Filed Date: 12/30/2008
Status: Precedential
Modified Date: 11/1/2024
Pursuant to a contract dated March 8, 2000, the plaintiff agreed to install an irrigation system at a golf course owned by the defendant. The contract provided that, if the system was not “installed and fully operational” by May .26, 2000 the plaintiff would be liable to the defendant for liquidated damages in the sum of $200 for each day of delay. After recurrent problems with the system, which necessitated frequent repairs and a modification of a major component, the system became
A contractual provision for liquidated damages will be upheld only if the amount fixed is a reasonable measure of the probable actual loss in the event of a breach, and the actual loss suffered is impossible or difficult to determine with precision (see JMD Holding Corp. v Congress Fin. Corp., 4 NY3d 373, 380 [2005]; Evangelista v Ward, 308 AD2d 504, 505 [2003]). If, however, the amount of actual damages that would be suffered upon a breach is readily ascertainable when the contract is entered, or the amount fixed as liquidated damages is conspicuously disproportionate to the foreseeable losses, the liquidated damages provision is unenforceable as a penalty (see Bates Adv. USA, Inc. v 498 Seventh, LLC, 7 NY3d 115, 120 [2006]). Where a court finds a liquidated damages provision enforceable, the measure of damages for a breach will be the sum fixed in the clause, no more, no less (see JMD Holding Corp. v Congress Fin. Corp., 4 NY3d at 380; Zeer v Azulay, 50 AD3d 781, 785 [2008]). Where, however, a liquidated damages provision is found to be an unenforceable penalty, the recovery is limited to actual damages proven (see Bates Adv. USA, Inc. v 498 Seventh, LLC, 7 NY3d at 120; Zeer v Azulay, 50 AD3d at 786; Jackson Hgts. Care Ctr., LLC v Bloch, 39 AD3d 477, 479 [2007]). Here, by fixing the amount of liquidated damages at $50,000, less than one third of the amount that would have been due under the liquidated damages provision of the contract, the Supreme Court implicitly found that the liquidated damages clause did not constitute a reasonable measure of the probable actual loss and, therefore, amounted to a penalty. Consequently, it should not have
Without any setoff for liquidated damages, the plaintiff is entitled to judgment in the principal sum of $11,104.27, plus statutory interest from May 26, 2000. That sum represents the amount due and owing on the contract.
The parties’ remaining contentions either are without merit or need not be reached in light of our determination. Skelos, J.P., Fisher, Dickerson and Belen, JJ., concur.