Citation Numbers: 34 A.D.3d 751, 826 N.Y.S.2d 340
Filed Date: 11/28/2006
Status: Precedential
Modified Date: 10/19/2024
In an action for payment of money on an instrument, brought
Ordered that the appeal from the order is dismissed; and it is further,
Ordered that the judgment is affirmed; and it is further,
Ordered that one bill of costs is awarded to the respondent.
The appeal from the intermediate order must be dismissed because the right of direct appeal therefrom terminated with the entry of judgment in the action (see Matter of Aho, 39 NY2d 241, 248 [1976]). The issues raised on the appeal from the order are brought up for review and have been considered on the appeal from the judgment (see CPLR 5501 [a] [1]).
To end a long and litigious dispute, the parties entered into an agreement containing a release and covenant not to sue (hereinafter the agreement). The agreement clearly expressed their intention that, in exchange for the payment of the sum of $90,000 in three equal installments from the defendant, PDK Labs, Inc. (hereinafter PDK), to the plaintiff, Perry D. Krape, existing litigation between the parties would be ended and that no further litigation of any kind between them would be brought. After making the first payment, PDK defaulted on the second. Krape then brought this action by means of a summons and motion for summary judgment in lieu of complaint pursuant to CPLR 3213. The Supreme Court granted the motion, and PDK appeals, arguing that the action was not “based upon an instrument for the payment of money only” (CPLR 3213) and that the covenant not to sue extended to actions to enforce the agreement itself. We disagree with both arguments.
The action was properly brought pursuant to CPLR 3213 (see Weissman v Sinorm Deli, 88 NY2d 437, 443 [1996]; J.D. Structures v Waldbaum, 282 AD2d 434 [2001]). Further, Krape established his prima facie entitlement to judgment as a matter of law by means of the agreement and proof of the failure of PDK to make payment according to its terms (see Weissman v Sinorm Deli, supra at 444; Zuckerman v City of New York, 49 NY2d 557, 562 [1980]). In opposition to the motion, PDK failed
If PDK were to prevail, Krape would be left with an illusory remedy, accrual of interest on the payments, with no means to collect it. “In construing a contract, the document must be read as a whole to determine the parties’ purpose and intent, giving a practical interpretation to the language employed so that the parties’ reasonable expectations are realized. Further, a court should not adopt an interpretation which would leave any provision without force and effect” (Snug Harbor Sq. Venture v Never Home Laundry, 252 AD2d 520, 521 [1998]; see Aivaliotis v Continental Broker-Dealer Corp., 30 AD3d 446, 447 [2006]). “Although the words [in a contract] might ‘seem to admit of a larger sense, yet they should be restrained to the particular occasion and to the particular object which the parties had in view’ ” (Hooper Assoc. v AGS Computers, 74 NY2d 487, 491 [1989], quoting Robertson v Ongley Elec. Co., 146 NY 20, 23 [1895]). In order to achieve its goal of ending the dispute and ending and precluding any litigation between the parties, PDK was required to perform its obligations under the agreement. That is the only reasonable interpretation of the words of the agreement given “the particular occasion and . . . the particular object which the parties had in view” (Hooper Assoc. v AGS Computers, supra at 491). We conclude that the covenant not to sue did not extend to actions to enforce the payments contemplated by the Agreement itself (see Snug Harbor Sq. Venture v Never Home Laundry, supra). Schmidt, J.P., Santucci, Mastro and Fisher, JJ., concur.