Judges: Patterson
Filed Date: 12/11/1896
Status: Precedential
Modified Date: 11/12/2024
There are two causes of action set forth in the complaint herein. On the trial the jury found in favor of the plaintiffs on the issues joined on the first cause of action only. From the judgment entered on the verdict, and from an order denying a motion for a new trial, the defendants appeal.
The controversy relates to a contract made between one Cox, the plaintiffs’ assignor, and the- defendants, for regulating, grading, draining, and improving the easterly portion of the grounds included in Yan Cortlandt Park. The contract was awarded to Cox, on a bid made by him, but the work was done by the plaintiffs, and to the full satisfaction of the commissioners of the department of public parks, expressed and certified by their engineer, as required by the contract. The whole work contracted for consisted of various items of excavation, of sewer building, of masonry, and of filling in and top soil, all the materials for which were furnished by the plaintiffs. On the trial the contest was narrowed down to the one item of the amount of material supplied for filling and top soil, and placing the same in embankment, which by the contract was to be paid for at 46 cents per cubic yard. The plaintiffs claim that they furnished and put in place 155,819 cubic yards, according to measurements asserted by them to have been made correctly and in accordance with the terms of the contract; while the engineer of the park commissioners insisted and certified that the measurements, as he finally ascertained and fixed them, showed that only 138,737 cubic yards had been furnished by the plaintiffs.
The section of the contract under which the dispute arises is as follows:
“The filling or embankment below the top soil to be placed thereon will be measured and computed from the levels taken upon the present surface of the grounds to be filled, and no allowance for settlement or shrinkage will be allowed or paid for.”
“Bidders must satisfy themselves hy personal examination of the location of the proposed work, and by such other means as they may prefer as to the accuracy of the foregoing engineer’s estimate, and shall not, at any time after the submission of an estimate, dispute or complain of such statement or estimate, nor assert that there was any misunderstanding in regard to the depth or character of the excavation to be made, or the nature or amount of the work to be done.”
And also that:
“Bidders will be required to complete the entire work to the satisfaction of the commissioners of the department of public parks, and in substantial accordance with the specifications and plans proposed.”
The plans and specifications referred to are the same plans and specifications mentioned in the contract, and the contractor stipulated in the contract that he would in every respect strictly conform to those specifications and plans, and that he would not at any time assert that there was any misunderstanding in regard to the nature, of the work, “or the nature or amount of materials to be furnished, and that it would all be done in substantial accordance with the specifications and plans therein mentioned.” Upon one of the plans (defendant’s Exhibit Mo. 2) there is a series of cross-sections drawn, showing the top and bottom lines of filling, and it is upon
Being thus narrowed down to the question of fact above referred to, it is indisputable that, from the terms of the contract, the engineer’s return and certificate, unless they can be successfully attacked, furnish conclusive evidence of the measurements in accordance with which the plaintiffs would be entitled to payment.
As was said in O’Brien v. Mayor, etc. (Cir. Ct.) 15 N. Y. Supp. 520:
“When the certificate is given, It is conclusive upon the parties. In the absence-of proof of corruption or bad faith or misconduct on the part of the person designated, or palpable mistake appearing on the face of the certificate, neither party can be allowed to prove that such designated person decided wrongfully as to the law or facts.”
Byron v. Low, 109 N. Y. 291, 16 N. E. 45; Sweet v. Morrison, 116 N. Y. 32, 22 N. E. 276; Phelan v. Mayor, etc., 119 N. Y. 86, 23 N. E. 175; Delaware & Hudson Canal Co. v. Pennsylvania Coal Co., 50 N. Y. 266.
The same ruling was made in Wyckoff v. Meyers, 44 N. Y. 143; Whiteman v. Mayor, etc., 21 Hun, 117, citing Butler v. Tucker, 24 Wend. 447, and other cases.
We have recently had occasion to consider the same question in the case of Burke v. City of New York, 7 App. Div. 128, 40 N. Y. Supp. 81, where it is said that where the question does not relate to misconstruction of the contract, but merely with respect to-the amount of work done and materials furnished, the engineer’s certificate, if made in good faith, is final, when, as in this case, it is made so by the terms of the contract. It is upon this view of the case that the plaintiffs have based their action. Recognizing it, they have alleged that the engineer in charge of the work has refused to certify properly the amount of work done thereunder, but. has made and filed “a wrong, false, and untrue certificate, and has refused, upon proper demand, to file a proper certificate,” and “that the said certificate made by the said engineer in charge of the work under said contract was false, fraudulent, untrue, and made in bad
Judgment must be reversed, and a new trial ordered, with costs to 1 he appellant to abide the event. All concur.