Judges: Stein
Filed Date: 2/10/2011
Status: Precedential
Modified Date: 11/1/2024
Appeal from a decision of the Workers’ Compensation Board, filed March 29, 2010, which directed the employer’s workers’ compensation carrier to make a deposit into the aggregate trust fund pursuant to Workers’ Compensation Law § 27 (2).
Claimant sustained a work-related injury in 2004, and was found to suffer from a marked permanent partial disability in 2009. As his injury predated a 2007 amendment to Workers’ Compensation Law § 15 (3) (w), there is no “cap on the number of weeks for which [he] can receive that subdivision’s non-schedule permanent partial disability . . . benefits” (Matter of
We affirm. We have previously considered and rejected the majority of the challenges made by the employer and carrier to the relevant provisions of the Workers’ Compensation Law (see Matter of Proulx v Burnett Process, 77 AD3d at 1038; Matter of Parkhurst v United Rentals Aerial Equip., Inc., 75 AD3d 702, 704-705 [2010], lvs granted 15 NY3d 712 [2010]; Matter of Collins v Dukes Plumbing & Sewer Serv., Inc., 75 AD3d 697, 698-702 [2010], lv granted 15 NY3d 713 [2010], appeal dismissed and lv granted 15 NY3d 891 [2010]). Notwithstanding the urging of the employer and carrier, we do not discern any relevant factual distinctions between those earlier cases and the present one.
The remaining arguments of the employer and carrier have been reviewed and found to be without merit.
Peters, J.P., Kavanagh, Garry and Egan Jr., JJ., concur. Ordered that the decision is affirmed, without costs.