Citation Numbers: 134 A.D.3d 1507, 22 N.Y.S.3d 272
Filed Date: 12/31/2015
Status: Precedential
Modified Date: 10/19/2024
It is hereby ordered that the order so appealed from is unanimously reversed on the law without costs, the motions of defendant-appellant are granted, and the complaint and the cross claims of defendants Liverpool Central School District, Liverpool Central School District Board of Education, Natare Corporation, and Bette & Cring, LLC, formerly known as Barry, Bette & Led Duke, Inc., against it are dismissed.
Memorandum: Plaintiff Chandra M. Hewitt, by her father, and plaintiff father, individually, commenced this action seeking damages for injuries sustained by Chandra when she lacerated her wrist on strips of metal in the water collection and filtration system of a swimming pool owned and operated by defendants Liverpool Central School District and the Liverpool Central School District Board of Education (collectively, School District defendants). Plaintiffs alleged that the injuries were caused by, inter alia, the negligent design, manufacture and installation of the water collection and filtration system, and that defendant Klepper, Hahn & Hyatt, Engineers and Landscape Architect, P.C. (KHH) was liable for damages because the School District defendants had hired KHH to provide structural and mechanical engineering services during a renovation of the swimming pool. After some discovery, KHH moved for summary judgment dismissing the complaint against it pursuant to CPLR 3212 (b) and (i), and KHH moved separately pursuant to those subdivisions for summary judgment dismissing “any and all current or prospective cross claims” against it. We note that KHH did not name any specific cross claimants in that motion, but the moving papers of KHH included the answers with cross claims against it from the School District defendants, defendant Natare Corporation (Natare), and defendant Bette & Cring, LLC, formerly known as Barry, Bette & Led Duke, Inc. (Bette & Cring). Supreme Court denied KHH’s motions pursuant to CPLR 3212 (f), without prejudice to renew pursuant to CPLR 3212 (b) and (i) following additional discovery. We reverse.
We conclude with respect to both motions that KHH met its initial burden pursuant to CPLR 3212 (b) by submitting
In light of our determination, we do not address KHH’s contention that it was entitled to summary judgment pursuant to CPLR 3212 (i). Present — Scudder, P.J., Centra, Peradotto, Lindley and Valentino, JJ.