Judges: Guy
Filed Date: 2/15/1916
Status: Precedential
Modified Date: 11/12/2024
The complaint alleges that plaintiff between the dates therein mentioned at the special in
In the written contract pleaded by defendant there was no provision for payment as the work progressed, so that payment could not be demanded as of right until the completion of the contract. Rosen v. Bonagur, 143 1ST. T. Supp. 1059. The testimony of plaintiff’s president, 'Ansorge, if believed would have obviated any such difficulty as far as the plaintiff was concerned, for he swore that there was no assignment, that he had at no time been connected with the contracting company, that that company went out of business and he received the contract from one of its former employees and on or about April 1, 1915, brought it to the defendant, told him the plaintiff company (whose name was almost the same as the contracting company, the only difference being that the word “ lighting ” was substituted for “ gas fixture ”) had taken oyer the plant of the contracting company and that if defendant, wanted the plaintiff to deliver under the contract plaintiff was willing to do so, but that the contract did not, say anything about payments, and on the promise of the defendant to make payments as the work progressed plaintiff
It is apparent therefore from the preponderance of credible testimony that plaintiff is the assignee of the contract ihade by defendant with the Empire Gas Fixture Company and as such bound by the provisions of that contract, and that there was no consideration for the payments on account actually made by defendant.
Under the contract plaintiff was required to “ furnish and install material specified above complete in the buildings located as above, and furnish certificates from the New York Board of Fire Underwriters for each and all fixtures furnished and installed.” Although plaintiff showed that an inspector of that
It further appears that because defendant refused to make payments 'the plaintiff did not supply fixtures called for by the contract of the value of fifty-five dollars and ten cents, according to the plaintiff’s estimate, and which defendant testified it cost him seventy-seven dollars and forty cents to furnish. This default was without excuse as defendant was under no obligation to make the payment demanded.
Judgment must be reversed and new trial ordered, with thirty dollars costs to appellant to abide the event.
Bijur and Gavegan, JJ., concur.
Judgment reversed and new trial ordered, with thirty dollars costs to appellant to abide event.