Citation Numbers: 190 A.D.2d 36, 596 N.Y.S.2d 898, 1993 N.Y. App. Div. LEXIS 4385
Judges: Levine
Filed Date: 4/29/1993
Status: Precedential
Modified Date: 10/31/2024
OPINION OF THE COURT
In December 1989 defendant executed as surety a $5,497,000 labor and materials payment bond on behalf of its principal, BIB Construction Company, Inc. (hereinafter BIB), the general contractor on a construction project in the City of Poughkeepsie, Dutchess County, for renovation of its City Hall building. Plaintiff was a concrete supplier for Jonel Associates, Ltd., the masonry contractor on the project.
Plaintiff brought this action on the bond to recover the unpaid balance allegedly due from Jonel for 88 cubic yards of concrete delivered to the project site. Defendant’s answer interposed affirmative defenses, inter alia, that the concrete furnished by plaintiff was not in conformity with the contract specifications for the project and that plaintiff "did not comply with the condition precedent certified mail notice provisions of the bond”. After issue was joined, plaintiff moved for summary judgment. Defendant cross-moved for the same relief based upon its affirmative defense of noncompliance with the notice provision of the bond requiring 90 days’ registered or certified mail notice to any two of the owner, general contractor or surety, plaintiff having only served notice on BIB, the general contractor.
Supreme Court denied plaintiff’s motion, concluding that triable issues existed as to whether the concrete delivered on the job conformed to the design mix approved by the engineer and to the specifications. The court also denied defendant’s cross motion on the ground that plaintiff’s notice to BIB satisfied the notice requirement of State Finance Law § 137 (3), which was controlling. These cross appeals followed.
There should be an affirmance. On its appeal, defendant
Thus, by the foregoing amendment, the Legislature extended to municipal public works contracts the strong public policy underlying the original enactment of State Finance Law § 137 regarding State public projects, i.e., to provide protection to persons furnishing labor and materials on such projects by guaranteeing payment even where there is no fund or insufficient funds due the general contractor or subcontractor against which a labor or materials lien could be filed (see, Chittenden Lbr. Co. v Silberblatt & Lasker, 288 NY 396, 404; State Bank v Dan-Bar Contr. Co., 23 Misc 2d 487, 491, affd 12 AD2d 416, affd 12 NY2d 804). The remedy on the payment bond guaranteed by State Finance Law § 137 " 'is in the nature of a third-party beneficiary recovery. It is dependent neither on the existence of a lien fund or a Lien Law trust fund for its utilization or enforcement’ ” (Syracuse Supply Co. v Seaboard Sur. Co., 167 AD2d 830, quoting Tri-City Elec. Co. v People, 96 AD2d 146, 150, affd 63 NY2d 969).
Prior to the foregoing 1985 amendment to State Finance Law § 137, it was discretionary on the part of a local municipal government whether to require a payment bond and, if so, either a statutory or common-law bond (see, Triple Cities Constr. Co. v Dan-Bar Contr. Co., 285 App Div 299, 304, affd 309 NY 665). By virtue of the 1985 amendment, municipalities no longer have the option to deny persons furnishing labor and materials on local public projects the protection of State Finance Law § 137, or to provide less protection to such persons. This being so, at least as to the furnishing of labor and materials on public projects covered by State Finance
Because the furnishing of concrete for the Poughkeepsie City Hall renovation project clearly fell within the scope of State Finance Law § 137, and concededly plaintiff complied with the notice required under that section, plaintiff’s right to recover on the payment bond cannot be defeated because it failed to meet the additional notice requirement of the bond; Supreme Court therefore properly denied defendant’s motion for summary judgment based on that ground.
We also agree with Supreme Court’s conclusion that an outstanding issue of fact is presented here as to whether the concrete plaintiff delivered met the requirements of plaintiff’s contractual obligations. Hence, Supreme Court’s denial of the cross motions for summary judgment should be upheld in all respects.
Mercure, Mahoney, Casey and Harvey, JJ., concur.
Ordered that the order is affirmed, without costs.