The judgment debtor is building a house at College Point as a general contractor for a third party. He claims that there is now due him $1,450. The judgment creditor herein has served upon the third party a subpoena containing
Section 36 of the Lien Law provides, in part, that funds received by an owner are trust funds to be applied to the payment of the cost of the improvement and that any owner £ £ who applies or consents to the application of such funds for any other purpose prior to paying the cost of improvement is guilty of larceny * * (Italics supplied.) There is no inhibition against applying the funds after the cost of the improvement has been paid for in response to'a lawful order of the court. The present subpeena does not require the owner to pay the funds over to anyone. It merely enjoins the owner from paying them to the judgment debtor until further order of the court. (Civ. Prac. Act, § 781.) There is, therefore, no danger of the owner’s being charged with larceny for obeying the injunctive provisions of the subpeena.
Moreover, the judgment creditor, recognizing that its judgment is subordinate to mechanics’ liens and to judgments recovered upon claims for materials furnished, labor performed or moneys advanced for the improvement of the real property (Lien Law, § 28), has consented that the owner may, with the approval of the judgment debtor, pay all proper claims of materialmen, laborers, subcontractors and others entitled to file notices of mechanics’ liens.
Under the circumstances, the motion to vacate the subpeena is denied. Submit order.