Judges: Stein
Filed Date: 7/11/2013
Status: Precedential
Modified Date: 11/1/2024
Appeal from an order and judgment of the Supreme Court (McDonough, J.), entered December 21, 2011 in Albany County, which granted petitioners’ application pursuant to CPLR 7503 to stay arbitration between the parties.
Pursuant to a letter of intent, respondent began to perform landscaping services for petitioner Brenda DeLuca Trust in July 2005 in conjunction with the construction of a custom home. Thereafter, the parties’ agreement was reduced to a written contract that, among other things, incorporated the terms of the “General Conditions of the Contract for Construction” of the American Institute of Architects. The contract designated
We affirm. Because the arbitration process is a creature of contract, the parties may choose to make any particular contract requirement a condition precedent to arbitration or a condition in arbitration (see Matter of County of Rockland [Primiano Constr. Co.], 51 NY2d 1, 8-9 [1980]; Matter of Spencer-Van Etten Cent. School Dist. [Auchinachie & Sons], 179 AD2d 855, 856 [1992], lv denied 79 NY2d 759 [1992]; Matter of Town of Queensbury [Joseph R. Wunderlich, Inc.], 175 AD2d 946, 947-948 [1991]). Whether a condition precedent to arbitration has been satisfied is a determination to be made by the courts in the first instance (see Matter of Town of Ticonderoga [United Fedn. of Police Officers, Inc.], 15 AD3d 756, 758 [2005]; Matter of Town of Queensbury [Joseph R. Wunderlich, Inc.], 175 AD2d at 947-948).
Here, section 4.4.1 of the General Conditions of the Contract for Construction directs that claims “shall be referred initially to the Architect for decision” and that “[a]n initial decision by the Architect shall be required as a condition precedent to mediation, arbitration or litigation of all Claims between [respondent] and [the Trust] arising prior to the date final payment is due, unless 30 days have passed after the Claim has been referred to the Architect with no decision having been rendered by the Architect.” Assuming, without finding, that respondent’s November 2005 letters to the Trust and Cathell constituted a claim, it is undisputed that respondent failed to provide notice to Land Design of such claim — a condition precedent to arbitration — and we reject respondent’s contention that it was under no obligation to do so.
While the record demonstrates that Cathell had, indeed,
Inasmuch as the parties’ contract explicitly established that submission of a claim for decision by the architect was a condition precedent to arbitration and respondent failed to satisfy such condition, Supreme Court properly granted petitioner’s application to stay arbitration (see Matter of Lakeland Fire Dist. v East Area Gen. Contrs., Inc., 16 AD3d 417, 417-418 [2005]; Matter of Board of Educ. of Schenevus Cent. School Dist. [Merritt Meridian Constr. Corp.], 210 AD2d 854, 855 [1994]; Matter of Board of Educ., Longwood Cent. School Dist. v Hatzel & Buehler, 156 AD2d 684, 685 [1989], lv denied 76 NY2d 703 [1990]).
Respondent’s remaining contentions have been rendered academic by our decision or have been considered and found to be without merit.
Peters, P.J., Lahtinen and Egan Jr., JJ., concur. Ordered that the order and judgment is affirmed, without costs.
. To the extent that respondent argues in the alternative that any failure to comply with the conditions precedent to arbitration was excused because the Trust had improperly terminated the contract, we need only note that the record is devoid of any evidence of such termination, aside from respondent’s unsubstantiated assertion.
. No explanation for the lengthy delay between the genesis of the dispute and the filing of the demand for arbitration is apparent from the record.