It is claimed, upon the part of the Board of Rapid Transit Railroad Commissioners, that the court had no power to require that certain-conditions should be complied with prior to its giving its consent to the construction of the road by confirming the report of the Supreme Court commissioners.
It is apparent, upon an inspection of the application of the Board of Rapid Transit Railroad Commissioners, that the security proposed to be taken by them is clearly inadequate to protect the city from the loss of a large part of the money it might advance towards the construction of the road in the event of the failure of the contractor to complete and equip the same.
It is suggested by the board .that the deposit by the contractor of $1,000,000 in cash or its equivalent, pursuant to the statute (which is to be returned to the contractor upon the construction and equipment of the road); the withholding of a reasonable percentage of the price of construction to be paid to the contractor only upon completion and equipment; a bond or several bonds to secure construction and equipment but not rental, the total amount of such bonds not to exceed $7,500,000; a lien upon the equipment to.be furnished by the • contractor pursuant to the statute, and, lastly, a bond.under section 34 of the Rapid Transit Act (Laws of 1891, chap. 4, as amended by Laws of 1895, chap. 519) in an amount which,
It is apparent that the bond last mentioned,. upon the basis 'suggested, would be a mere nominal bond. Assuming that the road could be constructed for $30,000,000, as estimated by the board, the aggregate rental would not much exceed $7,000,000, and as the cost of equipment would be from $7,500,000 to $12,000,000, there would be no excess of rental over the cost of equipment to make up the penalty of the bond.
In respect to the withholding of a reasonable percentage of the • price of construction until completion and equipment, we are in no way informed as to what the commissioners think would be :such reasonable percentage; and it will be apparent upon a moment’s reflection that such a system of security is the most onerous to the contractor and of the least benefit to the city, that can well be devised,’ because it is requiring the contractor to put up security in cash, when, by the giving of a proper bond, he might attain the same object by- credit. In respect to the city, the security would increase in proportion as the work progressed, and would be the .greatest when it would be least needed, namely, when the construction and equipment were completed; whereas, the city needs the greatest protection from the failure of the contractor to carry out his contract of construction in its earlier stages.
The only other question that it is necessary to consider is as to whether the amount of the bond required.by the Appellate Division is excessive. I think that it will "be seen, when we consider the obligations of the contractor, that if he, after entering upon the work, abandons the contract, $15,000,000 would be insufficient to put the city in the same position which it would have occupied had he completed the contract. The cause of such abandonment will only be for the reason that the cost of . construction is much greater than the contract price which the city is required to advance, and the only way in which the city can receive any benefit from the millions of money which it will have embarked in this enterprise, will be by the completing of the work itself — which will necessarily be at a cost to it largely exceeding the contract price, and this difference the sureties upon the bond should supply.
It is undoubtedly true that the city will be largely protected as to rents, maintenance and operation by the lien which is given to it by statute upon the equipment to be furnished by the contractor. But it is imperatively necessary that it should have adequate protection by way of security in the matter of construction and equipment.
There is no difficulty in the giving of a bond with several conditions and limited obligations. We are of opinion that the conditions of the bond should provide that $14,000,000 of the bond should be conditioned upon construction and equipment, and that $1,000,000 should be a continuing security, applicable to construction, equipment, rents, maintenance and operation; and that such bond may be executed by two or several .persons or corporations, each bound for at least $500,000 of the penalty, and justifying according to the statute.
We do not see how any adequate protection can be furnished to the city without the execution of security such as above required.
Rumset and Patterson, JJ., concurred; Ingraham, J., dissented.