Judges: Daniels, Parker, Potter
Filed Date: 6/15/1872
Status: Precedential
Modified Date: 11/9/2024
This action was brought upon a covenant or contract made by the defendants under and in pursuance of section 6 of chapter 503 of the Laws of 1866 (vol. 1, Laws of 18C6,-p. 1110). By the terms of such contract or covenant, the defendant bound itself to pay “all damages caused to property by the making ” of the improvement provided for by that act, and assumed all such liability, and further covenanted and agreed “ to and with the people of the State of Hew York, to at all times keep and save harmless and indemnify the said people against all and any claim or claims for such damages arising or accruing to property,” as before stated.
The improvements provided for by this act consisted chiefly
This improvement was applied for through the action of the public authorities of the defendant, and at its instance the act referred to was enacted by the Legislature. Under that consideration, and in pursuance of the provisions made-by the act Itself, the defendant entered into tjie contract or covenant already referred to. And, under that act, the improvement was afterward made, and substantially in conformity to the plan proposed by the engineer of the State. In some respects the plan was slightly varied and departed from in the prosecution of the work, but by that departure the volume of water which would otherwise have entered the basin from the river was, to a corresponding extent, diminished. The -work of making the improvement was completed in the month of December, 1867. And no evidence was given showing that the work performed in making the improvement had been either unskillfully, negligently or otherwise improperly performed, or -that the material made use of was defective, or for any other reason unadapted or inappropriate to the pulpóse it was used for.
In the absence -of such evidence, it must be assumed that the material made use of was in all respects proper for the uses to which it may have been appropriated, and that the work performed was carefully, skillfully and properly done; for a failure in either of those respects is not to he presumed, in the absence of proof showing that to be the fact. (Starr v, Peek, 1 Hill, 270, 272-3.)
As no objection has been made to the validity of the statute, and it does not appear that there is any foundation for
On the part of the plaintiff, it is contended that damages within the contemplation of that act were caused to the property maintained upon the pier constructed between the basin and the river. And the present action was brought for the benefit of the owners of such property, in order to compel the defendant to make the remuneration which it is claimed it became obligatory to make by the terms of its covenant or contract. No objection is taken to the form of the action adopted for this purpose, and probably none very well could be, since it has been provided for and sanctioned by an express enactment of the legislature. (Laws of 1869, vol. 2, chap. 642, p. 1521). But this act, authorizing the action in the name of the present plaintiff, in no manner changes or enlarges the liability of the defendant. For it was provided in it, that nothing therein contained should be construed as in any way affecting the liability of the city of Albany upon its bond. Then the liability, as well as its extent therefor, still depends upon the act of 1866, and the obligation made under it by the defendant.
This obligation is in terms no broader than the statute itself, and either may, therefore, be properly considered as indicating the rule by which that liability is to be ascertained.
The damages to property, for the recovery of which this action was brought, were neither produced nor sustained during the progress of the work by which the improvement was mude. And no act performed during the progress of the
But the referee nowhere says that this injury was caused by the improvement made, otherwise than by allowing the water to enter the basin in such a volume and manner as to produce it. This increased flow in the volume of water was the design and object of the improve-
Under this rule, before a recovery can be had, the damages must appear to have been caused by the act complained of.
The reasonable construction of the terms used in the statute, prescribing the measure of the defendant’s liability, necessarily leads to this limitation of its extent; for it was simply the damage to property by making the improvement, and nothing whatever beyond that, which the defendant was required to assume and pay; and none of the damages recovered by the judgment were caused by anything done in making the improvement, for that was finished and completed in December, 1867, while the injury producing the damages was not caused until the month of January, 1869.
Under ordinary circumstances, when a lawful act is performed in a careful, skillful and proper manner, the party performing it is not liable for mere incidental consequences injuriously resulting from it to another’s property. (Radcliff v. Mayor of Brooklyn, 4 Coms., 195 ; Thomasson v. Agnew, 24 Miss., 93, 95 ; Bellinger v. N. Y. Central R. R. Co., 23 N. Y., 42, 47,48; Goodale v. Tuttle, 29 id., 459 ; Trustees of Delhi v. Youmans, 50 Barb., 316, 318-320; Brand v. Hammersmith, etc., R. R. Co., 1 Queen’s Bench Law Rep., 200.)
A qualification of the defendant’s liability, similar to that, together with the further liability for all damages caused by the improvement itself, appears to have been all that the legislature designed to render the defendant responsible for in this instance. If it is not to be restricted in that manner, their the defendant may be made responsible for all future injuries to which property may at any time hereafter become exposed, through causes affecting it, which would not have been encountered if this improvement had not been made; an extent of liability which no one could prudently be expected to incur, even for the purpose of securing the most important benefits from a yal viable public improvement. It would be
The judgment, therefore, must be reversed; and, as no recovery, under the circumstances shown to exist, can in any event be sustained, the complaint should be dismissed, with costs.