Judges: Rumsey
Filed Date: 12/9/1898
Status: Precedential
Modified Date: 11/12/2024
The action was brought to foreclose a mechanic’s lien, filed by the plaintiff’s assignor, Frederick Robinson, against the property of the Chinese Charitable & Benevolent Association, situate in Mott street, for work done and materials furnished, pursuant to a contract for an extension and repair of buildings upon the premises. The contract was made on the 3d of August, 1896, by Frederick Robinson & Co. The price to be paid for the work was $6,870,—$3,000 payable on the performance of certain of the work, and $2,000 on the performance of certain other work, and $1,870 on the completion of the job. Upon the trial, the court found that Robinson had done the work which entitled him to the first payment of $3,000. This finding is not disputed, and the certificate called for by the contract was presented. The court further found that the plaintiff’s assignor was delayed in performing the work and furnishing the material which it was necessary for him to perform to entitle him to the second payment, because of the neglect of the defendant the Chinese Charitable & Benevolent Association to make the first payment. Whether the contractor did, in fact, perform the work necessary to entitle him to the second payment, was not actually decided by the court, although it is fairly to be inferred from the whole decision that the court concluded that that work was not performed. The court further found that Robinson failed to complete the work and furnish the materials required by the contract, and that the owners, on the 4th day of November, 1896, served on him the notice provided for in the contract, requiring him to complete the work, and that he still failed to proceed with it in accordance with the contract, and that the owners, three days after the service of the notice, proceeded with and completed the work, and furnished the materials. The court found that the owners had paid to Robinson himself $1,150 on account of the first payment; that they also had paid to certain persons $802 for material furnished to Robinson, and upon his order; that one Refrano was entitled to judgment for $751.20 for work done upon the building as a subcontractor; and that one Rosenberg was entitled to judgment for $289.52 also for work done under a subcontract with Robinson. The two persons last mentioned had filed liens upon the building. The court further found that "the owner had expended necessarily, in the completion of the building, the sum of $1,887. These several amounts were credited to the owner upon the contract price of $6,870, and the court directed a judgment against the owner for $2,004.28, with interest, and judgment was accordingly entered for that amount. From that judgment, this appeal is taken.
The first objection taken by the defendants is that the plaintiff does not prove that she is the assignee of the contract. The contract was originally made with Frederick Robinson and William
It is further complained by the defendants that the court erred in determining that the plaintiff was entitled to recover the sum of $2,004.28, or any other sum, upon this contract. It appears quite clearly from the evidence that, while Eobinson became entitled to the first payment, he never became entitled to receive any other sum according to the terms of his contract. He himself says, in a general way, that all the work was performed to entitle him to the second payment, but a careful examination of the evidence shows that he was not correct in this statement, and that the work necessary to be performed before he was entitled to the second payment was largely done upon the procurement of the owners, after Eobinson himself had abandoned the contract. But this, perhaps, is not very important, because the contract reserved to the owner the right to finish the work, and deduct the expense from the amount of the contract, in case the contractor should, upon three days’ notice in writing being given, refuse or neglect to supply a sufficiency of materials or workmen. This notice was given on the 4th of November, 1896, whereupon Eobinson at once abandoned further work upon the contract, and the completion of the work was undertaken by the owner, in pursuance of the terms of the contract.
The case was evidently tried and determined upon the theory that the owner then made an election to complete the work under the contract; ánd that being so, if the cost of the work proved to be less than the amount due to Eobinson, after deducting all payments made for him and on his account, he would be entitled to recover the amount of the difference, and to enforce the lien for that amount. Ogden v. Alexander, 140 N. Y. 356, 35 N. E. 638. Upon that theory, the owner was entitled to have allowed to him whatever he had paid to Eobinson, any sums that he paid for material in pursuance of Eobinson’s order, and whatever other sums it was necessary for him to pay to finish the work according to the contract. The court allowed him for all these items the sum of $4,880.72. In making this allowance, we think, the court
The owner claimed to be entitled to a credit of $200 as for amount.