Citation Numbers: 171 A.D. 15, 156 N.Y.S. 1027, 1916 N.Y. App. Div. LEXIS 9468
Judges: Kellogg
Filed Date: 1/5/1916
Status: Precedential
Modified Date: 10/19/2024
In an action brought by the People to dissolve an insolvent corporation and distribute its assets among its creditors, the distribution is to take place first among the creditors whose
Matter of Fleet v. Yawger (205 N. Y. 135) and Matter of Empire State Surety Co. (214 id. 553), along the dividing line between a fixed and a contingent liability, show that the line is narrow but nevertheless distinct. The Fleet Case arose upon an undertaking given to secure the issuing of an attachment in an action by which the surety was to pay any judgment that might be recovered against its principal in that action. At the time of the sequestration order the action was still pending. It was held that the liability was contingent and dependent entirely upon the event of a lawsuit; that if the lawsuit resulted in the plaintiff’s favor there never could be any liability. The Empire State Surety Co. case arose upon liability indemnity policies issued to employers to indemnify them against loss resulting from liability on account of accidents to their employees, and provided that in the case of accidents the surety company would defend the action unless it settled the claim and would pay any judgment within the limits of the policy. The accident happened before the order of sequestration, but the settlement or judgment did not take place until after the order was made. The court held that the action to dissolve the company and the order of sequestration rendered it impossible for the surety company to defend the action, and resulted, in substance, in its then breach of the policy and that the claim was a present and not a contingent liability. The fact that it was unknown at that time what the amount of damages would be was immaterial. That related not to the existence of the liability but to the liquidation of the damages.
In our case the court held that the appellant’s claim was contingent within the rule of the Fleet case. The surety com
It is urged that the supplemental agreement made between Stannard, the surety companies and the museum June 2, 1908, changed this present fixed liability into a contingent liability, and that the contingency continued until after the order of sequestration was made. The museum, immediately upon Stannard’s default, notified him that according to the terms of the contract it would take possession of the premises and the scaffolding apparatus and plant and proceed to complete the work. The supplemental agreement recited the facts and provided that the museum may forthwith take possession of the materials, scaffolding and plant and use the same to complete the work; that Stannard, so long as the museum desired, will act as the superintendent of the work under its supervision, and will, if requested, assign all subcontracts to it. The surety com. panies and Stannard agree, in substance, that the museum may proceed to complete the contract, make the necessary payments therefor as stated therein, and that the payments so made by the museum shall be deemed a part of the cost of completing the contract, and that the museum shall be credited with payments already made to Stannard and for all payments made by it in completing the contract. It then- provided: “The obligation of said Museum to pay to said Stannard any excess of contract price over the cost of completing said contract as defined herein and in said contract shall remain in full force; the obligation of said Stannard and of said Surety Com
The facts as developed make it plain that at the time of the breach of the contract it was evident that the surety companies would be required to pay substantial damages. That that was the understanding is evidenced by the supplemental agreement where the surety companies agree to be bound by the expenditures made by the museum in completing the contract. By the supplemental agreement the museum intended to have its building promptly completed and the damages against the surety companies and Stannard definitely ascertained, and the surety companies intended to have a fixed and certain method by which the damages should be ascertained. It was, so far as the surety companies were concerned, a mere method of ascertaining the damages resulting from the breach of the contract. It is evident, if after Stannard’s breach all parties had agreed to have the damages fixed by arbitrators, such agreement would not have rendered the liability of the surety company contingent, although the arbitration continued until after the sequestration order. It would seem to follow that any other means adopted could not result in converting the fixed liability into a contingent one. The language of the supplemental agreement, that “ the obligation of said Stannard and of said Surety Companies to pay to said Museum any excess of such cost over the contract price shall remain in full force,” makes it clear that the fixed liability of the surety com-
In erecting the building the museum expended $2,040.86 in premiums for liability insurance indemnifying it against liability on account of accidents to its employees. The order appealed from holds such expenditure is not a part of the cost of completing the building. If the question were open, it would seem the practice of liability insurance is so general and is so commonly treated as an overhead charge upon the work that it might well be considered a part of the cost. But the museum brought an action against Stannard in the United States District Court for the Southern District of New York to recover the damages which it had sustained by reason of his breach of the contract, in which it sought to recover this item, and the court held that the premiums were paid by the museum to guard itself against the results of its own negligence and could not be charged against the cost of the work. That decision remains in full force and no appeal has been taken. It, therefore, conclusively establishes between them for all time that this item was not a part of the damages resulting from Stannard’s breach of the contract. The surety company, by its bond, is liable to make good to the museum the damages it may sustain by Stannard’s breach of the contract. If an adjustment had been made between the museum and Stannard, and the liability fixed, it seems clear that the claimant could insist that its liability is limited to the amount agreed upon. We view this j udgment as having the same effect.
The museum brought actions on the bond against some of the other surety companies in Massachusetts to recover its damages, and in such actions it was held that this item was a proper element of damage, and that decision was affirmed by the Supreme Court. The Metropolitan Surety Company and Stannard were not parties to those actions, and they cannot be held to be adjustments of the liability between Stannard and the museum. We are not precluded, therefore, from considering that the receiver may urge that the plaintiff should get no more damage from the surety company than it could get from
The order appealed from should, therefore, be modified so as to provide that the claim of the appellant as fixed by it shall share in the assets of the surety company pro rata with all other allowed claims on bonds executed by the Metropolitan Surety Company as surety, which were existing liabilities on January 6, 1909, with ten dollars costs and printing disbursements to the appellant.
All concurred; Howard, J., in result.
Order modified as per opinion and as modified affirmed, with ten dollars costs and disbursements to the appellant.