DocketNumber: No. 2007-G-2789.
Citation Numbers: 2008 Ohio 1135
Judges: TIMOTHY P. CANNON, J.
Filed Date: 3/14/2008
Status: Precedential
Modified Date: 7/6/2016
{¶ 2} Appellant commenced this action on April 17, 2006, filing a two-count complaint against appellee and Chester Township. Count one of the complaint has been satisfied and is not at issue in the instant appeal. Count two, the subject of this appeal, alleges that appellee, working either independently or as an agent of *Page 2 Chesterland Township Road Department, negligently damaged appellant's property during underground excavation located at 11946 Sandgate Drive. Appellant sought damages in the amount of $2,108.09.
{¶ 3} After appellee and Chester Township filed an answer denying the allegations, discovery ensued. Prior to trial, appellant dismissed Chester Township with regard to both counts. Chester Township was not involved with respect to count one and sufficient evidence was presented at trial that appellee was acting as an independent contractor for Chester Township with respect to count two. The trial court held a bench trial on May 30, 2007.
{¶ 4} At trial, it was established that Chester Township notified the Ohio Utilities Protection Service ("OUPS") about the planned excavation project on May 5, 2005. OUPS located the underground wires and marked them accordingly. On May 25, 2005, appellee began excavating at the Sandgate location to replace a culvert. No question exists whether appellee struck the underground lines at the Sandgate excavation site and caused the damage.
{¶ 5} At the conclusion of trial, the court entered an order in favor of appellant on count one. With respect to count two, the trial court, in its judgment entry dated June 6, 2007, stated: "[t]he credible evidence is that the location marks placed by ``OUPS' (or by those in its employ) were wrong and that defendant [appellee] was not negligent." Appellant filed a timely notice of appeal and asserts the following assignment of error:
{¶ 6} "Whether the trial court erred in its application of O.R.C.
{¶ 7} "Judgments supported by some competent, credible evidence going to all the essential elements of the case will not be reversed by a reviewing court as being against the manifest weight of the evidence."C.E. Morris Co. v. Foley Constr. Co. (1978),
{¶ 8} An excavator must ascertain whether utility lines exist below ground so damage to them may be avoided. GTE North, Inc. v. Carr (1993),
{¶ 9} "Except as otherwise provided in divisions (C), (D), (E), and (F) of this section, at least forty-eight hours but not more than ten days before commencing excavation, the excavator shall notify the protection service of the location of the excavation site and the date on which excavation is planned to commence."
{¶ 10} An excavator, as defined in R.C.
{¶ 11} "Days," as defined in R.C.
{¶ 12} In the case sub judice, Chester Township hired appellee to perform the excavation for the Sandgate project using his own equipment. Chester Township did not participate in the excavation but performed the clean-up work after the project was complete. Therefore, since appellee was excavating underground, he was responsible for contacting OUPS to determine whether any underground utility lines were present beneath the area he sought to dig so that he might avoid damaging them.
{¶ 13} Although the trial testimony reveals appellee was unaware of any statutory requirement mandating him to contact OUPS before excavating, the evidence demonstrates notification was made to OUPS by Chester Township on May 4, 2005, and excavation took place on May 25, 2005. Therefore, pursuant to R.C.
{¶ 14} Appellant argues that although the site was marked, appellee assumed the risk when he excavated the area outside the ten-day requirement as mandated by R.C.
{¶ 15} Additionally, appellant argues appellee failed to discharge his nondelegable duty to inform himself with the location of the underground utility lines. In GTE Tel. Operations v. J H Reinforcing Structural, 4th Dist. No. 01CA2808, 2002-Ohio-2553, the Fourth District Court of Appeals stated:
{¶ 16} "We find nothing in the statute's language that creates a cause of action if an excavator fails to notify OUPS. Appellant cites no authority that the statute has ever been construed in that manner and we have found nothing to that effect in our own research. To the contrary, several courts have interpreted this statute as simply one way to fulfill the excavator's common law duty to ascertain the location of the cables. See e.g. Ohio Edison Co. v. Wartko Constr. (1995),
{¶ 17} The Fourth District determined that although the excavator did not inform OUPS of its planned work and meet the exact letter of the statute, he "clearly met the spirit of the statute if not the exact letter." Id. at ¶ 14.
{¶ 18} In GTE Tel. Operations v. J H Reinforcing Structural, the excavator conducted a "preconstruction meeting" with utility companies in order to ascertain the *Page 6
location of underground lines. Id. at ¶ 11. The excavator also received affirmation from a phone company representative that he could excavate the sidewalk, as long as he did not excavate underneath the sidewalk since the lines were located underneath, rather than embedded inside the sidewalk. Id. Yet, when the excavator began his excavation of the sidewalk, he damaged lines which were encased in the cement. In rendering its decision, the Fourth District stated, "we fully agree with the trial court's conclusion to not hold appellee liable on a mere technical failure when, even if it had followed the technical legal requirements of R.C.
{¶ 19} While in the instant case appellee failed to strictly comply with R.C.
{¶ 20} Thus, after our review of the record in this case, we conclude the trial court's judgment was supported by competent, credible evidence. Therefore, appellant's sole assignment of error is without merit and the judgment of the trial court is affirmed.
*Page 1COLLEEN MARY OTOOLE, J., MARY JANE TRAPP, J., concur.