Citation Numbers: 140 A.D.3d 1605, 33 N.Y.S.3d 609
Judges: Carni, Centra, Curran, Dejoseph, Scudder
Filed Date: 6/10/2016
Status: Precedential
Modified Date: 11/1/2024
Appeal from an order of the Supreme Court, Onondaga
It is hereby ordered that the order so appealed from is unanimously affirmed without costs.
Memorandum: Plaintiff subcontractor commenced this action seeking damages for delays allegedly caused by defendants and their construction manager on a school renovation project. Insofar as relevant to this appeal, plaintiff’s amended complaint alleges a cause of action for breach of contract for nonpayment. Defendants moved for summary judgment dismissing the amended complaint on the ground, inter alia, that plaintiff’s claims are barred by the no-damages-for-delay provisions of the contract. Supreme Court granted the motion on the basis of, inter alia, the exculpatory provisions of the contract. We affirm.
It is well settled that “[a] clause which exculpates a contractee from liability to a contractor for damages resulting from delays in the performance of the latter’s work is valid and enforceable and is not contrary to public policy if the clause and the contract of which it is a part satisfy the requirements for the validity of contracts generally” (Corinno Civetta Constr. Corp. v City of New York, 67 NY2d 297, 309 [1986], rearg denied 68 NY2d 753 [1986]; see McNamee Constr. Corp. v City of New Rochelle, 60 AD3d 918, 919 [2009], lv denied 13 NY3d 715 [2010]). However, “even with such a clause, damages may be recovered for: (1) delays caused by the contractee’s bad faith or its willful, malicious, or grossly negligent conduct, (2) uncontemplated delays, (3) delays so unreasonable that they constitute an intentional abandonment of the contract by the contractee, and (4) delays resulting from the contractee’s breach of a fundamental obligation of the contract” (Corinno Civetta Constr. Corp., 67 NY2d at 309-310). Initially, we reject plaintiff’s contention that there is a material distinction between damages caused by delay and those caused by “disruption,” which plaintiff contends are not barred by the exculpatory provisions. That contention rests on nothing more than semantics, and it is clear that plaintiff’s claim is that the alleged “disruption” resulted in delayed performance of its work.
Contrary to plaintiff’s further contention, we conclude that defendants met their prima facie burden on their motion of establishing that the damages sought by plaintiff for delays in the performance of its work are barred by the no-damages-for-delay exculpatory clause of the parties’ contract (see Aurora Contrs., Inc. v West Babylon Pub. Lib., 107 AD3d 922, 923-924
We reject plaintiff’s further contention that the court erred in granting the motion without providing plaintiff the opportunity to complete discovery. Although a motion for summary judgment may be opposed on the ground “that facts essential to justify opposition may exist but cannot then be stated” (CPLR 3212 [f]), “the opposing party must make an evidentiary showing supporting this conclusion, mere speculation or conjecture being insufficient” (Pank v Village of Canajo-harie, 275 AD2d 508, 509 [2000]). Plaintiff failed to make the necessary evidentiary showing.
In light of our determination, we do not consider plaintiff’s