Judges: McCarthy
Filed Date: 5/12/2011
Status: Precedential
Modified Date: 11/1/2024
Appeal from an order of the Supreme Court (Dowd, J.), entered April 13, 2010 in Otsego County, which denied defendant’s cross motion for summary judgment dismissing the complaint.
In 2002, plaintiff entered into a contract with defendant, an
In September 2007, plaintiff commenced this action alleging professional malpractice and breach of contract. After plaintiff moved for relief related to disclosure issues, defendant cross-moved for summary judgment dismissing the complaint. The parties resolved the disclosure issues.
Defendant did not prove as a matter of law that the action is time-barred. The applicable statute of limitations for a claim of architectural malpractice is three years, “regardless of whether the underlying theory is based in contract or tort” (CPLR 214 [6]; see Town of Wawarsing v Camp, Dresser & McKee, Inc., 49 AD3d 1100, 1101 [2008]). Such a claim “accrues upon the completion of performance under the contract and the consequent termination of the parties’ professional relationship” (Town of Wawarsing v Camp, Dresser & McKee, Inc., 49 AD3d at 1101-1102; see Board of Educ. of Tri-Val. Cent. School Dist. at Grahamsville v Celotex Corp., 88 AD2d 713, 714 [1982], affd 58 NY2d 684 [1982]). The time of completion must be determined based upon the terms of the contract and the parties’ responsibilities therein (see Board of Educ. of Tri-Val. Cent. School Dist. at Grahamsville v Celotex Corp., 88 AD2d at 714).
Here, integral portions of the contract required defendant to supply as-built drawings following the construction and to issue a certificate of completion for the contractor after conducting a final inspection and reviewing submitted documents (see id.; compare State of New York v Lundin, 60 NY2d 987, 989 [1983]).
Defendant issued the final certificate of completion to the contractor in November 2005. Contrary to defendant’s contention that this was merely a ministerial act of signing the certificate, the contract required defendant — prior to signing off on the completion of the project — to inspect the work, review numerous documents and certify that the work was properly completed and documented. Defendant argues that it had completed its duties, other than signing the certificate and delivering it, but that plaintiff requested that defendant delay those final actions while plaintiff resolved a dispute with the contractor.
Defendant also failed to establish as a matter of law that it performed in accordance with the relevant professional standards. In support of its motion, defendant submitted the affidavit of an expert who opined that defendant’s work on the project complied with the State Building Code. The expert did not state, however, that compliance with the Code is equivalent to
Even if defendant complied with industry standards, thus rendering it free from professional malpractice, defendant could still be held liable for a breach of contract. Parties are free to enter into a contract requiring performance at a level above that of the industry standard.
Even had defendant met its initial burden, plaintiff raised factual questions through submission of an expert affidavit specifically asserting how defendant’s designs did not comply with the IBC standards or accepted industry standards. The expert expressed this opinion with full knowledge that plaintiff terminated defendant’s services before undertaking phase two; he opined that the installation of the fourth shear wall under phase two would not make the building comply with seismic load standards and defendant’s designs supplied under phase one were deficient with or without the fourth wall. Hence, as questions of fact exist, Supreme Court properly denied defendant’s cross motion for summary judgment.
Spain, J.E, Lahtinen, Kavanagh and Egan Jr., JJ., concur. Ordered that the order is affirmed, with costs.
. The parties have previously been before this Court on a prior appeal also relating to disclosure (66 AD3d 1286 [2009]).
. The contract required defendant to participate in resolution of disagreements between plaintiff and the contractor. While defendant was apparently not asked to become involved in resolving this dispute, defendant was aware of the dispute and did not itself attempt to assist in the dispute’s resolution.
. Indeed, while defendant’s expert stated that the current edition of the State Building Code would not impose any seismic design requirements on plaintiffs building, this ignores plaintiffs purpose and desire, as reflected in the contract, to improve the building’s ability to withstand a seismic catastrophe.