Citation Numbers: 69 A.D.3d 435, 894 N.Y.2d 14
Filed Date: 1/7/2010
Status: Precedential
Modified Date: 11/1/2024
Certificates of substantial completion were executed more than three months prior to plaintiff contractor’s filing its notice of claim for three of the four contracts on which it sought to recover. Such certificates fixed the date on which damages were ascertainable, and therefore when plaintiffs claim accrued (see C.S.A. Contr. Corp. v New York City School Constr. Auth., 5 NY3d 189, 192 [2005]; Koren-DiResta Constr. Co. v New York City School Constr. Auth., 293 AD2d 189, 191-192 [2002]). Accordingly, since three of plaintiffs contract claims accrued more than three months before the notice of claim is dated, they are barred by the late filing of the notice of claim.
Plaintiffs fourth contract claim is also time-barred as beyond the one-year statute of limitations set forth in Public Authorities Law § 1744 (2). Given that plaintiffs September 2002 notice of claim alleged that defendant breached the contract, it triggered the running of the one-year statute of limitations (.Koren-DiResta Constr. Co., 293 AD2d at 192), irrespective of whether or not plaintiff knew the precise amount of damages, or even if no damages occur until later (see Ely-Cruikshank Co. v Bank of Montreal, 81 NY2d 399, 402 [1993]).
We decline to consider plaintiffs arguments relying on Lien Law article 3-A, which are improperly raised for the first time on appeal (see D.A.G. Floors, Inc. v St. Paul Mercury Ins. Co., 35 AD3d 207 [2006]). Were we to consider these arguments, we would find them unavailing. The fact that defendant may have paid plaintiffs subcontractors after the dates of substantial