Filed Date: 2/17/1981
Status: Precedential
Modified Date: 11/1/2024
In a condemnation proceeding, the claimant appeals, as limited by its brief, from so much of a final order of the Supreme Court, Nassau County, entered December 26, 1979, as awarded it only $15,800 for the taking of a certain parcel. Final order modified, on the law and the facts, by increasing the first taking award from $15,800 to $58,361. As so modified, final order affirmed insofar as appealed from, with costs to the appellant. The subject of this condemnation proceeding is a parcel of land located in Woodmere, Long Island, in the Residence B single-family district in which the minimum lot is 6,000 square feet. The parcel is improved with an estate-type house fronting on an 8.36 acre man-made elongated lake known as Lee Lake. The first taking (Jan. 10, 1974) was of the 8.36 acres of
“Value Before Taking Value After Taking (1) Total Damages
$2,000,000
786,475
$1,213,515 [sic; should be $1,213,525]
Comprised of:
Direct Damages
8.6938 acres at $100,000 ac. $ 869,300
Landscaping — dock & pilings 22,500
(Marshall Valuation Service)
Lake 210,000
Total Direct Damages $1,101,800
Remainder Non-Direct Damages
to Land and Improvements $ 111,715”.
The legal rationale for this theory is noted in the report of claimant’s appraiser, which quotes from a letter written by claimant’s counsel: “ ‘Together with you, we have concluded that traditional market approaches to valuing such lake would result in manifest injustice to the property owner. This result comes about because of the total lack of a market for private lakes in Nassau County and because utilization of comparable land sales presumes that the lake be filled, thus reversing the creation of the lake. This was the very reason the subject property was acquired by the Town of Hempstead. Valuing the land as filled (the alternative proposal) would result in a double loss to the property owner: the cost of creating the lake and the cost of filling the lake.’ ” We find no basis for an award on this “summation” theory, viz., the $210,000 depreciated reproduction cost of the lake on land to be purchased at $100,000 per acre. Lee Lake was artificially created by claimant by dredging it of fill, which was then used to develop nearby marshland into residential plots. It thus previously extracted value from the lake in the form of the prices obtained on the sale of those residential plots with a lake view. Immediately prior to this condemnation proceeding claimant was reversing the process, i.e., it had begun to fill in the lake land — again to develop and sell residential plots. Under all the circumstances, a “summation” award whether on a specialty theory (see Matter of County of Nassau [Colony Beach Club of Lido], 43 AD2d 45, afid 39 NY2d 958), or some “manifest injustice” concept (see Matter of Port Auth. Trans-Hudson Corp. [Hudson Rapid Tubes Corp], 20 NY2d 457, 469; Matter of City of New York [Fifth Ave. Coach Lines], 18 NY2d 212; City of New York v State of New York, 49 AD2d 659) is unwarranted. The town’s appraiser was of the opinion that “because the subject property is zoned Residence ‘B’, permitting one-family construction on 6,000 square feet, the subject property as a one-family residence enjoys excess lands which have been analyzed on the basis of their potential for residential development.” Noting that the property could be divided into four major areas (Parcels A [approximately 1.45 acres],
“Estimated Gross Value 8.36 raw acres x $92,000. per acre
(if at grade) R.F. $769,100.
Extraordinary Costs (to bring subject property to grade)
Fill 645,812.
Storm Drainage 268,880.
Retaining Wall 30,565.
Storm Drainage at Retaining Wall 28,880.
Engineering $ 26,000.
$1,000,137.
R.F. $1,000,100.”
He therefore concluded that development of the 8.36-acre lands under water was not economically feasible since the direct costs alone exceeded by $231,000 the value created. Furthermore, there would be additional costs for carrying the property while it was being filled, plus costs for the normal development of raw acreage such as road pavement, sidewalks, curbs, aprons, and sanitary sewers. Nevertheless, the appraiser concluded that no property is totally without value and evaluated it on the basis of $1,000 per acre for a rounded value estimate of $8,500. Special Term agreed with that assessment: “In summary, the Court finds the claimant suffered only nominal damages in the taking of Lee Lake *** and makes no award except for $15,800 which includes nominal damages of $8,500 for the lake, $800 for the surface easements acquired in the taking, and the remainder for the loss of riparian rights and the dock.” As may be seen, the major cost items that resulted in the town appraiser’s conclusion that making the property usable for residential development would result in a loss of $231,000, are the $645,812 cost of purchasing and installing fill and the $268,880 storm drainage item. The $645,812 item was derived from an engineering study commissioned by the town which reported that residential development of Parcel B would require 311,250 cubic yards of fill at a unit price of $1.85, the total cost of which would be $575,812 plus $70,000 to place the fill. We find, however, that the town experts’ cost estimates were based on the unnecessary and erroneous assumptions that the property (if filled to grade) would be developed to its maximum, yielding 50 plots; that a rigidly prescribed schedule would have to be followed in order that claimant not breach its obligations under the easement agreement; and that such 50-lot
“Assuming Lot Yield Explanation At 39 At 30 Total costs per Carlin [town’s engineering expert] * * * $1,275,591 $1,275,591 Less Savings: (a) By using free fill $ 575,812 $ 575,812 (b) By piping for easement #1 85,200 (c) By eliminating 84” pipe for open ditch #1 easement 227.200 TOTAL SAVINGS 661,012 803,012 Corrected Costs $ 614.579 1 472.579 Value ready to build found by Special Term 810,726 623,640 * * * Less corrected costs 614,579 472,579 Indicated value ‘As-Is’ $ 196,147 $ 151.061”.
We find that the testimony, the easement agreement and other exhibits in this factually complex case support and require an award to claimant on the above alternative theory on the basis of a 30-lot yield, but that in view of the range of evidence as to the cost of fill, claimant’s estimated “free fill” saving of $575,812 is excessive. Just as the town’s evidence that development would require 311,250 cubic yards of fill at $1.85 a cubic yard (total of $575,812) is based upon erroneous assumptions of maximum lot development, a rigid time schedule, and a misreading of the easement agreement, claimant’s contention that fill could be obtained entirely free is partially erroneous. Its witness, Joseph Farley, executive vice-president of a large contractor, testified that he probably could get 200,000 yards of fill “for nothing” and could actually charge someone to dump a certain type of fill “and perhaps I may have to pay a dollar to $1.50, let us say for 50,000 yards, but I definitely would incur income if I had this hole in'the ground” (emphasis supplied). Joseph Gibbons, chief engineer and vice-president of a construction company, testified on behalf of claimant that “in those years [1974-1978] on the sewer contracts that we were doing” his company averaged a surplus of suitable fill of approximately 80,000 to 100,000 yards per contract. During 1974 and 1975 the company had at least four contracts and was dumping fill in various areas. Gibbons declared that his company did deliver fill for as much as $20 a load, but that was a very small amount compared to what was actually dumped for nothing. In view of the range and quality of the evidence,