Judges: Parker
Filed Date: 12/15/1893
Status: Precedential
Modified Date: 11/12/2024
In October 1888, the plaintiff entered into a contract with the city of New York to enlarge the American Museum of Natural History, in Manhattan square. The contract provided that certain portions of the building exposed to view on the exterior should be faced with granite. Shortly thereafter, plaintiff made a contract with Pratt & Molleson to furnish, cut, set, and clean all the new granite work which plaintiff had contracted to furnish. Pratt & Molleson gave to plaintiff a bond in the penal sum of $6,000, conditioned that they would faithfully perform their contract. This they did not do. Hence this action against their surety, who assigns two grounds of defense: (1) That the bond is without consideration to support it; (2) that the plaintiff and Pratt & Molleson varied the terms of the contract.
Touching the question of the want of consideration, it appears that before the contract was made between the plaintiff and Pratt & Molleson it was agreed that, if the contract should be awarded to the latter, security for faithful performance on their part should be furnished by them. Plaintiff so testifies, and the senior member of the firm, who were the principals in the bond, conceded it. In accordance with their promise, the making of which was a condition precedent to the awarding of the contract, they presented to the plaintiff the bond in suit, which recited the making of the contract between Smith and Pratt & Molleson, and briefly described the work which Pratt & Molleson had therein covenanted to perform, and the compensation to be paid therefor; and it was conditioned that Pratt & Molleson should faithfully perform their contract, or that they should pay such sum of money as the other party to the contract should suffer by reason of a failure of performance, not exceeding $6,000. It is apparent that the parties to the contract, as well as the surety on the bond, understood that the giving of the bond was requisite in order to secure to Pratt & Molleson the contract, and that the purpose of it was to secure Smith against loss in case of a failure of performance. The letting of the contract to Pratt & Molleson on condition that they should furnish security for their faithful performance of the contract furnished a good consideration to sustain the bond given. This proposition is sufficiently supported in the reasoning of the court in Bank v. Coit, 104 N. Y. 532-536,11 N. E. 54.
The second defense is sought to be founded on that principle of the law of suretyship which gives to a substantial variation of a contract by the parties to it, without the consent of the surety, the effect of' releasing him. The contract provided that Smith should pay to Pratt & Molleson, for the work which they covenanted to perform, the sum of $30,000, “as follows: In monthly payments not to exceed eighty per cent, of the estimated value of the work performed on the building; the final payment to be made when this work is all complete, and after the expiration of thirty days, and after all
But defendant calls attention to the fact that the 80 per cent, was to be based on the estimated value, and she insists that the estimates were to be made by the architects, and that the estimates which they did make were based on'stone actually in the building; so that, assuming the construction we have given to the contract to be the true one, still, the payments were unauthorized by reason of an absence of proper estimates. The plaintiff’s contract with the city did not provide for monthly payments based on estimates, but, on the contrary, that plaintiff should not be entitled to demand payment for any portion of the work until it should be entirely completed. The agreement further provides, however, that, if the commissioners should direct, the architects, should make estimates from time to time of the value of the work performed, upon which the commissioners could make payments in their discretion, not exceeding 80 per cent., provided the value of the work certified in such estimates should amount to $20,000. But, when the plaintiff came to subcontract the granite work to Pratt & Molleson, he agreed to make monthly payments, and without reference ta the value of the work performed. Now, the estimates to which defendant refers were made by the architects under the contract between plaintiff and the city, and they were delivered to the commissioners of the department of public parks having the matter in charge. It is clear, therefore, that it .could not have been' upon such estimates that the parties intended to base monthly payments. Nowhere in the agreement between plaintiff and Pratt & Molleson is it provided, in terms, by whom the estimates should be made; but it is fair to presume, we think, that it was expected that the architects would make them. The plaintiff testifies that Mr. Berg,
“I superintended the work for Cady & Company, reporting to them. I was called up to go up to Niantic to investigate the amount of granite that might be found there, to find out for J. C. Cady & Company how much was there. * * * In reference to the work of J. B. Smith, I may have gone a dozen times. * * * I have been through the yard, and examined the amount of granite that was there, and calculated how much was there, and reported. * * * In a way, I reported it to Mr. Smith also. I did so more to govern his control with the contractors than anything else,—to urge the work, and partly in regard to payments. * * * My report to Mr. Smith was in the nature of a voucher to Mr. Smith, and in the nature of orders from J. C. Cady & Company to push the work. I made one report as to the amount of granite in the place at Niantic, and another as to the amount that was actually put in the building.”
The testimony quoted is supported by other testimony in the case, and shows that the formal estimate made by the architects, in accordance with- the contract between this plaintiff and the city, and filed with the commissioners, was only intended as a basis for the commissioners to determine what, if any, amounts should be paid to the plaintiff as the work progressed. It did not include anything except materials actually put in the structure. For the purposes of such an estimate, it was wholly unnecessary to go to Niantic, and determine the value of the stone there and the work done thereon. Such an examination and estimate was only valuable as between Smith and his subcontractors, Pratt & Molleson. It furnished a basis for the 80 per cent, payment to them, which was authorized, as we have observed, by the terms of the contract; and the estimates thus made and acted upon by both parties constitute a reasonable compliance with the provisions of the agreement. The judgment should be affirmed, with costs. All concur.