Judges: Ingraham
Filed Date: 4/17/1903
Status: Precedential
Modified Date: 11/12/2024
The plaintiff filed a notice of a mechanic’s lien with the clerk of the city of New York for the sum of $47. This notice stated that the defendant Durando, lessee of the premises, entered into a contract with the defendants John Schubert and Conrad Link, composing the firm of Link & Schubert, for the erection of a three-story roadhouse; that the appellants entered into a contract with the plaintiff whereby the lienor agreed to erect and finish the mason work of said building to be erected on said premises, and for which the said firm of Link & Schubert agreed to pay the said lienor the sum of $1,600, to be paid as the work progressed; that, in addition to the work provided for in said contract, the lienor performed other work, in plastering a dumb waiter, which was reasonably worth the sum of $12, and which was not provided for in the specifications. It is not alleged in the notice of lien that this extra work in plastering a dumb waiter was at the request of the appellants, or was a part of their1 contract with the lessee of the premises. The plaintiff then brought this action to foreclose this $47 lien, making the owners of the property, the tenant who made the contract with the appellants, and the appellants, parties defendant.
The complaint alleges that the defendant Durando was in actual possession of the premises as lessee; that Durando made a contract with the defendants Link & Schubert for the erection of this house upon the leased premises, and thereby promised to pay to the appellants a sum of money exceeding $10,000; that the contractors performed the conditions of said contract on their part to be performed, and so far completed the same as to be entitled at the time of filing of the notice of lien by the plaintiff to receive a payment from Durando largely in excess of the amount of the plaintiff’s claim, and that there was due to the appellants from Durando a sum in excess- of the plaintiff’s claim; that the appellants entered into a contract with the plaintiff whereby the plaintiff agreed to erect and finish the mason work for
Upon the trial the plaintiff testified that he did not concrete the area and the walls between the sleepers. He offered to make an allowance of $14.35 for not concreting the area, and also an allowance for the failure to concrete between the sleepers. It seems that the cost of doing the work that plaintiff did not do was $14.35 c°r the area and $18 for the sleepers, making a total of $32.35; and that, added to the payments consisting of $1,565, makes the amount still owing by the appellants under the contract $2.65. The plaintiff testified that plastering the dumb waiter was not in the contract; that ■the studs of the partition were set by the contractors on the job; that while he was doing the work one of the defendants was there every day or two; that after the work was done he saw Schubert, one of the appellants; that Schubert wanted to' pay for the extra work under the condition that he was to make allowance for the things that he did not do; that he made the allowance, and that the appellants promised to pay him for plastering the dumb waiter; that he got no order to do the work, but his men were there, and they did not know any difference; that it had to be done in order to complete the building. Schubert, one of the appellants, testified that he never had any conversation with the plaintiff in regard to the dumb waiter; that he never promised to pay for plastering it.
It is difficult to see upon what principle the plaintiff can be entitled to recover for plastering this dumb waiter. It was either a part of the contract, or it was not. If it was a part of the contract, then plaintiff was not entitled to be paid for it as extra work. If it was not part of the contract, to make the appellants, who were contractors, liable, they must have ordered it. The work was not done by the plaintiff, but by a subcontractor, and it was done because this subcontractor supposed it was to be done; and apparently the workmen did it because it was there to be done, and they did not know
It follows that the judgment appealed from must be modified by reducing the recovery to the sum of $2.65, and, as modified, affirmed, without costs in the court below, and with costs to the appellant in. this court. All concur.