Citation Numbers: 125 Misc. 794, 211 N.Y.S. 712, 1925 N.Y. Misc. LEXIS 1017
Judges: Hagarty
Filed Date: 7/3/1925
Status: Precedential
Modified Date: 10/18/2024
The plaintiff undertook the construction of a sewer in Corona avenue, borough of Queens, city of New York, along certain prescribed lines, pursuant to a contract made between the parties in July, 1918. The contract provided that the line of the sewer might be changed by the borough president, provided such changes did not materially affect either the character or the amount of the work or the conditions under which it was to have been performed. There was also a provision that the contract might “ be modified and changed from time to time as may previously be agreed to, in writing between the parties hereto, in a manner not materially affecting the substance thereof or increasing the contract price thereunder in order to carry out and complete more fully and perfectly the work herein agreed to be done and performed; ” that no claim should be made for additional work unless before the performance thereof it was authorized in writing by the borough president and should not exceed five per cent of the contract price, and that all claims for extra work should be made in writing to the engineer before the fifteenth day of the following month, and failing to make such claim within the time required the rights of the contractor to additional pay “ shall be deemed to have been waived and forfeited.” Concededly, there was no modification of the contract in writing; no extra work was authorized in writing; nor was a claim in writing made for the value of it. Before the commencement of the work the fine of the sewer was changed by the engineer in such manner that it materially affected the character, the amount of work to be done and the conditions under which it was to have been performed. Plaintiff disclaims that it is suing to recover the value of extra labor and materials or that it is suing upon the contract. The plaintiff in its letters to the president of the borough of Queens, dated respectively August 23,1918, and August 26,1918, protested against the change on the ground that “ it materially increases the cost of construction over the work as originally laid out and bid upon by us and calls for work not included in our contract.” There is a rule of law that “ where the municipal representative, without collusion and against the contractor’s opposition, requires the latter to do something as covered by his contract, and the question whether the thing required is embraced within the contract is fairly debatable and its deter