Judges: Kelby
Filed Date: 7/1/1919
Status: Precedential
Modified Date: 11/10/2024
The action is to foreclose a lien. The defendant Conners Bros. Company on the 15th day of November, 1915, entered into a contract in writing with the New York Municipal Railway Corporation to construct concrete foundations and to erect thereon approximately two and two-tenths miles of a two-track elevated railroad structure known as section 2 of the Jamaica line, commencing at a point on Jamaica avenue, nea!r Walnut street, and running thence easterly
The plaintiff now sues on a quantum meruit after rescission, because of the alleged breach of the contract
The contract of the plaintiff with Conners Bros, provides that he will “ furnish all materials and labor and tools * * * necessary * * * for the performance * * * all the excavation, masonry work, and incidentals, as set forth in items 1 and 2 in the contract ” between the railway company and Conners Bros., and further provides it shall be done “ according to the specifications and plans set forth and referred to in said contract, and which said plans and specifications, so far as they relate to said items 1 and 2, are hereby made part of this agreement,” and again, “All necessary lines, locations and grades * * * will be furnished * * * by the engineer of the New York Municipal Railway Corporation, under whose direction and to whose satisfaction the work is to be performed.”
The main contract between the railway company and Conners Bros, provides that “ a description of the work to be done is set forth, and the requirements, provisions, and details and specifications are stated in the printed form of contract and in the drawings therein referred to;” and at page 3 of the same contract it is provided that the contractor “ shall complete the works * * * in accordance with this contract and specifications and drawings herein mentioned: * * # Provided, however, that the said drawings may from time to time be altered or modified as hereinafter provided.” There is a further provision on page 5, subdivision 7, which gives the company the right, during the progress of the work, to amplify
An inspection of these alignment plans shows that there were but few proposed changes in the curb line. The engineer of the railway, however, stated that he knew that there was going to be a substantial change in the curb line, but that he did not know whether the
44
On January 12, 1916, the date of the signing of the contract between Lewis and Conners Bros., the detailed work plan of the column foundations was completed, and these called for a new curb not shown on either the contract plans or the existing wire condition plans, and by these detailed work plans 126 of the 244 piers east of Queens boulevard were located in front of existing curb line, but actually behind a new curb line that had been established by the local authorities. The action of the local authorities narrowed the street by pushing out into the roadway the proposed curb in front of the existing curb. It is claimed by Lewis that before he entered into the written agreement between himself and Conners Bros, on January 12, 1916, he called upon Conners and stated in effect that the contract plans given him did not locate the columns with sufficient accuracy, and that he could not give Conners any price without knowing the position of the columns with respect to the curbs, and that Conners thereupon said that the columns were all behind the curbs, and that he was informed by Conners or by Mr. Lee, an employee of Conners, in the presence of Conners, that there could not be any doubt about the location of the columns, for the reason that the steel had been ordered for that form of construction which provided for the columns on the curbs, and that reference was then made to plan C2911; and plaintiff further contends that the plan showing existing wiring conditions was then produced by Mr. Lee in the presence of Conners, and that there was specifically pointed out to him the proposed columns shown on said plan, and that Lee said those showed the location of columns. This is absolutely denied by both Conners and Lee; the defendant’s contention being that the only papers given to Lewis were the contract and specifications, the contract
On January 24, 1916, and before the exercise of the right of acceptance of the option by Conners, Lewis wrote to Conners Bros, in part as follows: “ I have been giving much time during the past ten days looking into your work on Jamaica avenue, and I find that I have made you a lower price than I would have given, had I taken more time to consider it. However, I will stand by my proposal, if my understanding is correct in the following particulars based upon the information you gave me: (1) Contractor is to be paid for the width of 6 inches outside the line of excavation for each size of footing. (2) Water and gas mains will be • allowed to go through footings without change; small service pipes, gas or water, house connections, etc., to be offset around the footings. (3) All footings to be behind the curb. (4) You to turn over to me your price on cement at $1.66 a gross.”
Three days later, January 27,1916, defendant wrote to plaintiff a letter stating: “ In accordance with our option, we have executed and signed the contract between you and ourselves for the work on section 2, Jamaica Line, and are inclosing the same herewith.” This letter also stated in terms that it acknowledged “ receipt of your favor of the 24th inst. and note the various suggestions made by you.” The defendant then acquiesced to that part of plaintiff’s letter concerning payment for excavation to be made on the basis of six inches outside the lines of excavation for each size of footing, and also undertook to turn over price for cement at one dollar and sixty-six cents gross
There is no question that this letter of defendant was received by plaintiff, for it inclosed the contract and option to plaintiff. The latter then discovered that defendant had not signed the contract but only the option, and on January 28, 1916, plaintiff brought the contract to defendant, and it was then properly executed. Nothing was then said about modifying the contract to conform to the terms of plaintiff’s letter as to “ all footings to be behind the curb.” Plaintiff contends this letter was “ interpolated ” in the contract, and that he did not see it or read it until three or four weeks afterward. The contract consisted of seven typewritten pages on the letter head of the defendant; the option being on an additional page. I find nothing to support plaintiff’s claim that defendant placed his letter with the contract, so as to cause it to be overlooked by plaintiff. The letter and contents were delivered in the ordinary course of business, as the parties customarily did. Subsequently, and on February first, plaintiff received a letter from defendant, dated February first, which in express terms stated: “Will you kindly forward bond as mentioned in the contract, and referred to in letter of January 27, so that records may be complete on this matter.” This last letter was sent by plaintiff to Mr. Porter, agent of the bonding company, with request that bond be furnished. Mr. Porter, when called as a witness to corroborate plaintiff’s theory that the contract was
Under this state of facts the plaintiff has not sustained the burden of proving the contract alleged in the complaint, and I find the plaintiff’s bid was predicated on the contract of the railroad with defendant Conners Construction Company, and the drawings therein referred to and the “ drawings showing existing conditions taken from data furnished from the various city departments, gas companies, and water supply companies.” The express ground of rescission having been the placing of piers and their foundations in front of existing curbs, the plaintiff can be heard on no other ground for rescission. Littlejohn v. Shaw, 159 N. Y. 188. Nor does the evidence sustain a finding that the placing of piers in front of existing curb increased the cost of the work. The water main east of Queens boulevard was under the sidewalk area, and the piers having been moved out in the roadway, were moved away from the location of the water main. Nor is the evidence satisfactory as to increased costs on the surface.
It must, therefore, be held that defendant did not breach the contract. It follows from the above that plaintiff has not performed the contract on his part, and is liable over to defendant for the breach on the counterclaim pleaded. The measure of damages is the difference between the contract price and the fair and reasonable cost to the defendant of completing the work. I find the reasonable cost to defendant up to January, 1918, was $79,272.74, that there was paid to plaintiff in cash $3,901.50, that the reasonable value of asphalt to be done is $1,000, sidewalks to be done $400, work with relation to changed curbs to be done
Judgment accordingly.