DocketNumber: Claim No. 78016
Judges: Carpinello
Filed Date: 7/22/2004
Status: Precedential
Modified Date: 11/1/2024
Appeal from a judgment of the Court of Claims (Corbett, Jr., J.), entered July 3, 2003, upon a decision of the court in favor of claimant.
At issue is an $185,000, plus interest, damage award to Tougher Industries, Inc., a subcontractor of claimant on a correctional facility construction project. Damages were awarded to Tougher, which had a liquidating agreement with claimant, as a result of defendant’s failure to properly coordinate the project. Defendant does not take issue with the substantive finding that it caused delays in this project; rather, on appeal, it claims that a contractual notice provision in the contract between itself and claimant was not complied with by Tougher, that a particular exhibit was improperly admitted into evidence at trial and that the damage award itself is based upon speculative evidence. None of these contentions has merit; accordingly, we affirm.
As the contract between claimant and defendant did not require Tougher, as a subcontractor, to give independent notice of its claim to defendant, we reject defendant’s contention that Tougher’s claim should be dismissed on this ground (cf. Tug Hill Constr. v County of Broome, 270 AD2d 755, 756-757 [2000]). Nor do we find any error in the Court of Claims’ evidentiary decision to admit claimant’s exhibit No. 130 into evidence since the testimony of several witnesses sufficiently established the contents as business records (see CPLR 4518 [a]). Even if the court erred, such error was harmless given the testimonial evidence on the issue of damages.
Finally, with respect to defendant’s argument that Tougher’s
Defendant’s remaining contentions have been reviewed and rejected as being without merit.
Cardona, EJ., Peters, Spain and Kane, JJ, concur. Ordered that the judgment is affirmed, without costs.