Citation Numbers: 39 Misc. 2d 276, 240 N.Y.S.2d 711, 1963 N.Y. Misc. LEXIS 2004
Judges: Zaleski
Filed Date: 5/23/1963
Status: Precedential
Modified Date: 10/19/2024
This is an article 78 proceeding to review and vacate the award of a contract for work to be performed in the replacement- of asphalt and bituminous shoulders on municipal highways. The petition is dismissed.
The petitioner asserts that it was the low bidder for so-called Group I Plants, but that the contract was awarded to a higher bidder in violation of section 1088 of the Public Authorities Law. Petitioner argues that of the total number of unit bids submitted by each bidder, it submitted more low bids than did the successful bidder. That may be true, but by using respondent’s method of computation petitioner was not the lowest. In awarding the contract respondent considered the quantity of the same kind of work performed in the year 1962. There was then applied the unit prices submitted by each-bidder. By that method of computation the respondent ascertained that a bidder other than petitioner was the low bidder and that the anticipated cost would be some $5,000 less than the cost if petitioner were hired; .The question then is whether the method adopted by the respondent was arbitrary in the sense that it had no reasonable basis.
Section 1088 of the Public Authorities Law requires that unless all bids are rejected in the interest of the authority “ it shall award the contract to the lowest bidder, unless the authority
Petitioner also complains that the successful bidder submitted a qualified bid because it stated that it would charge a $50 minimum at any given site. The court does not construe the bid as qualified. When making the computation the Authority simply looked back to 1962, ascertained the number of jobs costing less than $50 and arrived at a figure which was added to the total. The result still made the successful bidder lowest.
Under all the circumstances disclosed the court concludes that the Authority did not act improperly.