Judges: Weiss
Filed Date: 3/30/1989
Status: Precedential
Modified Date: 10/31/2024
Appeal from a judgment in favor of the State, entered September 14, 1987, upon a decision of the Court of Claims (Lowery, Jr., J.).
In February 1981, the State Department of Transportation (hereinafter DOT) accepted claimant’s bid to reconstruct a portion of Grove-Blue Mountain Lake Road, State Routes 28N and 30, in Hamilton County. The project was completed in October 1982 and final payment issued on July 18, 1983. This action was commenced by verified claim filed August 18, 1983. Claimant’s first cause of action seeks damages attributable to order-on-contract No. 1 (hereinafter OOC No. 1), by which DOT added six "undercut” areas to the project requiring additional excavation and backfill. Claimant maintained that OOC No. 1 did not fall within lump-sum contract items 619.01 (basic maintenance and protection of traffic) and 634.01 (survey and stakeout), and initially demanded $6,929.55 in compensation and $40,000 for consequential delay damage. The consequential loss demand was subsequently raised to $400,000. The second cause of action seeks loss of profits claimant ostensibly would have earned under contract item 619.15 (pavement delineation) had the State not opted to place certain temporary road markings itself. During the ensuing trial, claimant moved to amend the pleadings to conform to the proof by enhancing the damages claimed by asserting a specific claim of fraud. Ultimately, the Court of Claims denied the motion and dismissed the claim for failure to comply with State Finance Law § 145. This appeal ensued.
Initially, we find that the Court of Claims erred in dismissing the claim outright pursuant to State Finance Law § 145. This provision requires an aggrieved contractor to serve a detailed and verified statement of claim against the public entity involved within 40 days of accepting final payment; additionally, a claim founded upon such statement must be filed within six months of final payment. The statutory objective is to allow a contractor to accept final payment without waiving any contract rights, while concomitantly preserving timely notice to the State (see, Ferran Concrete Co. v Facilities
We also find that the Court of Claims properly denied claimant’s trial motion to add a new cause of action for fraud.
The question remains whether claimant established a basis for recovery. Having dismissed the claim as untimely, the Court of Claims did not make any relevant findings of fact or conclusions of law as to whether claimant sustained any damages. This court is authorized to render judgment as warranted by the facts (see, Northern Westchester Professional Park Assocs. v Town of Bedford, 60 NY2d 492, 499). Nonetheless, several pertinent questions of credibility have been presented, particularly with respect to whether OOC No. 1 constituted a qualitative change in the nature of the work or a mere quantitative change (see, Depot Constr. Corp. v State of New York, 23 AD2d 707, 709, affd 19 NY2d 109; see also, John Arborio, Inc. v State of New York, 41 Misc 2d 145, 147). Moreover, the trial exhibits have not been included in the record before us. Accordingly, we opt to remit the matter for further review by the Court of Claims (see, Matter of Commissioner of Social Servs. of County of Erie v Richardson, 112 AD2d 760, 761).
Judgment modified, on the law, without costs, by reversing so much thereof as dismissed the claim; matter remitted to the Court of Claims for further proceedings not inconsistent with this court’s decision; and, as so modified, affirmed. Mahoney, P. J., Kane, Casey, Weiss and Yesawich, Jr., JJ., concur.
We recognize that State Finance Law § 145 limits the claim to the specific items listed in the statement of claim, a restriction properly interpreted as precluding any subsequent amendments arising out of the contract (see, Kembridge Corp. v State of New York, 101 Misc 2d 904, 907-908). We do not, however, interpret this provision or the contractual release clause as precluding an amendment premised on fraud in the inducement of the contract, such as claimant posits here (see, Sabo v Delman, 3 NY2d 155). To hold otherwise would effectively authorize the State "to perpetrate a fraud with immunity” (supra, at 161; see, Jackson v State of New York, 210 App Div 115, 119-120, affd 241 NY 563; 60 NY Jur 2d, Fraud and Deceit, § 222, at 762). Thus, the court’s reliance on Kembridge Corp. in denying the instant application was misplaced.