Citation Numbers: 24 Misc. 225, 52 N.Y.S. 513
Judges: Gaynor
Filed Date: 7/15/1898
Status: Precedential
Modified Date: 11/12/2024
This is a suit to foreclose a mechanic’s lien for work done and material furnished under a contract to construct a canal in from tidewater and a basin at the head of it. I find that the plaintiff substantially performed. He did not' lay the plank walk around the bulkhead of the basin because the other party to the contract prevented him. The dredging was done and the bulkhead built. The crumbling and silting in of the banks and the weakness of the bulkhead are due to the plan on which the work was Constructed, and not to any default or neglect of the plaintiff. The change from piles about twelve feet back of the bulkhead to horizontal logs sunk in the ground much farther back, for the purpose of holding the bulkhead up by means of tie rods, was found to be necessary as the work progressed, for the reason that the caving ground would not hold the piles up with the weight of the bulkhead upon them by means of the tie rods, and the change was made by mutual consent.
Many objections and exceptions to admissions of evidence were strenuously taken for the defendants. I have considered them all in determining what competent and probative evidence there is in the case. The rules of evidence of the common law courts were never adopted by and did not prevail in chancery.. All kinds of testimony was and is taken in equity suits. It was and still is in many jurisdictions the practice for the evidence' to be taken before masters or commissioners, and for them to take, everything. The chancellor or .equity judge was and is presumed to know on reflection what is competent and probative; and the question on review of his decision is whether his findings of fact are sufficiently supported by competent evidence, and substantial justice has been done. It does not matter that, incompetent evidence was received,
It was also insisted by the learned counsel for the defendants that the reason why the certificate to the completion of the work by the engineer as required by the contract was not given, could not be proved for the reason that the same was not specifically pleaded. I do not understand that any such rule of pleading survives. Under common law pleading-it was necessary for the plaintiff to particularly plead each condition precedent, and compliance therewith, or the reáson or excuse for non-compliance, such as that the defendant waived or prevented compliance; but under our system of pleading such particularity has been made unnecessary, a general allegation that the plaintiff performed on his part sufficing to enable proof to be made either of actual compliance with each condition by both parties, or that plaintiff performed by doing all that he was required to do in compliance and the defendant failed, or of excusable non-compliance (Code Civ. Pro., § 533; McManus v. Western Assurance Co., 22 Misc. Rep. 269, and authorities and case there cited.) This rule is of every day application in actions upon insurance policies, in respect of provisions thereof for notice of the fire, furnishing proofs of loss and the ascertainment of the amount of loss by agreement or by appraisal, as conditions precedent to a right of action (supra). If applicable to such conditions, why not to a provision in a building contract requiring the certificate of an architect or engineer as a condition precedent to a
Judgment for the plaintiff.