Judges: Guy
Filed Date: 5/15/1914
Status: Precedential
Modified Date: 11/12/2024
The defendant appeals from a judgment in favor of plaintiff entered upon the verdict of a jury in an action for rent claimed to be due under the terms of a written lease entered into between plaintiff and defendant on May 25, 1905, whereby plaintiff let to defendant certain premises for the term of five years, to commence May 1,1908, and expire April 30,1913.
The complaint alleges the making of a lease ‘ ‘ at the annual rent or sum of $16,000 to be paid in equal monthly payments in advance on the first day of each and every month during said term;’.’ that defendant duly entered into possession of the said premises under said lease, and that no part of the rent which became payable under the terms of said lease on the 1st day of March, 1913, amounting to $1,333.33, had been paid.
The answer denies that ‘ ‘ the plaintiff rented and the defendant hired the premises described therein at the annual rent or sum of $16,000 to be paid in equal
The evidence shows that at the time of the fire the defendant was not in physical possession of the premises, but that it was in possession of a sub-tenant, to whom the defendant had rented the premises. The plaintiff took possession of the premises on December 28, 1912, notifying defendant that it did so for the purpose of placing them in complete repair. At the time of the fire the lease had four months and five days to run. The plaintiff finally tendered the premises to defendant as being in complete repair on February 28, 1913. The defendant rejected the tender on the ground that the premises had not been put in complete repair, and on the trial contended that, in retaining the building for two months and five days for the making of repairs, the plaintiff had failed to comply with its covenant to make such repair “ as speedily as possible.”
On the trial the plaintiff offered in evidence the lease annexed to defendant’s answer, and rested. Defendant moved to dismiss on the ground that plaintiff had failed to show the condition precedent to the recovery of rent, that the premises had been restored and put in complete repair. This motion was denied and an exception taken.
Defendant also excepted to that portion of the charge to the jury where the court said: “In your deliberations the first thing you must do when you reach the jury room is to determine whether the defendant or its sub-agents were guilty of negligence or carelessness or improper conduct in connection with the fire.” Under the.lease the burden of establishing
“ Twelfth. That the burden is cast by law upon the plaintiff to prove by a reasonable preponderance of evidence that the premises were put in complete repair and were in complete repair on the 1st day of March, 1913 (the date when they were tendered to defendant), and if the jury find that the premises had not been put in complete repair by March 1, 1913, the verdict must be for the defendant. -
“ Thirteenth'. That the burden is cast by law upon the plaintiff to prove that the repairs, if completed, were made as speedily as possible; that it appears by the uncontradicted testimony of the witnesses on behalf of the plaintiff that the fire occurred on December 26, 1912, and that the work of repairing was not commenced until January 10, 1913, some fifteen days thereafter, and that if in the judgment of the jury fifteen days was an unreasonable delay, the plaintiff failed to perform the provisions of the lease and the verdict must be for the defendant.” See Bacon v. Albany Perf. Wrapping Paper Co., 22 Misc. Rep. 592.
The refusal to charge each of these requests constituted prejudicial error.
The judgment must, therefore, be reversed, with costs, and the complaint dismissed, with costs.
Page and Whitaker, JJ., concur.
Judgment reversed, with costs, and complaint dismissed, with costs.