Citation Numbers: 132 A.D.2d 105, 522 N.Y.S.2d 679, 1987 N.Y. App. Div. LEXIS 49552
Judges: Weiss
Filed Date: 11/25/1987
Status: Precedential
Modified Date: 10/28/2024
OPINION OF THE COURT
Petitioner commenced the instant CPLR article 78 proceeding seeking to compel respondent to issue a mining permit pursuant to the provisions of the Mined Land Reclamation Law (ECL art 23, tit 27 [hereinafter MLRL]), or, in the alternative, to redesignate itself as the lead agency on petitioner’s pending permit application. A brief recitation of the underlying events is in order.
On or about August 2, 1985, petitioner applied to respondent for a permit to mine sand and gravel on an 18-acre parcel located in the Town of Smithtown, Nassau County (see, ECL 23-2711 [1]). Respondent classified the project as type I for purposes of review under the State Environmental Quality Review Act (ECL art 8 [hereinafter SEQRA]) and, on September 26, 1985, designated the town as "lead agency”. Respondent thereafter rejected petitioner’s request that it redesignate itself as lead agency, finding that the town was not without jurisdiction to act in this capacity. In the meantime, the town requested additional information from petitioner, the last of which was provided on February 6, 1986. One week later, the town returned petitioner’s application on the premise that it "no longer accepted] applications for regrading and excavating permits”. By letter dated February 28, 1986, petitioner notified both the town and respondent that the town’s failure to make a timely determination of environmental significance as required by 6 NYCRR former 617.6 (d) (2)
In our view, Supreme Court erred in granting petitioner summary judgment and directing the issuance of a mining permit. The initial premise underlying petitioner’s argument is that the town’s failure to make a determination of environmental significance by February 21, 1986, i.e., 15 days after receiving all pertinent information, resulted in a de facto declaration of nonsignificance for purposes of SEQRA review. Once this occurred, petitioner maintains that respondent was obligated to make a decision on the permit request within 90 days pursuant to the Uniform Procedures Act (ECL art 70 [hereinafter UPA]) (see, ECL 70-0109 [3] [a] [i]). Since respondent ostensibly failed to timely respond to petitioner’s May 1, 1986 demand letter, petitioner concludes that the permit must be granted (see, ECL 70-0109 [3] [b]). The argument fails for several reasons.
It is undisputed that the town did not comply with the 15-day time limitation set forth in 6 NYCRR former 617.6 (d) (2). Petitioner, however, has misperceived the consequence of the town’s delay. By its terms, the regulation does not provide any penalty for untimeliness. In our view, the regulation does not work a limitation on the actual authority of a lead agency to complete SEQRA review and is directory rather than mandatory in nature (see, Matter of Grossman v Rankin, 43 NY2d 493, 501; Matter of Tri Cities Indus. Park v Commissioner of Dept. of Envtl. Conservation, 76 AD2d 232, 236, lv denied 51 NY2d 706; compare, Matter of 400 Del. Ave. Prop. Co. v State of New York Div. of Hous. & Community Renewal, 105 AD2d 1046). Thus, the town’s delay did not, as petitioner suggests, result in a de facto negative declaration.
Petitioner would have us superimpose the default provision delineated in ECL 70-0109 (3) (b) on the SEQRA regulation in
It is evident that the UPA default provisions are mandatory, not directory in nature. We do not, however, deem it appropriate to impose the UPA strictures on the pertinent SEQRA regulations. Significantly, the UPA accommodates an instance where, as here, a lead agency other than respondent undertakes SEQRA review. ECL 70-0109 (4) specifically tolls the 90-day time period within which respondent is required to rule on a permit application pending the completion of the SEQRA review process by the lead agency (see, Tayntor v New York State Dept. of Envtl. Conservation, 130 AD2d 571). This provision evinces a legislative recognition that the time limitations delineated in the UPA must be distinguished from the SEQRA review process. This is not to suggest that a lead agency enjoys unbridled authority to delay SEQRA review, but the short delay here was clearly not excessive as a matter of law (see, Matter of East Clinton Developers v Town of Clinton, 88 AD2d 416, 423).
It follows that respondent properly rejected petitioner’s May 1, 1986 demand letter as premature (see, Tayntor v New York State Dept. of Envtl. Conservation, supra, at 572). The event triggering the 90-day time limit delineated in ECL 70-0109 (3) (a) (i) is the completion of the permit application. But the application cannot be considered complete until SEQRA review is concluded, either when the lead agency makes a negative declaration or, in the case of a positive declaration, a draft environmental impact statement (hereinafter DEIS) is approved and a final environmental impact statement (hereinafter FEIS) is filed with respondent (ECL 8-0109 [4], [5]; 70-0105 [2]; 6 NYCRR 617.3 [former (e)]; 621.3 [a] [5]; see, Tayntor v New York State Dept. of Envtl. Conservation, supra,). As
Here, the town made a positive declaration on March 20, 1986 and petitioner has apparently submitted a DEIS. Since a FEIS has yet to be filed with respondent and the time requirements imposed by ECL 70-0109 remain tolled pursuant to ECL 70-0109 (4), petitioner’s permit demand is premature and respondent is precluded from acting on the application (see, 6 NYCRR 617.3 [former (a)]; 621.9 [a] [4]; Matter of East Clinton Developers v Department of Envtl. Conservation, 109 Misc 2d 786). Accordingly, Supreme Court erred in directing the issuance of a mining permit. We further emphasize that relief in the nature of mandamus to compel the issuance of a permit was not appropriate here since petitioner failed to establish a clear right to the relief sought; respondent performs a discretionary, not a mere ministerial, function in reviewing permit applications (see, Matter of Atlantic Cement Co. v Williams, 129 AD2d 84, 92-93, supra; Matter of East Clinton Developers v Department of Envtl. Conservation, supra, at 787).
Petitioner further challenges respondent’s designation of the town as lead agency and maintains that, at the very least, respondent should redesignate itself as lead agency.
This argument focuses on whether the town has a jurisdictional basis to act as lead agency. The SEQRA regulations imply that only an "involved agency” may be designated as lead agency (see, 6 NYCRR former 617.6 [d], [e]). An
For present purposes, the Tree Ordinance remains facially valid, thus confirming a jurisdictional predicate for the town’s status as lead agency. Since the town has decision-making authority, albeit not the ultimate authority to issue or deny the mining permit, and is clearly concerned with the local impact of the project (6 NYCRR former 617.6 [d] [1] [i]), we cannot say that respondent’s designation of the town as lead agency was irrational (see, Matter of Congdon v Washington County, 130 AD2d 27, 32). The ultimate conclusion to be drawn here is that petitioner has failed to establish a clear right to compel a redesignation of respondent as lead agency. It follows that the lead agency issue is not ripe for judicial review.
Judgment reversed, on the law, without costs, motion for summary judgment denied and cross motion to consolidate granted.
Appeal from order dismissed, as academic, without costs.
. We note that the SEQRA regulations contained in 6 NYCRR part 617 were amended in March 1987, but the former version pertains to the instant proceeding (6 NYCRR 617.20).
. We note that the revised regulations do provide for such a redesignation where the lead agency’s basis of jurisdiction fails (6 NYCRR 617.6 [f] [1] [ii]).