Judges: Devine, Lahtinen, McCarthy, Rose, Stein
Filed Date: 10/23/2014
Status: Precedential
Modified Date: 10/19/2024
Appeals from two orders of the Supreme Court (Crowell, J.), entered February 28, 2012 and April 19, 2012 in Saratoga County, which, among other things, granted defendants’ motions for summary judgment dismissing the complaint.
Yasmeen Begum (hereinafter decedent)
Hussain and decedent commenced this action alleging, among other things, that defendants were obligated to replace the
We affirm. “ ‘The extent and nature of an easement must be determined by the language contained in the grant, aided where necessary by any circumstances tending to manifest the intent of the parties’ ” (Albrechta v Broome County Indus. Dev. Agency, 274 AD2d 651, 651-652 [2000], quoting Hopper v Friery, 260 AD2d 964, 966 [1999]; accord Ketchuck v Town of Owego, 72 AD3d 1173, 1174 [2010]). The easement provides in relevant part that “[t]he [g]rantee . . . may remove from within the boundaries of the permanent easement . . . any obstruction which may interfere with the access to or the installation, repairing, replacing, maintaining the use of [the] water pipe line . . . , providing that appropriate restoration or replacement is made.” A restoration provision sets forth the obligations of the grantee. Significantly, it also includes an exception in that “the actual area where the water pipe line, or appurtenances[,] are installed will not be restored as it must function for its intended purpose.”
Under the terms of the easement, defendants had the right to remove the sewer system and they were not under any obligation to replace it in the area where the water pipe was located. Defendants further met their burden of establishing that they were not required to construct a code-compliant sewer system on another portion of the property to replace the removed antiquated system that could not be lawfully used. Proof in such regard included that, among other things, the cabins were uninhabitable and had not been used as rentals for decades, the antiquated sewer system was not grandfathered, and the sewer system could not have been used because that type of system was no longer permitted. If the cabins had been properly brought up to code and made habitable, a new septic system would have been required in another location on the property and the one removed by defendants would have been of no benefit or value in such regard. Further, defendants established that the 12-unit motel used a separate sewer system that was located west of the cabins — not in the easement or where defendants did any work — and, in fact, the separate system was in an area where plaintiffs had been doing work and piling debris. Plaintiffs failed to produce proof other than speculation that
Ordered that the orders are affirmed, without costs.
. Decedent, who was a plaintiff, passed away while this appeal was pending and we granted a motion to substitute Shahyer Hussain, the administrator of decedent’s estate, as a plaintiff.
. The County assigned the easement to defendant Saratoga County Water Authority. Defendant Malcolm Pirnie, Inc. designed the water system and oversaw the project. Defendant Trinity Construction, Inc. was the general contractor on the project.