Judges: Mullin
Filed Date: 1/1/1867
Status: Precedential
Modified Date: 11/2/2024
It was held by the Court of Appeals, in Reed v. Randall (29 N. Y., 358,) that in cases of executory contracts for the sale and delivery of personal property, the purchaser must return, or offer to
Applying these principles to this case, it is quite clear that the defendant was not entitled to damages for any deficiency in quantity, or defect in quality, of the hoops.
The property was, by the terms of the contract, to be delivered at Carthage, and when delivered there, it was the duty of the defendant to examine it, and promptly to accept or reject it. (Chitty on Contracts, 460, &c.)
The subsequent agreement, that the hoops should be inspected, with reference to their quality, without designating any time when, place where, or person by whom, such inspection should be made, does not alter the original contract, except by relieving the defendant from inspecting at the very time of delivery. The hoops were still to be delivered at Carthage. The inspection must be held to have been intended to be made at Carthage ; and whether the inspection was to be made by a licensed inspector, or by a person acquainted with such property, is not very material, as no inspection is pretended at Carthage — at any time.
Unless the plaintiff assented to an inspection at Syracuse, (which is not found by the referee,) the acceptance at Carthage and shipment of the hoops to Syracuse without the knowledge or assent of the plaintiff, is such a retention of the property as amounts to an admission that it was accepted in satisfaction of the contract. (Chitty on Cont., 461-2.)
If it.should be held that there was not an acceptance of the hoops, so as to preclude the defendant from alleging and proving non-performance on the part of the plaintiff, I am of the opinion that there was no offer to return, within the principle of Reed v. Randall, (supra.)
When the purchaser is bound by the contract, to in
If, in this case, it had been found that there was an agreement that the property should be inspected at Syracuse, that would then be the place of performance; and if the vendor had delivered property not such as was called for by the contract, he should bear the expense of the transportation, as his own misconduct had led to the expenditure.
When, however, the property was deliverable and to be accepted or rejected at Carthage, an offer to return at Syracuse, on payment of charges, is not such an offer as the plaintiff was bound to accept.
The referee is of the opinion that the refusal to accept was so broad and unequivocal as to cure any defect in the offer. In this I cannot Concur with him. When the offer was made, the plaintiff was bound to accept or reject it. He did reject it, promptly and emphatically, and he was justified in doing so. The defendant had not yet made the offer he was bound to make in order to enable him to recover damages. Hor did he intimate that he would deliver at any other place, or upon any other terms than such as he then offered. When a
If it should be held that the defendant had done enough to entitle him to be allowed for the inferior quality of the hoops and deficiency in number, I am of the opinion that he was allowed, by the referee, for all the damages proved, on the facts found by him. It is found that only 300 bundles of the whole quantity were actually inspected; and as these were found to be but one half, or 15,000 of them answering the description called for by the contract, the referee deducted, by way of damage to the defendant, $52.50, being the value of 15,000 hoops at $3.50 per thousand. The defendant insists that it was the duty of the referee to have found, upon this evidence, that the plaintiff delivered but one half of the whole nominal quantity actually delivered. In other words, that as it was the custom to count but á few of the whole number of bundles of hoops, and from them to determine the quality of the whole quantity, and as out of 30,000 examined, only half were such as answered the contract, it followed, and the referee was bound to find, that but one half of the whole quantity delivered by the plaintiff conformed to the contract.
The plaintiff was bound by the custom at Carthage, of inspecting a part of the whole quantity, and to arrive at the quality and quantity of the whole by the average thus ascertained. Had the inspection been made at Carthage, I have no doubt the average of the bundles examined would have determined the character of the whole. But no such inspection Was then made; and an inspection of a part, made at Syracuse, would not be conclusive evidence of the quality of the whole, but would be persuasive evidence of the condition of the
But the trouble is* the inspection at Syracuse did not bind the plaintiff; and besides, it came too late. When it was made, the property had passed from the plaintiff to the defendant.
Again; it is by no means certain that either ISTutting, the inspector at Syracuse, or McCollom, confined their inspection to the hoops delivered by the plaintiff. There was room for mistake in attempting to distinguish those delivered by the plaintiff from the 127,000 sold to the defendant by other parties. At all events, the fact that there was this additional quantity on the boat, detracts very much from the weight which might otherwise be given to the inspection.
The finding of the custom of inspecting a part of the hoops delivered and averaging the residue, disposes of the point made by the appellant, that proof of such a custom was improperly rejected. While the evidence offered was rejected^ the fact proposed to be proved is found by the referee.
The plaintiff offered in evidence a contract between the parties for the sale of all the hoops manufactured by the plaintiff during the season of 1863, at $3.75. This agreement was dated April 2d, 1863. The evidence was objected to by the defendant’s counsel, but the objection was overruled, and the defendant’s counsel excepted. The plaintiff’s counsel did not disclose the object he had in view in giving this evidence; and we are therefore left to conjecture as to the reasons which induced the referee to receive it. The only pur
But, if it was not competent, it was wholly immaterial, if the defendant could not, on the case made by him, recover damages for the defective condition of the hoops.
The defendant’s counsel excepts to the finding of the referee that the price of the hoops, after deducting $53.50 for damages, was $758.30. The ground of this exception, I presume, is, that by mistake in calculation, the referee has made the price $100 too much; and this exception is therefore well taken. If it was intended by the counsel, by this exception, to assail the finding as improper in any other respect, I think it is not well taken, for the reasons already stated.
There is another exception to the amount found due
The counsel and the referee have called the deduction of $52.50, made by the referee, damages allowed for the defective quality of the hoops. But I do not perceive how it can be called damages, or an allowance to the defendant for any purpose. The plaintiff was bound to deliver 200,000 well rived ash hoops, of given dimensions. Upon inspection, after delivery of 30,000 of them, only 15,000 were found to answer the contract. The plaintiff was therefore entitled to recover for 15,000, instead of 30,000. Limiting the recovery to 15,000 was merely holding the plaintiff to the performance of his contract. The whole quantity called for by the contract not being delivered, the defendant was entitled to recoup such damages as he sustained by reason of such nondelivery; and these damages would be the difference between the contract price and the market price at the time of delivery. For this (the only damage actually sustained, by the defendant,) no allowance whatever was made. But no question was made, in regard to it, before the referee, and as a consequence, no question can be raised, upon it, on this appeal.
I am of opinion that the judgment of the referee should be reversed; unless the plaintiff shall stipulate to deduct from the same $100, as of the date of its entry. If such stipulation is given, then the judgment must be-affirmed, without costs of appeal to either party.
Judgment accordingly.
Bacon, Foster and Mullin, Justices.]