Judges: Parker
Filed Date: 3/15/1867
Status: Precedential
Modified Date: 11/15/2024
The plaintiff was a contractor .with the Buffalo, New York and Erie Railroad company, to lay its track and superstructure from Attica to Batavia, a distance of eleven miles. By the contract, he was to receive the materials, iron, ties and spikes, from the company at Attica and Batavia, and himself distribute them for use, between the two places. The defendant’s railroad ran between these places, parallel to and so near the railroad which the plaintiff was employed to build, that the materials above mentioned could conveniently be distributed from defendant’s cars at the places where the plaintiff wanted them for use; and he contracted with the defendants to do this work of distribution for him, at a price equal to the actual cost to defendant of doing the same. The defendant commenced distributing pursuant to its agreement with the plaintiff, and, after doing a small portion of the work, refused to proceed; and plaintiff was obliged to resort to other means of having this work done, at an increased expense to himself, and, to recover from the defendant his damages arising therefrom, he brings this action.
The suit was tried before a referee, who found a contract between the parties as follows; “ That the said plaintiff, in the
In- regard to the breach of the contract by the defendant, and the quantity of material which the plaintiff was obliged to have transported by other means, and the expense of such transportation, as compared with what it would have cost him if the defendant had transported it, there is evidence in the case tending to the conclusions of fact arrived at by the referee. The correctness of these conclusions, therefore, is not here open to review.
There is but a single exception in this case, beyond the exceptions filed to the findings of fact, and the general exception that the judgment should have been for the defendant. Upon the trial, after giving evidence tending to prove his contract with the defendant; the amount of work done by defendant upon it; the amount left undone, and defendant’s refusal to do any more; the mode then adopted by plaintiff for distributing the residue of the materials, to wit: part by
The objection, in terms, is broad enough to include all the testimony which Miller had given. There is nothing to point the expression “this evidence” to the last sentence rather than to the whole, as there should have been if the last sentence alone was to be included in the objection; and, as some portions of Miller’s evidence is clearly unexceptionable, the objection, being too broad in that view, must go for nothing.
But, if the objection were confined to the sentence giving the comparative cost of laying the track before and after the rails were placed in situ, as described, I think this fact a proper one to prove; for it is the fact to which the objection points, and not the mode of proving it. This extra cost of laying the track was in effect but the extra cost of doing the work which the defendant was to do, for the track was thus partially laid as a part of the work necessary in transporting the ties; it was virtually laying down a temporary track on which to transport the materials, and after they were transported taking it up again, and then,.with the materials thus brought upon the ground, together with what was there
Indeed, regarding this extra expense as applicable exclusively to the cost of the superstructure, as the witness gave it, inasmuch as it was the direct and immediate result of the materials not being distributed as defendant undertook to distribute them, it is an injury for which the plaintiff was entitled to recover.
I am of the opinion that the judgment should be affirmed.
All the judges concurring,
Judgment affirmed.