Citation Numbers: 207 A.D. 426, 202 N.Y.S. 132, 1923 N.Y. App. Div. LEXIS 5974
Judges: McAvoy
Filed Date: 12/14/1923
Status: Precedential
Modified Date: 10/27/2024
The amount found in the judgment here, in a suit upon a mechanic’s lien, is claimed to have been erroneously awarded because of the plaintiff’s failure to substantially .complete the building contracted for according to the plans which were the basis of the plaintiff’s claims. The contract provided that the-plaintiff was to make certain alterations according to plans and
The walls of the building were, under the contract, to be white-. washed, yet he used in the construction of those walls brick taken from an old chimney — bricks saturated with soot — from which bricks the soot penetrated, through the whitewash. The plans 'called for iron beams, according to Mr. Cerra. These he admits he did not use. The plans called for an extension. This he admits he did not build. The binding used in the construction of the walls was lime mortar, but the filed specifications call for cement mortar. His excuse for using lime mortar was, “ Nobody stopped me.” The use of lime mortar was contrary to the contract, and if by its use plaintiff substantially performed the contract which it must have done to recover, the burden of so proving
He was to build the concrete wall of concrete blocks, but upon the giving out of blocks, he threw in pieces of wood and concrete, and in building the brick wall, running out of brick, he used concrete blocks.
Though the building was to be a garage yet the floor was so constructed that water necessarily used for washing the trucks failed to drain off and remained in pools.
The plaintiff’s attention was at once called to this fault, and Cerra sought to remedy it. He testified, “ I put on cement again, level it up with cement,” but when he saw the floor on the Saturday prior to the trial, it still failed to properly drain.
He testified: “ A. Just around where I put the cement was scratched out some pieces of cement, those patches I make, and a little drain water lay there.”
The witness Dahlem made a test as to this drainage by throwing a pail of water on the floor near one of the two catch basins. As to what he observed, he testified: “A. It [the water] went down, but of course there wasn’t perfect drainage. The floor was evidently damaged by usage and the drainage was somewhat" disturbed, but most of the water drained through the basin.”
At the very beginning water remained in pools on the floor and still did so at the end.
The plaintiff offers the explanation through its witness Cerrathat because a sink was omitted the catch basin was also omitted. The defendants, however, deny that this sink was omitted with their consent. In any event there should have been proper drainage.
These are the most striking failures of performance. Many others will be found in the testimony.
There can hardly be a difference of opinion that this testimony .shows an entire failure of substantial performance of the contract.
The proof shows that the defendants have never been allowed to put motor cars containing gasoline inside the building which they had built for the purposes of a garage.
The admitted non-compliance with the terms of the contract, especially the admission that the best of second-hand material was only partly furnished, and the testimony as to the general character of the work, show such a failure of substantial performance as to demand a dismissal of the complaint and a reversal of the judgment.
That there was no substantial compliance with the contract under which the plaintiff agreed to do the work specified therein
This failure of substantial compliance prevents plaintiff from recovering anything in this action, since it has not shown the1 cost of making the proper substitutions, nor any reason for omitting the original requirements.
We think the judgment should be reversed, with costs, and the complaint dismissed, with costs, and findings settled in accordance with this opinion.
Clarke, P. J., Dowling, Finch and Martin, JJ., concur.
Judgment reversed, with costs, and complaint dismissed, with costs. Settle order on notice.