( 1947 )
Dorsey v. Oregon Motor Stages ( 1947 )
mcnally-wellman-company-a-division-of-boliden-allis-inc ( 1995 )
Marvin Stern, and Cross-Appellant v. Satra Corporation and ... ( 1976 )
richard-e-sayers-v-the-rochester-telephone-corporation-supplemental ( 1993 )
Venizelos, S.A. v. Chase Manhattan Bank ( 1970 )
schiavone-construction-company-inc-and-edward-b-fitzpatrick-jr ( 1983 )
Schering Corp. v. Home Insurance ( 1982 )
In Re the Arbitration of Controversies Between Old Dutch ... ( 1963 )
Division of the Triple T Service, Inc. v. Mobil Oil Corp. ( 1969 )
Skandia America Reinsurance Corp. v. Schenck ( 1977 )
Warner Bros. Pictures, Inc. v. Columbia Broadcasting System,... ( 1951 )
Lubrication & Maintenance, Inc. v. Union Resources Co. ( 1981 )
United States v. Jacobs ( 1969 )
Corning Glass Works v. Southern New England Telephone Co. ( 1987 )