Citation Numbers: 48 Misc. 380, 95 N.Y.S. 551
Judges: Scott
Filed Date: 10/15/1905
Status: Precedential
Modified Date: 11/12/2024
The lease existing between the parties to this proceeding contained the following clauses:
“Furthermore the party of the second part further covenants and agrees that he will do any and all necessary repairs in and about the premises demised at his own proper cost and expense, and that he will remove the violation now pending in the Tenement House Department against the bakery hereby leased and will comply with the orders and rules of the said Tenement House Department of the city of New York. And furthermore the said party of the second part hereby agrees to comply with any and all rules, regulations and orders of all the municipal departments of the city of New York, as far as the premises hereby leased are effected and that should he fail to begin work within fifteen days after notice of said violation or said order from the parties of the first part that then and in that event this lease shall cease and be null and void from then on.”
“ The party of the second part is to begin work at once on the violation now pending against the said building by reason of the condition of the bakery and is to repair the same to the satisfaction of the parties of the first part as well as the Tenement House Department of the city of New York, and within ninety days after date is to have the said violation pending against said building, because of the defective condition of the bakery, removed and to give notice of the removal of the said violation to the parties of the first part and the party of the second part hereby consents to permit the said parties of the first part to enter the said demised premises, and to make any alterations and repairs to said building in which said demised premises are located, should the said parties of the first part be called upon or ordered by any of the municipal departments of the city of New York to make any repairs or changes in the building itself.” The lease was executed June 4, 1905. The tenant was proceeded against as a holdover. The claim of the petitioner as set up in his petition was that on July 5, 1904, an order and notice of a violation of the tenement house department was filed against the premises; that notice of such violation was given the tenant May 15, 1905, and that
The final order must, therefore, be reversed.
Bischoff and Fitzgerald, JJ., concur. /
Final order reversed and new trial ordered, with costs to appellant to abide event.