Citation Numbers: 20 A.D.3d 448, 798 N.Y.S.2d 518
Filed Date: 7/11/2005
Status: Precedential
Modified Date: 11/1/2024
Ordered that the order is affirmed, without costs or disbursements.
The lease between the parties provided that the “Tenant shall undertake all Construction Work, including, without limitation, the Construction Work required in connection with the construction of the Required Capital Improvements.” “Construction Commencement Date” with respect to “Required Capital Improvements” was defined as “a date occurring within 2 years of the Commencement Date” of the lease on November 1, 2000. Article 27.01 (c) of the lease provided that “if Tenant shall fail to commence construction of the Required Capital Improvements within 24 months of the commencement date of the lease” the tenant could be held in default.
On November 19, 2002, the defendant landlord sent the plaintiff tenant a notice to cure stating that the tenant failed to “commence construction of the Required Capital Improvements within 24 months of the commencement date of the Lease” and if the default was not cured on or before December 17, 2002, the lease would be terminated. On December 13, 2002, the tenant commenced the instant action and sought a Yellowstone injunction (see First Natl. Stores v Yellowstone Shopping Ctr., 21 NY2d 630, 638 [1968]), which was granted by the Supreme Court in an order dated April 15, 2003.
The defendant moved for summary judgment, inter alia, dismissing the complaint and for a declaration that the lease “is
The Supreme Court denied the motion and the cross motion, stating that there were issues of fact as to whether the defendant’s course of conduct constituted “a waiver of its right to insist upon commencement of construction by the contractual deadline.”
Contrary to the plaintiffs contention, the proposed building constituted a “Required Capital Improvement” described in the lease. However, the defendant failed to establish, as a matter of law, that it complied with the provision of the lease that required it to cooperate with the plaintiff in obtaining the required permits from governmental authorities. Further, we agree with the Supreme Court that there are triable issues of fact as to whether the defendant waived its right to insist upon commencement of construction by the contractual deadline.
Accordingly, the motion and the cross motion were properly denied. Prudenti, PJ., Goldstein, Crane and Mastro, JJ., concur.