Citation Numbers: 65 Misc. 376
Judges: Sutherland
Filed Date: 6/15/1909
Status: Precedential
Modified Date: 11/10/2024
The defendant J. Charles Dayton contracted with the State of Hew York through the State Engineer and Surveyor to do all the work and furnish the necessary materials for the improvement of the Skaneateles-Spafford Boad Ho. 431, in the towns of Skaneateles and Spafford, Onondaga county, pursuant to chapter 115 of the I,aws of 1898, as amended by chapter 468 of the Laws of 1906. The work has been completed; and it is conceded by the Attorney-General that there is $4,067.99 due the contractor, Dayton, for the performance of said contract and for extra work. Dayton claims that the amount due him is $7,883.28. There is no contest or question as to the validity of the liens filed, or the amount due the lienors. The plaintiffs have a valid lien upon the fund for $119.86, with, interest from Hovember 4, 1908. The defendant Bishop filed a lien for $190, with interest from October 31, 1908, and thereafter assigned that lien and all his rights thereunder to the defendant James J. Hosmer, who is entitled to the avails thereof. The defendants Shultz and DeWitt have a lien for $184.79, with interest from September 23, 1908. All of these lienors furnished material to or performed labor for the defendant J. Charles Dayton in the construction of said road, and concededly there is a considerable sum due the principal contractor Dayton in excess of the liens. The contest in this case is over the right of the contractor Dayton to a money judgment against the State for the amount due him in excess of the liens. The contractor has offered evidence in support of his claim for extra work; and evidence has been offered on behalf of the State in relation thereto; the State, however, insisting throughout the trial that this court has no jurisdiction in this action to adjudicate upon
But the contractor Dayton has filed no lien. The statute permitting the filing of mechanics’ liens upon funds applicable to the payment for public improvements does not permit the contractor to file a lien. The statute, in that respect, is only for the benefit of “ a person performing work for or furnishing materials to a contractor, or his subcontractor, assignee or legal representative.”
In 1906 the Code of Civil Procedure was amended by adding to section 3402 a provision that the plaintiff in an action to foreclose a mechanic’s lien shall join as a defendant “ The state, in the same manner as a private person, when the lien is one filed against funds of the state for which public improvement is constructed. In such a case the summons must be served upon the attorney-general, who must appear in behalf of the people.” And when this action was commenced the Code also- provided (§ 3400) : “A lien for labor done or materials furnished for a public improvement may be enforced against the funds of the state or the municipal corporation for which such public improvement is constructed, to the extent prescribed in article 1 of the Lien Law, and against the contractor or sub-contractor liable for the debt, by a civil action, in the same court and in the same manner as a mechanic’s lien on real property.” And section 3403 provided that “ The court may adjust and determine the equities of all the parties to the action and the order of priority of different liens, and determine all issues raised by any defense or counterclaim in the action.”
This is a matter of statutory construction. The general policy of the Legislature has been to have all legal claims against the State which are in dispute tried by the Court of Claims, a tribunal created by law for that particular purpose and invested with ample jurisdiction in the premises. And it is axiomatic that the State cannot be sued by one of its citizens in any court, unless by express legislative enactment the State has given its consent to be thus sued. Matter of Hoople, 179 N. Y. 308. But if, by the sections of the Code quoted above, the Legislature has intended to invest the Supreme Court with jurisdiction to adjudicate the disputed claim of a contractor against the State in any action brought to foreclose a mechanic’s lien against the moneys due from the State to said contractor, no matter how far the claim of the contractor may exceed the amount necessary to satisfy the lien filed by his servant or materialman, then it is manifestly the duty of this court to pass upon the sufficiency of the evidence tendered by the contractor Dayton, and to render a judgment fixing the amount due, once for all, from the State to him.
But, in my opinion, the sections of the Code of Civil Procedure which have been 'referred to and which are now incorporated in substantially the same language in the Consolidated Lien Law (Laws of 1909, chap. 58) disclose no such intention on the part of the Legislature. The defenses and counterclaims referred to, which may be litigated in such an action, are defenses to and counterclaims against
Deane Steam Pump Co. v. Clark was before the Appellate Division of the first department on two appeals. The action was brought to foreclose a mechanic’s lien. The owner of the premises and the contractor were made defendants. The contractor had filed no lien. The trial court awarded a personal judgment against the owner for the payment of the amount claimed by the contractor in excess of the mechanics’ liens filed. On the first appeal (84 App. Div. 450) the judgment was reversed upon the ground that the contractor had not demanded in his answer a personal judgment against the owner; but, in the opinion, the right of the contractor to have such pérsonal judgment was also questioned on the ground that he had filed no lien. The contractor then moved at Special Term for leave to amend his answer by setting up in his prayer for judgment a demand for personal judgment against the owner. The Special Term granted the motion; but, on the appeal from the order permitting the amendment, the order was reversed (87 App. Div. 459), the Appellate Division then squarely holding, upon the one point upon which the appeal
In the case of Thomas v. Sahagan, 10 N. Y. Supp. 874, modified by Court of Appeals sub nomine Thomas v. Stewart, 132 N. Y. 580, the assignee of a contractor who had filed no lien was awarded by the trial court a personal judgment against the owner for a sum in excess of the liens filed by the plaintiff and others to foreclose which the action was brought. The right of the contractor to such personal judgment was upheld by the General Term; but, on appeal to the Court of Appeals, the judgment was modified, and the assignee of the contractor and the third lienor were required to stipulate that the judgment against the owner be reduced by $180, payments proved but not allowed by the trial court. It appears in the record, however, that the personal judgment recovered by the assignee amounted to only $159, so that the reduction made by the Court of Appeals more than wiped out that judgment; and the total recovery against the owner in that action, as finally allowed by the Court of Appeals, was less than the total amount of the liens which had been filed and proved. Accordingly, the case does not stand as an adjudication against the owner in favor of the contractor who had filed no lien.
And, following the authority of Deane Steam Pump Co. v. Clark and the other cases cited, we decline to pass upon the sufficiency of the evidence offered by the contractor Dayton to sustain his claim in excess of the amount required to satisfy the three liens which have been mentioned.
In Freidenrich v. Condict, 124 App. Div. 807, the trial court refused to give the defendant contractor who had filed no lien any judgment against the owner. The Appellate Division affirmed the judgment of the Special Term (holding that the court could not adjudicate that question), but added to the judgment a provision that it should not be a bar to any future action which the contractor might elect to bring, either upon his contract or for extra work. In the case at bar, this court having no jurisdiction to award a
Accordingly, findings will be made establishing the validity of the three liens in this case, and directing the payment thereof out of the moneys due the contractor" Dayton, with costs, which are allowed the plaintiff; hut no judgment will he granted the defendant Dayton in this action for any sum in excess of said liens. Costs are also allowed the defendant lienors.
Judgment accordingly.