Filed Date: 11/16/2006
Status: Precedential
Modified Date: 11/1/2024
Order, Supreme Court, New York County (Richard E Braun, J.), entered April 21, 2005, which, to the extent appealed from, denied plaintiff’s motion for partial summary judgment on its cause of action seeking liquidated damages for breach of contract, unanimously modified, on the law, to the extent of granting that portion of the motion which, in essence, sought a declaration that the liquidated damages clause is enforceable, and not an unenforceable penalty, and otherwise affirmed, without costs.
There are questions of fact as to whether plaintiff restricted access to defendant’s building, thereby breaching the agreement and causing delay in performance of the work. Accordingly, Supreme Court properly denied plaintiffs motion for summary judgment on the issue of liability on its first cause of action seeking liquidated damages.
Supreme Court erred, however, in denying that aspect of the motion which, in essence, sought a declaration that the liquidated damages clause is, as a matter of law, enforceable, rather than being an unenforceable penalty. Plaintiff made a prima facie showing both that damages flowing from the alleged breach were, at the time the parties entered into the agreement, difficult to ascertain and that the provision fixing damages is a reasonable measure of the anticipated probable harm (see Truck Rent-A-Ctr. v Puritan Farms 2nd, 41 NY2d 420, 423-424 [1977]).