DocketNumber: No. 06CA3127.
Judges: Abele, Kline, McFarland
Filed Date: 8/15/2007
Status: Precedential
Modified Date: 11/12/2024
{¶ 1} This is an appeal from a Scioto County Common Pleas Court judgment in favor of Portco, Inc. ("Portco"), plaintiff below and appellee herein, on its claim against Eye Specialists, Inc. ("Eye Specialists"), defendant below and appellant herein.
{¶ 2} Appellant assigns the following errors for review: *Page 110
FIRST ASSIGNMENT OF ERROR:
The trial court erred by failing to credit defendant for the entire amount of the West Virginia Electric lien.
SECOND ASSIGNMENT OF ERROR:
The trial court erred in failing to award defendant damages pursuant to the contract based upon plaintiff's failure to complete the work prior to the completion date.
THIRD ASSIGNMENT OF ERROR:
The trial court erred by not ruling on defendant's counterclaim seeking damages for plaintiff's unworkmanlike performance of the contract.
{¶ 3} In July 2003, Portco agreed to renovate a former auto-arts store into a medical facility for Eye Specialists. In return, Eye Specialists promised to pay Portco $320,178. Because Eye Specialists wanted to open its Portsmouth office as soon as possible, the contract required "substantial completion" of the project no later than November 27, 2003. "Substantial completion" is defined in the contract as possession of an "occupancy permit." If the renovation was not substantially completed by that time, Portco agreed to pay a $200 per day penalty. In the end, Portco did not obtain an "occupancy permit" until several months after the targeted completion date.
{¶ 4} Portco commenced the instant proceeding and alleged that the contract had been completed, but Eye Specialists owed $31,061.13 for additional construction (change orders) that it had requested. Eye Specialists denied liability, counterclaimed for various alleged breaches of the contract, and requested in excess of $25,000 in compensatory damages.1 Portco denied any liability on the counterclaim(s).
{¶ 5} At the bench trial, parties mainly focused on the change orders and their effect on the contract. John Kendall, a carpenter and inspector, also testified that the faulty installation of a generator caused roof leaks. Kendall explained that $8,000 to $10,000 would be needed to repair the roof. Likewise, Terry Lee Shultz, the Eye Specialists clinic director, testified that he had received a $10,000 quote for roof repair.2 *Page 111
{¶ 6} The trial court concluded that the construction delays were not caused by Portco, but rather by various change orders from Eye Specialists. Further, the court determined that Portco was due and owing $17,885.13 for the additional work. This appeal followed.
{¶ 7} We proceed, out of order, to appellant's third assignment of error. Eye Specialists asserts that the trial court erred by not deciding its counterclaim concerning the leaking roof. We agree. However, rather than reverse the trial court's judgment and remand the case, for the reasons that follow, we simply dismiss the appeal for lack of jurisdiction.
{¶ 8} Ohio courts of appeals possess jurisdiction to review the final orders of inferior courts within their district. See Section
{¶ 9} Eye Specialists notes that the trial court failed to resolve the "second count" in its counterclaim that alleged that the work was not done in a workmanlike manner. During opening argument, Eye Specialists narrowed its argument under this count to the leaky roof and adduced evidence to show that roof repair will cost $8,000 to $10,000. The trial court did not rule on the counterclaim in its December 1, 2006 judgment. The trial court did, however, enter a Civ.R. 54(B) finding of "no just reason for delay," and this language would ordinarily resolve the jurisdictional issue. However, inWisintainer v. Elcen Power Strut, Co. (1993),
{¶ 10} We recognize that Wisintainer
sets forth a deferential standard and we are always reluctant to strike a Civ.R. 54(B) certification. See Oakley v. CitizensBank of Logan, Athens App. No. 04CA25,
{¶ 11} For these reasons, we believe that judicial economy and justice are better served by resolving these claims together, and we strike the Civ.R. 54(B) "no just reason for delay" finding. Therefore, we hold that the trial court's judgment is neither final nor appealable, and we lack jurisdiction at this juncture to conduct a review. Accordingly, we hereby dismiss the appeal.
Appeal dismissed.
MCFARLAND, P.J., and KLINE, J., concur.