Citation Numbers: 82 A.D.3d 720, 917 N.Y.2d 687
Filed Date: 3/1/2011
Status: Precedential
Modified Date: 11/1/2024
The appeal from the order must be dismissed because the right of direct appeal therefrom terminated with the entry of judgment in the action (see Matter of Aho, 39 NY2d 241, 248
The defendant Volmar Construction, Inc. (hereinafter Volmar), was the general contractor on a construction project to renovate a school for the New York City School Construction Authority (hereinafter the SCA). The plaintiff subcontractor performed certain masonry work on the project. When Volmar failed to pay the plaintiff for the work performed, the plaintiff filed a notice of mechanic’s lien pursuant to Lien Law § 5, which Volmar discharged by obtaining a bond from the defendant Travelers Casualty and Surety Company of America (hereinafter Travelers) (see Lien Law § 21). The plaintiff commenced this action against, among others, Volmar and Travelers (hereinafter together the defendants), seeking, inter alia, to recover damages for breach of contract or in quantum meruit, and to foreclose its mechanic’s lien. The plaintiff moved, among other things, for summary judgment on its first, second, and third causes of action asserted against the defendants to the extent of awarding it the principal sum of $498,000, which it claimed was the amount of its subcontract. The Supreme Court granted those branches of the motion, and a judgment was entered in favor of the plaintiff and against the defendants in the principal sum of $498,000.
“[T]he existence of a binding contract is not dependent on the subjective intent” of the parties (Brown Bros. Elec. Contrs. v Beam Constr. Corp., 41 NY2d 397, 399 [1977]; see Mencher v Weiss, 306 NY 1, 7 [1953]). “In determining whether the parties entered into a contractual agreement and what were its terms, it is necessary to look, rather, to the objective manifestations of the intent of the parties as gathered by their expressed words and deeds” (Brown Bros. Elec. Contrs. v Beam Constr. Corp., 41 NY2d at 399; see Mencher v Weiss, 306 NY at 7; Matter of Express Indus. & Term. Corp. v New York State Dept. of Transp., 93 NY2d 584, 589 [1999]). “Generally, courts look to the basic elements of the offer and the acceptance to determine whether there is an objective meeting of the minds” (Matter of Express Indus. & Term. Corp. v New York State Dept. of Transp., 93 NY2d at 589). “The manifestation or expression of assent necessary to form a contract may be by word, act, or conduct which evinces the intention of the parties to contract” (Maffea v Ippolito, 247 AD2d 366, 367 [1998]; see Knight v Barteau, 65 AD3d 671, 672 [2009]).
Here, while a letter of intent to enter into a subcontract which was issued by Volmar to the plaintiff was expressly contingent
While the Supreme Court properly awarded the plaintiff summary judgment on its causes of action to recover damages for breach of contract and to foreclose its mechanic’s lien in the principal sum of $498,000, we note that the plaintiff was not entitled to an award of summary judgment on its second cause
The plaintiffs remaining contention is without merit.
Accordingly, the plaintiff was properly awarded judgment against the defendants in the principal sum of $498,000. Skelos, J.E, Covello, Balkin and Sgroi, JJ., concur.