DocketNumber: No. 8-97-26.
Citation Numbers: 710 N.E.2d 299, 126 Ohio App. 3d 251, 1998 Ohio App. LEXIS 666
Judges: Hadley, Bryant, Evans
Filed Date: 2/12/1998
Status: Precedential
Modified Date: 11/12/2024
Defendants-appellants, Danis Building Construction Company ("Danis") and the University of Dayton, appeal the judgment of the Logan County Common Pleas Court denying Danis's motion to dismiss and/or stay the proceedings pending arbitration. For the reasons that follow, we affirm the judgment of the trial court. *Page 253
In June 1995, Danis and plaintiff-appellee, Carter Steel Fabricating Company ("Carter"), entered into a contract whereby Carter agreed to supply and install steel for the construction of the Joseph E. Keller Hall School of Law on the University of Dayton campus. Danis was the general contractor for the project, an Carter was one of the subcontractors. As part of the agreement, the parties entered into an arbitration agreement.
Carter performed under the contract. The University of Dayton paid Danis for the steel. Danis, however, refuses to pay Carter $116,057 owed under the base contract.1 Carter contends that Danis refuses to pay the remaining base contract. Carter contends that Danis refuses to pay the remaining $116,057 because Danis is using that amount as a setoff allegedly owed by Carter to Kenhill Construction Company ("Kenhill").2 Kenhill is a subsidiary of Danis.
On June 9, 1997 Carter filed a complaint against Danis in the Logan County Common Pleas Court for breach of contract and for damages under R.C.
"The trial court erred in denying appellants' motion to dismiss and/or stay pending arbitration."
Danis contends that the contract between the parties contains a mandatory arbitration provision to resolve any disputes involving damages claimed by the subcontractor (Carter) against the general contractor (Danis). Carter does not dispute the existence of the arbitration provision. Rather, Carter contends that a claim for payment under the base contract is not a matter referable to arbitration under the agreement.
The contract the parties entered into in June 1995 contained a section entitled "Disputes and Settlement." The section of the agreement in dispute provides the following: *Page 254
"30.4 If any claim, dispute or other matter in question arisesbetween Danis and Subcontractor with respect to interpretationsof this Agreement, extra work or other charges in Subcontractor's Work ordered by Danis, or other disputes involving delays or damages claimed by Danis against Subcontractor or by Subcontractor against Danis, and if any such claim, dispute or other matter (i) is not [a covered dispute under] the provisions of Section 30.1 and (ii) is not resolved [within a reasonable time after a settlement meeting], but in no event later than the date of final payment, either party may file a demand forarbitration." (Emphasis added.)
The trial court found that the arbitration provision was limited in scope, and "was not intended to be used to compel payment of money due under the base contract."
"``It is the policy of the law to favor and encourage arbitration and every reasonable intendment will be indulged to give effect to such proceedings and to favor the regularity and integrity of the arbitrator's acts. * * *' Campbell v. AutomaticDie Products Co. (1954),
"If any action is brought upon any issue referable to arbitration under an agreement in writing for arbitration, the court in which the action is pending, upon being satisfied that the issue involved in the action is referable to arbitration under an agreement in writing for arbitration, shall on application of one of the parties stay the trial of the action until the arbitration of the issue has been had in accordance with the agreement * * *." (Emphasis added.)
However, this presumption for arbitration is not absolute.Stillings v. Franklin Twp. Bd. of Trustees (1994),
We must determine whether the trial court properly held that the issue in this action (complete payment under the base contract) was not referable to arbitration under the agreement between Danis and Carter.
The standard, of review for this case is the "abuse of discretion" standard. Harsco Corp. v. Crane Carrier Co. (1997),
The trial court in the present case relied on the decision ofGillen Concrete Excavating, Inc. v. Fortney Weygandt, Inc. (July 16, 1997), Lorain App. No. 96CA006525, unreported, 1997 WL 430863, to hold that the issue involved in this action was not referable to arbitration. We find the Gillen court's decision persuasive. In a situation similar to the present case, Gillen Concrete, a subcontractor, filed a complaint in common pleas court seeking performance from the general contractor's unambiguous promise to pay sums of money for work performed. The general contractor sought a stay from the court and requested the court refer the matter to arbitration. The parties' contracts provided, in essence, that arbitration would be utilized to resolve adjustments or interpretations of the contracts. The trial court, as well as the appellate court, found that Gillen Concrete's complaint seeking the unambiguous promise to pay sums of money did not fall within the scope of the contractual arbitration clause.
Upon review of the arbitration provision in the contract in the present case, we initially note that Section 30.4 is not a mandatory arbitration provision. Specifically, the provision states that "[i]f any claim, dispute or other matter in question arises between Danis and Subcontractor with respect to interpretations of this Agreement * * * either party may file a demand for arbitration." Therefore, Carter was under no obligation to submit this issue to arbitration.
Nevertheless, Danis retained the right to submit an issue to arbitration if the issue required an interpretation of the agreement between Danis and Carter. However, the unambiguous promise to pay sums of money owed to Carter does not require an interpretation of the agreement. The parties do not dispute that Carter performed under the contract or that the $116,057 is owed. Rather, Danis wants to utilize the sum owed as a setoff for amounts owed by Carter to another company. As the trial court found, Danis's failure to pay does not require an interpretation of the agreement through arbitration.
Therefore, we affirm the judgment of the Logan County Common Pleas Court denying Danis's motion to dismiss and/or stay the proceedings pending arbitration.
Judgment affirmed.
THOMAS F. BRYANT and EVANS, JJ., concur.
"Danis shall be entitled to deduct as a set-off to any money due Subcontractor any amount which Subcontractor or any of its affiliates * * * owes Danis arising out of this Project, otherprojects, or otherwise. * * *" (Emphasis added.)
N. Elec. Inc. v. Amsdell Constr., Inc., Unpublished ... , 2005 Ohio 4134 ( 2005 )
Neel v. A. Perrino Constr., Inc. , 113 N.E.3d 70 ( 2018 )
Seyfried v. O'Brien , 2017 Ohio 286 ( 2017 )
W.K. v. Farrell , 167 Ohio App. 3d 14 ( 2006 )
Gustavus, L.L.C. v. Eagle Invests. , 2012 Ohio 1433 ( 2012 )
Eagle v. Fred Martin Motor Co. , 157 Ohio App. 3d 150 ( 2004 )
Church v. Fleishour Homes, Inc. , 172 Ohio App. 3d 205 ( 2007 )